Bushman Construction Co. v. Conner

307 F.2d 888
CourtCourt of Appeals for the Tenth Circuit
DecidedAugust 28, 1962
DocketNo. 6931
StatusPublished
Cited by19 cases

This text of 307 F.2d 888 (Bushman Construction Co. v. Conner) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bushman Construction Co. v. Conner, 307 F.2d 888 (10th Cir. 1962).

Opinion

PICKETT, Circuit Judge.

This action by Bushman Construction Company arose out of the failure of the defendant R. P. R. Construction Company, a subcontractor on a military housing project at the United States [890]*890Air Force Academy, Colorado Springs, Colorado, to deliver, pursuant to a written direction of proceeds, money due to one of its subcontractors. Bushman appeals from a summary judgment in favor of R. P. R.

The record, consisting of the complaint, affidavits, depositions, and evidence introduced in support of an application for an injunction, discloses that R. P. R., by subcontract, agreed to perform a portion of the prime contract requirements in the construction of the housing project at the Air Force Academy. In turn, R. P. R. negotiated with the defendant Conner to do a portion of its work. These parties reached an agreement, and R. P. R. delivered to Conner a letter of intent to award him a portion of its work for a consideration of $2,184,600. Because Conner needed financial assistance, and was unable to furnish the required performance and payment bonds, the letter of intent was presented to Bushman, and, after considerable discussion, a participating arrangement was worked out between Conner and Bushman. In substance, this agreement required Bushman to pay all bills necessary to complete the work, establish a drawing account of $1,000 per month for Conner, and furnish the necessary bonds. Conner agreed to assign all payments to Bushman, and the profits were to be equally divided. On May 22, 1958, Conner delivered the bonds to R. P. R., which were guaranteed by Bushman, and the subcontract involved here was executed.1 On June 3, 1958, the joint adventure arrangement was reduced to writing.2

Prior to the execution of the written agreement between Conner and Bushman, Conner furnished to R. P. R. an irrevocable direction for the payment of proceeds which provided that all money due to Conner under the subcontract should be forwarded to the Mechanics Bank, St. Joseph, Missouri.3 In addition to the direction for the payment of [891]*891proceeds, Conner executed his power attorney authorizing an officer of the Mechanics Bank to endorse the checks so forwarded and credit the proceeds to Bushman’s account. As security for the performance of Conner’s subcontract, Bushman’s name and credit were used. It paid costs of operation in excess of $1,900,000, and received from R. P. R. $1,463,780.05 in accordance with the procedure outlined. of

The record indicates that early in August, 1959 Bushman and Conner had a disagreement. Bushman, having advanced approximately one-half million dollars more than it had received, refused to furnish more money for the subcontract until additional progress payments were made by R. P. R. Conner thereupon undertook to terminate the joint adventure and revoke the authority of the officer of the Mechanics Bank to endorse checks. He advised R. P. R. that in the future all checks should bear the personal endorsement of W. S. Conner, and gave notice to R. P. R. that the direction to deliver the proceeds due on the contract to the bank was withdrawn. It is alleged that R. P. R., acting in cooperation with Conner, and with full knowledge of Bushman’s interest, stopped payment on a $150,000 check which had been delivered to the bank, endorsed and deposited according to the preexisting agreement. Thereafter R. P. R. refused to make further payments to Bushman, and later payments were made directly to Conner or jointly to him and others. It is also alleged that disbursements were made by R. P. R. to Conner during the pend-ency of this action, “and with full knowledge of the contentions of Plaintiff.”

In the first amended complaint Bushman alleges, in its first claim for relief, that there was a breach of Subcontract No. 581 by R. P. R. and a breach of a specific promise to pay Bushman $150,000 made to induce Bushman’s continued participation, and it asks for recovery of the balance due on the subcontract as damages. In its second claim for relief recovery is sought on quantum meruit. The allegation is that certain sums were paid for the use and benefit of R. P. R. and Conner, and the relief prayed for is the reasonable value of the services rendered by Bushman or, alternatively, for restitution of the amounts paid on behalf of the defendants. In the third claim for relief Bushman alleges a conspiracy between R. P. R. and Conner to deprive it of the benefit of the joint adventure and defraud it of amounts previously expended. The allegations in this claim for relief could be construed as alleging a scheme to defraud Bushman by inducing it to advance funds for the performance of the subcontract with the intent to stop payments to Bushman after it had advanced substantially more than had been paid to it.4 Apparently R. P. R. takes the position that it knew [892]*892nothing of the Bushman-Conner arrangement and owed no duty to Bushman.

In granting the motion for summary judgment the trial court held that the “Direction of Proceeds” was an unambiguous instrument, complete on its face, which could not be altered or explained by parol evidence. The court also held that the instrument was not an assignment, and that there was no contractual relationship between R. P. R. and Bushman.5 The effect of the court’s conclusion is that Bushman could not sue on a claim for relief for breach of Subcontract No. 581, and that since no express contract existed, no contract could be implied between R. P. R. and Bushman. As to the third claim for relief, which was not mentioned by the defendant in its motion, the court dismissed it on the theory that no cause of action would lie for conspiracy to breach a contract which did not exist.

Rule 56(c), Fed.R.Civ.P., 28 U.S.C.A., provides that a motion for summary judgment should be granted “if the pleadings, depositions, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Standards for the application of this rule have been thoroughly developed by this court. E. g., Atkinson v. Jory, 10 Cir., 292 F.2d 169; United States v. Kansas Gas & Elec. Co., 10 Cir., 287 F.2d 601; McCollar v. Euler, 10 Cir., 286 F.2d 327; Champlin v. Oklahoma Furniture Mfg. Co., 10 Cir., 269 F.2d 918, 74 A.L.R.2d 978; Alaniz v. United States, 10 Cir., 257 F.2d 108; James v. Honaker Drilling, Inc., 10 Cir., 254 F.2d 702; Zampos v. United States Smelting, Ref. and Mining Co., 10 Cir., 206 F.2d 171.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Filho v. Rodriguez
36 P.3d 199 (Colorado Court of Appeals, 2001)
TIWARI
19 I. & N. Dec. 875 (Board of Immigration Appeals, 1989)
Frackowiak v. Farmers Ins. Co., Inc.
411 F. Supp. 1309 (D. Kansas, 1976)
Taylor v. Nichols
409 F. Supp. 927 (D. Kansas, 1976)
McCullough Tool Co. v. Well Surveys, Inc.
395 F.2d 230 (Tenth Circuit, 1968)
Maryland Casualty Company v. W. S. Conner
382 F.2d 13 (Tenth Circuit, 1967)
Maryland Casualty Co. v. Conner
382 F.2d 13 (Tenth Circuit, 1967)
Smoot v. Chicago, Rock Island & Pacific Railroad
378 F.2d 879 (Tenth Circuit, 1967)
Bushman Construction Co. v. Conner
351 F.2d 681 (Tenth Circuit, 1965)
Riera v. Riera
87 P.R. 537 (Supreme Court of Puerto Rico, 1963)
Mercado Riera v. Mercado Riera
87 P.R. Dec. 566 (Supreme Court of Puerto Rico, 1963)
Bushman Construction Company v. W. S. Conner
307 F.2d 888 (Tenth Circuit, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
307 F.2d 888, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bushman-construction-co-v-conner-ca10-1962.