Main Electric, Ltd. v. Printz Services Corp.

980 P.2d 522, 1999 Colo. J. C.A.R. 1353, 1999 Colo. LEXIS 235, 1999 WL 138785
CourtSupreme Court of Colorado
DecidedMarch 15, 1999
Docket97SC601
StatusPublished
Cited by32 cases

This text of 980 P.2d 522 (Main Electric, Ltd. v. Printz Services Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Main Electric, Ltd. v. Printz Services Corp., 980 P.2d 522, 1999 Colo. J. C.A.R. 1353, 1999 Colo. LEXIS 235, 1999 WL 138785 (Colo. 1999).

Opinion

BENDER, Justice.

In this case we interpret the payment provisions of a construction contract to -require a general contractor to pay a subcontractor even though the owner has failed to pay the general contractor. This provision is referred to as a “pay-when-paid” clause. We hold that the “when” of this clause is not a contingency, but rather means that payinent may be delayed. We decline to find that this clause is a “pay-if-paid” clause that excuses the general contractor’s obligation to the subcontractor if the owner does not pay.

In Printz Services Corp. v. Main Electric, Ltd., 949 P.2d 77 (Colo.App.1997), the court of appeals held that the relevant language in the construction contract between the general contractor and a subcontractor was a pay-if-paid clause which barred the subcontractor from receiving payment from the general contractor because the owner became insolvent and never paid the general contractor. We reverse on this issue. We construe the *524 relevant payment phrase in this contract, that the subcontractor would be paid “provided like payment shall have been made by owner to contractor,” to be insufficient to constitute a condition precedent that results in shifting the risk of the owner’s nonpayment from the general contractor to the subcontractor. We hold that in order to create a condition precedent, the language of the parties’ agreement must clearly express their intent that the subcontractor is to be paid only if the owner first pays the general contractor. Thus, we hold that the payment clause in this contract constitutes a pay-when-paid clause - that is, an unconditional promise by the general contractor to pay its subcontractor even if the owner becomes insolvent.

As part of this case, a second subcontractor sought to recover from the same general contractor based upon an implied oral contract. We agree with the analysis of the court of appeals that the second subcontractor’s claim is not ripe for appellate review because the trial court did not make findings of fact concerning the terms, if any, of the payment clause of their oral agreement. Hence, with respect to the court of appeals’ opinion, we reverse in part and affirm in part and return this case to that court with directions to remand this case to the trial court for further proceedings consistent with this opinion.

I.

Facts and Proceedings Below

Respondent Printz Services Corporation was the general contractor on a casino construction project in Cripple Creek, Colorado. Petitioners C.J. Masonry and Main Electric were subcontractors on the project. The relationship between Printz and C.J. Masonry was governed by a preprinted form contract prepared by Printz, the general contractor. The form contains the following pertinent payment provisions:

3.SUBCONTRACT AMOUNT. In consideration of the faithful performance of the covenants and agreements herein, ... Contractor agrees to pay, or cause to be paid, Subcontractor ... at the times and in the manner following in Articles 4 and 5.
4. PROGRESS PAYMENTS.
[[Image here]]
D. Contractor shall make payment on or before the 25th day of the next month following receipt of the Payment Request provided like payment has been made by Owner to Contractor.
[[Image here]]
5. FINAL PAYMENT. Contractor shall make final payment to Subcontractor after work is complete and accepted by Owner and Architect provided like payment shall have been made by Owner to Contractor....

Main Electric did not sign a written form contract but agreed orally to work for Printz.

Before the project was complete, the owner became insolvent and lost the property in a deed of trust foreclosure. The owner failed to pay Printz, and Printz in turn failed to pay its subcontractors. C.J. Masonry and Main Electric both sought payment for breach of contract against the general contractor. Printz claimed in defense that it was obligated to pay its subcontractors only if it was first paid by the owner.

The trial court interpreted the payment clause “provided like payment shall have been made by Owner to Contractor” in C.J. Masonry’s contract to be a promise by Printz to pay the subcontractor when and not if the general contractor was paid by the owner. In the trial court’s view, the general contractor remained unconditionally obligated to pay the subcontractor provided the work was performed. The trial court ruled that Printz must pay C.J. Masonry regardless of the owner’s insolvency.

Concerning Main Electric’s claim, the trial court found that although Printz and Main Electric did not execute a written agreement, Main Electric had performed valuable services for Printz. Ruling that an implied contract existed between the two, the court awarded damages to the subcontractor under a quantum meruit theory.

The court of appeals reversed the trial court on both subcontractors’ claims. See Printz Servs. Corp., 949 P.2d at 79. It held *525 that the contract between Printz and C.J. Masonry created a condition precedent rather than a promise to pay, relying substantially on language in Orman v. Ryan, 25 Colo. 383, 55 P. 168 (1897), in which a similarly worded clause in a construction contract was referred to as a condition precedent. See id. at 388, 55 P. at 170. Thus, the court of appeals ruled Printz was not obligated to pay C.J. Masonry. See Printz Serus. Corp., 949 P.2d at 81-82.

Turning to Main Electric’s claim, the court of appeals reasoned that since both parties conceded that they had an express oral agreement, an award based on a theory of quantum meruit was inappropriate. The court noted that ordinarily the distinction between enforcement of an oral contract and a quantum meruit award would make no substantive difference and would not require remand. However, because the parties disputed whether the payment clause formed part of their express oral agreement, and since the trial court did not resolve this disputed fact, remand to the trial court was appropriate.

We granted certiorari to determine whether the holding in Orman controls this case and whether the relevant contract provisions between the general contractor and the subcontractor should be interpreted as creating a condition precedent. 1

II.

Orman Does Not Govern Our Analysis

Because the parties and the court of appeals rely so heavily upon Orman, we first examine that case in some detail. In Orman, the subcontractor agreed to perform trestle work on a railroad construction project with the knowledge that the railroad company had no assets, and only by selling its own bonds could the railroad company finance the construction. See Orman, 25 Colo, at 388, 55 P. at 170.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peo v. Huntley
Colorado Court of Appeals, 2025
Goodwin v. Chambers
D. Colorado, 2024
Ward Petroleum v. Kent
Colorado Court of Appeals, 2022
Yen, LLC v. Jefferson County Board of Commissioners
2021 COA 107 (Colorado Court of Appeals, 2021)
v. Thomas
2020 COA 19 (Colorado Court of Appeals, 2020)
v. Quezada-Caro
2019 COA 155 (Colorado Court of Appeals, 2019)
People v. Miller
409 P.3d 667 (Supreme Court of Colorado, 2017)
Sinclair Transportation Co. v. Sandberg
2014 COA 76M (Colorado Court of Appeals, 2014)
Ferguson Enterprises, Inc. v. Keybuild Solutions, Inc.
275 P.3d 741 (Colorado Court of Appeals, 2011)
Evans, Mechwart, Hambleton & Tilton, Inc. v. Triad Architects, Ltd.
965 N.E.2d 1007 (Ohio Court of Appeals, 2011)
Paredes v. Air-Serv Corp., Inc.
251 P.3d 1239 (Colorado Court of Appeals, 2010)
People v. Riley
240 P.3d 334 (Colorado Court of Appeals, 2009)
USAA v. Parker
200 P.3d 350 (Supreme Court of Colorado, 2009)
Parker v. USAA
216 P.3d 7 (Colorado Court of Appeals, 2007)
Union Carbide Corp. v. Industrial Claim Appeals Office of the State
128 P.3d 319 (Colorado Court of Appeals, 2005)
Berg v. Industrial Claim Appeals Office of the State
128 P.3d 270 (Colorado Court of Appeals, 2005)
Seefried v. Hummel
148 P.3d 184 (Colorado Court of Appeals, 2005)
Dinnerware Plus Holdings, Inc. v. Silverthorne Factory Stores, LLC
128 P.3d 245 (Colorado Court of Appeals, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
980 P.2d 522, 1999 Colo. J. C.A.R. 1353, 1999 Colo. LEXIS 235, 1999 WL 138785, Counsel Stack Legal Research, https://law.counselstack.com/opinion/main-electric-ltd-v-printz-services-corp-colo-1999.