Printz Services Corp. v. Main Electric, Ltd.

949 P.2d 77, 1997 WL 183998
CourtColorado Court of Appeals
DecidedJanuary 20, 1998
Docket95CA1664, 95CA1688
StatusPublished
Cited by6 cases

This text of 949 P.2d 77 (Printz Services Corp. v. Main Electric, Ltd.) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Printz Services Corp. v. Main Electric, Ltd., 949 P.2d 77, 1997 WL 183998 (Colo. Ct. App. 1998).

Opinion

Opinion by

Judge KAPELKE.

In this mechanics’ lien foreclosure action, plaintiff, Printz Services Corp. (Contractor), and defendants Main Electric, Ltd., Sprehe Interior Construction, Inc., and Connie J. Sullivan-Brown d/b/a C.J. Masonry (Subcontractors) challenge the trial court’s determination that their mechanics’ liens are junior to deeds of trust held by defendants Joel D. Roberts and Placer Gold, Inc. (Sellers). Contractor also challenges the trial court’s ruling that receipt of payment by Southern Group, Inc., (Owner) was not a contractual condition precedent to any liability by Contractor to Subcontractors. We affirm in part, reverse in part, and reinand for further proceedings.

These consolidated cases arose from the sale and development of a property for a casino. On January 2,1992, Roberts sold the property to Placer Gold and took back a deed of trust that was recorded the same day. Placer Gold, in turn, sold the property to Owner on March 27, 1992, and received a deed of trust which was recorded on March 31, 1992. Owner later defaulted, and Placer Gold foreclosed on its deed of trust and received a public trustee’s deed in 1993.

During February and March 1992, Contractor was preparing a proposal for the development of the property into a casino. On February 25, 1992, Contractor met with an architect and requested that he prepare initial sketches showing possible designs for the building and estimating square footage resulting from each design. The architect prepared the sketches and accompanying notes the following day.

Contractor sent Owner a letter containing a guaranteed price quotation on March 24, 1992. Contractor signed a contract with the architect on March 30, 1992. The contract provided for payment of a “stipulated sum” of $500 for the work the architect had already performed. On April 1,1992, Contractor and Owner signed a general contract for the project.

Contractor entered into agreements with various subcontractors. All Subcontractors with the exception of Main Electric signed Contractor’s preprinted subcontract form, which contained the following provisions:

Contractor shall make payment on or before the 25th day of the next month following receipt of the Payment Request provided like payment has been made by Owner to Contractor.
[[Image here]]
Contractor shall make final payment to Subcontractor after work is complete and accepted by Owner and Architect provided like payment shall have been made by Owner to Contractor....

Contractor and Subcontractors filed mechanics’ liens on the property. In this foreclosure action following Owner’s default, Sellers, Contractor, and Subcontractors filed cross-motions for summary judgment on the issue of priority as between the mechanics’ liens and Sellers’ deeds of trust.

All parties agreed that the January 2, 1992, deed of trust enjoyed priority over all other claims. However, Contractor and Subcontractors argued that the mechanics’ hens hád priority over the second deed of trust by reason' of the architect’s having performed lienable work on the project before that deed of trust was recorded. The trial court granted summary judgment- in favor of Sellers, finding that any work performed before March 31, 1992, was commissioned by Contractor in connection with its preparation of its own proposal, and was not performed at the request of Owner or Sellers.

In the- first phase of a bifurcated trial, the court ruled that Subcontractors’ mechanics’ hens against the property were vahd, but junior to Sellers’ deeds of trust. The court also held that, although Main Electric had no written subcontract with Contractor, it had performed services enhancing the value of the property in the amount of $50,929.74. The court therefore determined that Main Electric had a vahd mechanic’s hen in that amount.

Following the second stage of trial, the court found in favor of Subcontractors on *80 their contract claims against Contractor. With respect to the claim of Main Electric, the court based its judgment on the theory of quantum meruit. The court rejected Contractor’s defense that the “pay when paid” clause of the subcontracts relieved it of the obligation to pay Subcontractors because it had not been paid in full by Owner. The court ruled that the contract language was not sufficiently clear to make payment by Owner to Contractor a condition precedent to Contractor’s obligation to pay Subcontractors, or to shift the burden of the risk of Owner’s nonpayment from Contractor to Subcontractors.

I.

Contractor and Subcontractors contend that the trial court erred in according priority to Sellers’ March 31, 1992, deed of trust over the mechanics’ liens. We disagree.

Section 38-22-106(1), C.R.S. (1982 Repl. Vol 16A) provides, in pertinent part:

All liens established by virtue of this article shall relate back to the time of the commencement of work under the contract between the owner and the first contractor, or, if said contract is not in writing, then such liens shall relate back to and take effect as of the time of the commencement of the work upon the structure or improvement ....

The statute presupposes the existence of either a written or oral agreement between the first contractor and the owner or lessee in order for a lien to attach. See Bankers Trust Co. v. El Paso Pre-Cast Co., 192 Colo. 468, 560 P.2d 457 (1977) (“first contractor” status depends on which contractor first entered into an express or implied contract with owner); C & W Electric, Inc. v. Casa Dorado Corp., 34 Colo.App. 117, 523 P.2d 137 (1974) (work not performed “at the instance of the owner” could not support a mechanic’s lien); General Growth Development Corp. v. A & P Steel, Inc., 678 F.Supp. 243 (D.Colo.1988) (priority dated from the time owner informed contractor it had been awarded the contract).

Here, Contractor and Subcontractors base their claims of priority on architectural work performed in late February 1992, well before Owner executed its written contract with Contractor on April 1, 1992, and well before March 24, 1992, the date Contractor claimed he received an oral “go ahead” from Owner. The undisputed facts in the record establish that the architect did not begin his work at the instance of Owner or a lessee, but rather solely at the request of Contractor.

Contractor and Subcontractors argue that even though the architect’s work predates the prime contract with Owner, because such a contract was eventually signed, the mechanics’ liens relate back to the date work was first commenced by the architect. We disagree.

In C & W Electric, supra, a subcontractor performed a substantial portion of its work on a modular home before the owner purchased the home and moved it to his property. The subcontractor performed the remainder of the work on the home after its purchase.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Goodwin v. Chambers
D. Colorado, 2024
Ward Petroleum v. Kent
Colorado Court of Appeals, 2022
Ferguson Enterprises, Inc. v. Keybuild Solutions, Inc.
275 P.3d 741 (Colorado Court of Appeals, 2011)
Main Electric, Ltd. v. Printz Services Corp.
980 P.2d 522 (Supreme Court of Colorado, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
949 P.2d 77, 1997 WL 183998, Counsel Stack Legal Research, https://law.counselstack.com/opinion/printz-services-corp-v-main-electric-ltd-coloctapp-1998.