Richardson Engineering Co. v. International Business MacHines Corp.

554 F. Supp. 467, 1981 U.S. Dist. LEXIS 10156
CourtDistrict Court, D. Vermont
DecidedNovember 24, 1981
DocketCiv. A. 81-91
StatusPublished
Cited by11 cases

This text of 554 F. Supp. 467 (Richardson Engineering Co. v. International Business MacHines Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Richardson Engineering Co. v. International Business MacHines Corp., 554 F. Supp. 467, 1981 U.S. Dist. LEXIS 10156 (D. Vt. 1981).

Opinion

OPINION AND ORDER

COFFRIN, District Judge.

Plaintiff Richardson Engineering Company (Richardson), a New Jersey corporation, has filed a seven count complaint against defendant International Business Machines Corporation (IBM), a New York corporation. The William L. Crow Construction Company (Crow) contracted with defendant to construct a manufacturing building in Essex Junction, Vermont. Under a 9.2 million dollar subcontract with Crow, plaintiff agreed to perform plumbing, heating, and other piping work in this building. Plaintiff alleges that, although it performed its work diligently and in a workmanlike manner, defendant prevented plaintiff from completing its obligations under the subcontract. Plaintiff suggests that IBM induced Crow to terminate its subcontract with plaintiff in order to avoid paying plaintiff for extra and changed work. In counts I-VI, plaintiff seeks recovery under several contract law theories and in count VII requests enforcement of a mechanic’s lien on defendant’s property.

Defendant has moved under Fed.R.Civ.P. 12(b)(3) to dismiss counts I-VI for improper venue. It has moved under Fed.R.Civ.P. 12(b)(6) to dismiss count VII for failure to state a claim upon which relief can be granted. Since the court has considered affidavits and other materials submitted along with the pleadings, we will treat these as motions for summary judgment under Fed.R.Civ.P. 56. For the reasons set out below, we grant defendant summary judgment.

I. Venue

The first paragraph on the first page of plaintiff’s subcontract with Crow says that the subcontractor shall be bound by all terms of the general contract between IBM and Crow. 1 Paragraph 11.4 of the general contract provides: “The parties hereby agree that the proper venue of any lawsuit arising out of this contract or in connection with the work based on a claim by the Contractor, shall be the Supreme Court of the State of New York, County of Westchester.” Relying on this choice of forum clause, defendant seeks to dismiss counts I-VI for improper venue.

It is now generally accepted that a choice of forum agreement of contracting parties controls absent a strong showing that it should be set aside. Historically, courts disfavored choice of forum clauses as attempts to oust jurisdiction. See Annot., 56 A.L. R.2d 300 (1957). Courts eventually abandoned this legal fiction and resolved to enforce choice of forum clauses that appeared in international maritime agreements. See The Bremen v. Zapata Offshore Co., 407 U.S. 1, 92 S.Ct. 1907, 32 L.Ed.2d 513 (1972); *469 Win. H. Muller & Co. v. Swedish American Line Ltd., 224 F.2d 806 (2d Cir.), cert. denied, 350 U.S. 903, 76 S.Ct. 182, 100 L.Ed. 793 (1955). 2 Numerous courts have extended the rationale of these admiralty cases to civil actions in contract and tort. E.g., Hoffman v. National Equipment Rental, Ltd., 643 F.2d 987 (4th Cir.1981); Furbee v. Vantage Press, Inc., 464 F.2d 835 (D.C.Cir.1972); Central Contracting Co. v. Maryland Casualty Co., 367 F.2d 341 (3d Cir.1966); Hoes of America, Inc. v. Hoes, 493 F.Supp. 1205 (C.D.Ill.1979); Full-Sight Contact Lens Corp. v. Soft Lenses, Inc., 466 F.Supp. 71 (S.D.N.Y.1978); Cruise v. Castleton, Inc., 449 F.Supp. 564 (S.D.N.Y.1978).

In Bremen, the Supreme Court set forth several factors a court should consider in determining whether to enforce a forum selection clause. Forum clauses are “prima facie valid.” 407 U.S. at 10, 92 S.Ct. at 1913. Thus, a forum clause must be specifically enforced unless the party resisting its application can “clearly show that enforcement would be unreasonable and unjust, or that the clause was invalid for such reasons as fraud or overreaching.” Id. at 15, 92 S.Ct. at 1916. “A contractual choice-of-forum clause should be held unenforceable if enforcement would contravene a strong public policy of the forum in which suit is brought, whether declared by statute or by judicial decision.” Id. The Bremen court also allowed that in rare cases, where the remoteness of the forum might suggest that the agreement was an adhesive one, a forum clause might be unenforceable if the chosen forum were “seriously inconvenient” for the trial of the action. Id. at 16, 92 S.Ct. at 1916 (emphasis in original). 3

Plaintiff suggests that the forum selection clause in the IBM-Crow general contract should not be enforced because plain-

tiff did not freely consent to it. Although the first paragraph of the subcontract says that the subcontractor will be bound by the terms of the general contract, plaintiff asserts that it did not read or even see the general contract until after it signed the subcontract. Plaintiff now relies on its unfamiliarity with the general contract in an effort to characterize the subcontract as a contract of adhesion. Plaintiff, an experienced and sophisticated business entity, cannot complain of overweening bargaining power. In an affidavit attached to plaintiff’s motion for a writ of attachment, plaintiff’s president asserted that plaintiff is one of the fifty largest mechanical contractors in the United States and that it successfully completed the largest mechanical contract ever undertaken in its home state of New Jersey. Plaintiff therefore was surely aware of the virtual ubiquity of forum selection clauses in large construction contracts. If plaintiff had felt a need for an unfettered choice of forum for any possible litigation, it defies reason to believe that plaintiff would not have specifically raised the subject in negotiating a nine million dollar subcontract. We conclude, therefore, that the clause is not invalid by reason of overreaching.

The chosen forum — Westchester County, New York — is an eminently convenient locus for trial of this action. Plaintiff is based in New Brunswick, New Jersey and no longer has a location in Vermont. Defendant has its headquarters in Westchester County. Crow has its offices in New York City. Most potential witnesses apparently reside in the New York area. Plaintiff does not mention any inconveniences that might result from a trial in New York.

*470 As in Bremen,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mid-Am Builders, Inc. v. Federated Mutual Insurance
194 F. Supp. 2d 822 (C.D. Illinois, 2002)
Farmers Ins. Co. of Idaho v. Talbot
987 P.2d 1043 (Idaho Supreme Court, 1999)
Chase Commercial Corp. v. Barton
571 A.2d 682 (Supreme Court of Vermont, 1990)
Paul v. International Precious Metals Corp.
613 F. Supp. 174 (S.D. Mississippi, 1985)
Benge v. Software Galeria, Inc.
608 F. Supp. 601 (E.D. Missouri, 1985)
Furry v. First National Monetary Corp.
602 F. Supp. 6 (W.D. Oklahoma, 1984)
Crewe Tractor & Equipment Co. v. Deutz Corp.
574 F. Supp. 139 (E.D. Virginia, 1983)
D'Antuono v. CCH Computax Systems, Inc.
570 F. Supp. 708 (D. Rhode Island, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
554 F. Supp. 467, 1981 U.S. Dist. LEXIS 10156, Counsel Stack Legal Research, https://law.counselstack.com/opinion/richardson-engineering-co-v-international-business-machines-corp-vtd-1981.