Bushman Construction Co. v. Conner

260 F. Supp. 779, 1966 U.S. Dist. LEXIS 7970
CourtDistrict Court, D. Colorado
DecidedNovember 21, 1966
DocketCiv. A. No. 6743
StatusPublished
Cited by2 cases

This text of 260 F. Supp. 779 (Bushman Construction Co. v. Conner) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bushman Construction Co. v. Conner, 260 F. Supp. 779, 1966 U.S. Dist. LEXIS 7970 (D. Colo. 1966).

Opinion

MEMORANDUM OPINION FINDINGS OF FACT AND CONCLUSIONS OF LAW

CHILSON, District Judge.

Since the decision of the United States Court of Appeals, Tenth Circuit, in Bushman Construction Company v. Air Force Academy Housing, Inc. et al., 327 F.2d 481, there remains for disposition in this case the claim of the plaintiff against W. S. Conner and the Maryland Casualty Company. Plaintiff’s claim is based on an assignment of a claim of the Harrison Engineering and Construction Corporation against Conner. After the Circuit Court’s decision, an amended complaint was filed relating only to this claim.

Conner has not answered the amended complaint; he did not participate in the Pre-trial Conference, which was held March 4, 1966, and he has failed to appear by local counsel as required by the Local Rules of this Court and as specifically Ordered in the Pre-trial Order entered April 29, 1966. Accordingly, the default of the defendant Conner has been entered.

Maryland answered the amended complaint and on October 31, 1966, trial was had to the Court without a jury. The Court heard the evidence and argument of counsel and took the matter under advisement.

The principal issues to be determined are:

1. Was the defendant Conner indebted to Harrison Engineering Company for the use of its equipment by Conner in performing a subcontract on certain Capehart Housing projects at the Air Force Academy near Colorado Springs, Colorado ?

2. If so, is Maryland liable to the plaintiff for Conner’s debt as surety on the payment bond executed by the prime contractors as principals?

FINDINGS OF FACT

Dell Webb Construction Company and the Rubenstein Construction Company as joint venturers were the prime contractors in a contract to construct several Armed Services housing projects (referred to as “Capehart Projects”) at the Air Force Academy near Colorado Springs.

This was a multimillion dollar contract. The prime contractor performed a portion of the work (the cement and carpentry work) and subcontracted the balance to R.P.R. Construction Company. R.P.R., in turn, subcontracted its portion of the work to various subcontractors, one of which was the defendant Conner. The prime contractors were aware that R.P.R. intended to perform its subcontract by subcontracting to others. Conner’s subcontract involved a substantial part of the work (in excess of Two Million Dollars).

In performing the subcontract, Conner used some equipment of the Harrison Engineering Company and agreed to pay rental therefor at the going rate at the time and place of use. The rental, computed at the going rate together with the cost of the transportation of the equipment is the sum of $25,125.00.

In accordance with the provision of the Capehart Act, 42 U.S.C.A. § 1594(a), the prime contractor, as principal, and the defendant Maryland Casualty Company, as surety, executed a “payment bond”, which is in evidence as Exhibit One. The bond provides in its essential parts as follows:

“NOW, THEREFORE, the condition of this obligation is such that if the Principal shall promptly make pay[781]*781ment to all claimants as hereinafter defined for all labor and material furnished in the prosecution of the work provided for in the Contract, then this obligation shall be null and void; otherwise, it shall remain in full force and effect. A claimant, as hereinafter defined, shall have a direct right of action hereunder against the Surety, subject to the following conditions:
“1. A claimant is defined as one having a direct contract with the Principal or with a subcontractor of the Principal who has furnished labor, material, or both, in the prosecution of the work provided for in the Contract and who has not been paid in full therefor. Labor and material are construed to include, but are not limited to, that part of water, gas, power, light, heat, oil, gasoline, telephone service or rental of equipment directly applicable to the Contract.”

The Court concludes that plaintiff is entitled to judgment against Conner for the sum of $25,125.00 together with interest thereon at the rate of six percent per annum from December 8, 1959 (the date plaintiff acquired the Harrison claim) and for its costs.

OPINION RE: LIABILITY OF MARYLAND

Maryland makes two contentions as a basis for its claim of nonliability. The first is that since the United States Court of Appeals, Tenth Circuit, in Bushman Construction Company v. Air Force Academy Housing, Inc., 327 F.2d 481, held the principals on the bond were not personally liable to the plaintiff, therefore, the surety is not liable.

It is clear from a reading of the bond that Maryland’s obligation extends to all claimants furnishing materials and labor irrespective of whether or not the principals are personally liable to the claimants. The Court concludes the first contention is not valid.

This leads us to Maryland’s second contention, which is that Harrison and its assignee, the plaintiff, are not “claimants” within the meaning of the bond and, therefore, are not beneficiaries of the bond. Maryland points to the provision of the bond which states, “Claimant is defined as one having a direct contract with the principal or with a subcontractor of the principal.” Admittedly, Harrison had no direct contract with the principals. There remains the question of the construction to be given to the words “subcontractor of the principal.” Maryland contends that these words should be construed to mean only those subcontractors having a direct subcontract with the principals and not those who subcontract from a subcontractor. Or to put it another way, Maryland contends the words “a subcontractor of the principal” mean in this case only the first tier subcontractor, R.P.R. and does not include Conner who admittedly is a second tier subcontractor. If this construction is adopted, Harrison and its assignee, the plaintiff, are not entitled to the benefits of the bond and plaintiff cannot recover from Maryland.

We have found no case law construing a Capehart bond in the respects here involved and counsel have cited none.

In determining the construction to be given to the bond, we should properly consider the reason why the bond was required. The 1956 Amendment to the Capehart Act (42 U.S.C.A. § 1594) provides that any contract for the construction of a Capehart project “ * * * shall provide for the furnishing by the contractor of a performance bond and a payment bond * * * and the furnishing of such bonds shall be deemed a sufficient compliance with the provisions of section 270a of Title 40 * * *” Section 270a of Title 40 is a part of the Miller Act. Although the term “payment bond” is not defined in Section 1594, the reference to the Miller Act clearly indicates that Congress had in mind a “payment bond” of the kind provided for in that Act.

The Miller Act states that the payment bond required is “for the protection of all persons supplying labor and material in the prosecution of the work * * * ” [782]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maryland Casualty Company v. W. S. Conner
382 F.2d 13 (Tenth Circuit, 1967)
Maryland Casualty Co. v. Conner
382 F.2d 13 (Tenth Circuit, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
260 F. Supp. 779, 1966 U.S. Dist. LEXIS 7970, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bushman-construction-co-v-conner-cod-1966.