Charles Simkin & Sons, Inc., a Corporation of the State of New Jersey, in 13,423 v. Frederick Massiah, in 13,422, and City of Trenton

289 F.2d 26, 1961 U.S. App. LEXIS 4827
CourtCourt of Appeals for the Third Circuit
DecidedApril 13, 1961
Docket13423_1
StatusPublished
Cited by21 cases

This text of 289 F.2d 26 (Charles Simkin & Sons, Inc., a Corporation of the State of New Jersey, in 13,423 v. Frederick Massiah, in 13,422, and City of Trenton) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Charles Simkin & Sons, Inc., a Corporation of the State of New Jersey, in 13,423 v. Frederick Massiah, in 13,422, and City of Trenton, 289 F.2d 26, 1961 U.S. App. LEXIS 4827 (3d Cir. 1961).

Opinion

McLAUGHLIN, Circuit Judge.

The first of these two appeals denied plaintiff’s (Simkin’s) application for an interlocutory injunction to compel defendant (Massiah) to withdraw a lien claim filed by him. The second denied defendant’s application for an interlocutory injunction against plaintiff’s continued possession and use of defendant’s equipment and tools. Both arise out of the following facts.

In April 1959, plaintiff entered into a contract with the City of Trenton, New Jersey, for the construction of a Sewage Treatment Plant at Duck Island, Tren *27 ton. Pursuant to the requirements of N.J.S.A. 2A:44-143 and 144, plaintiff provided performance and payment bonds with sureties in the amount of $3,752,-714.00. These bonds were conditioned as prescribed by N.J.S.A. 2A:44-144, and were in the required form of N.J.S.A. 2A:44-147.

Plaintiff, by written agreement, subcontracted the concrete work to the defendant. During the course of performance of the subcontract, various disputes arose between the parties, and on June 10, 1960, the plaintiff gave notice of termination for the alleged default of .the defendant. On July 12, 1960, defendant filed with the City of Trenton, a notice of lien claim in the amount of $413,110.-60. On July 13, 1960, the plaintiff took possession of defendant’s tools and equipment and assumed performance of the concrete work.

Ten days later, plaintiff instituted an action in the Superior Court of New Jersey and inter alia secured an order directing the defendant to show cause why the defendant should not “ * * * waive and release the Notice of Lien Claim * * * ” and why the City of Trenton should not be directed to refrain from withholding payments otherwise due plaintiff under the contract. Upon the requisite showing, the defendant removed the case to the Federal District Court. Defendant filed an answer and counterclaimed for sums allegedly due under the contract, breach of contract, conversion of the tools and equipment and injunctive relief against the plaintiff’s continued use and possession of them. Thereafter, plaintiff secured an Order to Show Cause asking for the same injunctive relief that was originally sought in the New Jersey Superior Court. Defendant moved by similar proceedings to obtain possession of the tools and equipment seized and used by the plaintiff. The District Court denied both petitions.

I.

Plaintiff’s right to have the defendant’s notice of lien claim removed is based on the waiver provision in the subcontract which reads:

“22. The Subcontractor hereby waives and releases any and all liens or right of lien under any applicable State or Federal law which he now has or may hereafter have against any fund, building, structure and land in connection with which labor shall be performed and materials furnished under this Contract, and further, expressly agrees not to file or place on record any Mechanic’s notice of intention, stop notice or lien claim of any kind against any such fund, building, structure and land.”

The terms of this clause are clear. It is a waiver by the defendant of any right to assert or file “ * * * any and all liens or right of lien under any applicable State or Federal law * * (Emphasis .supplied). The defendant voluntarily agreed to the waiver and is bound by its terms. Under New Jersey law such provisions are valid and enforceable. Mitchell v. Wrightstown Community Apartments, Inc., App.Div. 1949, 4 N.J.Super. 321, 67 A.2d 203; City Hall Building & Loan Ass’n of Newark, N. J. v. Florence Realty Company, Ch.1932, 110 N.J.Eq. 12, 158 A. 506. And this is true though the person seeking to invoke the waiver is the party in default. Mitchell v. Wrightstown Community Apartments, Inc., supra. In the Mitchell case, supra, the plaintiff urged the proposition that if the defendant breached the contract, the defendant could not assert the contractual waiver of lien. The court unequivocally held to the contrary, stating at page 325 of 4 N.J.Super., at page 205 of 67 A.2d:

“The plaintiff contends that the defendant’s breach of the contract, as alleged in the complaint and quoted above, estops the defendants to deny plaintiff’s right to a lien. In support of this novel proposition, no authorities are cited and certainly plaintiff does not show a situation within the usual definition of estop *28 pel. Pom.Eq.Jur. § 805. The lien of the contractor comes into play only upon the owner’s breach of the contract, for if the owner pays the contractor what falls due from time to time, the lien is unimportant. The waiver of the lien means that, in case the owner fails to pay, the contractor will assert no lien on the land but will rely upon the owner’s general credit. Clearly, the defendants’ failure or refusal to pay does not es-top them from, asserting the waiver of the lien.” (Emphasis supplied).

The holding in Mitchell is applicable to the Simkin suit. Regardless of which party is found to have breached the contract at the trial that will follow, the plaintiff is entitled to enforce, and the defendant is bound by, the contractual waiver of lien.

The district court as one of its reasons for denying plaintiff’s petition stated [186 F.Supp. 233]:

“ * * * N.J.S.A. 2A:44-130 expressly provides that the funds to which a lien has attached may be released and paid to the contractor by the municipality upon the filing with the latter of a bond in double the sum of all claims filed under the provisions of the statute against the contract or the funds due or to grow due thereunder, and conditioned for the payment of such sums as may be adjudged to be due under such claims.”

To follow this course, the plaintiff would be required to post a bond of $826,-221.20. This would be over and above the $3,752,714.00 performance and payment bond already posted. The performance bond is guaranteed by two surety companies and is specifically designed to insure payment of “ * * * all lawful claims of subcontractors, materialmen, laborers, persons, firms or corporations for labor performed or materials * * * furnished, used or consumed in the carrying forward, performing or completing of said contract * * N.J.S.A. 2A :44-147. In addition, the plaintiff has posted a lien bond of $218,000.00, which was necessary because of the defendant’s failure to pay his materialmen and suppliers. On the other hand, the defendant has advanced no valid reason for sustaining his contention that the lien claim should be allowed to remain filed. In view of these most substantial assurances of payment already in existence, equitable considerations do not warrant placing this additional burden on the plaintiff.

As a second reason for denying plaintiff’s petition, the district court stated [186 F.Supp. 233]:

“No proof has been presented to me excluding the possibility that Massiah may have a right to assert some lien against the funds in the possession of the municipality upon some of the items of his lien claim, despite the waiver of lien set forth in the subcontract between him and the plaintiff.”

We disagree.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gruntal & Co., Inc. v. Steinberg
843 F. Supp. 1 (D. New Jersey, 1994)
Apollo Technologies Corp. v. Centrosphere Industrial Corp.
805 F. Supp. 1157 (D. New Jersey, 1992)
Oxford House-Evergreen v. City of Plainfield
769 F. Supp. 1329 (D. New Jersey, 1991)
Western Elec. Co., Inc. v. Milgo Electronic Corp.
450 F. Supp. 835 (S.D. Florida, 1978)
AMERICAN AIR FILTER COMPANY, INC. v. McNichol
361 F. Supp. 908 (E.D. Pennsylvania, 1973)
Supermarket Films, Inc. v. Sylvania Electric Products, Inc.
321 F. Supp. 855 (W.D. Pennsylvania, 1971)
Babcock v. Local Board No. 5
321 F. Supp. 1017 (D. Delaware, 1970)
Radio Hanover, Inc. v. United Utilities, Inc.
273 F. Supp. 709 (M.D. Pennsylvania, 1967)
Kontes Glass Co. v. Lab Glass, Inc.
250 F. Supp. 193 (D. New Jersey, 1966)
Lawrence Warehouse Co. v. Rudio Lumber Co.
405 P.2d 634 (Idaho Supreme Court, 1965)
Gantt v. Clemson Agricultural College of South Carolina
208 F. Supp. 416 (W.D. South Carolina, 1962)
Bateman v. Ford Motor Co.
204 F. Supp. 357 (E.D. Pennsylvania, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
289 F.2d 26, 1961 U.S. App. LEXIS 4827, Counsel Stack Legal Research, https://law.counselstack.com/opinion/charles-simkin-sons-inc-a-corporation-of-the-state-of-new-jersey-in-ca3-1961.