Steele & Lebby v. Flynn-Sullivan Co.

54 S.W.2d 325, 245 Ky. 772, 1932 Ky. LEXIS 676
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedNovember 11, 1932
StatusPublished
Cited by18 cases

This text of 54 S.W.2d 325 (Steele & Lebby v. Flynn-Sullivan Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Steele & Lebby v. Flynn-Sullivan Co., 54 S.W.2d 325, 245 Ky. 772, 1932 Ky. LEXIS 676 (Ky. 1932).

Opinion

Opinion op the Court by

Judge Thomas —

Reversing.

Tbe appellants and defendants below, James A. Steele and Thomas D. Lebby, are partners doing business under the firm name of “Steele & Lebby.” Tbe appellee and plaintiff below, Flynn-Sullivan Company, is a corporation, under tbe laws of West Virginia. It recovered a judgment in tbe Floyd circuit court against defendants for $2,414.40 with interest and costs, and for tbe enforcement of a materialman’s lien on a fund due to defendants by Floyd county to secure it, and defendants prosecute this, appeal therefrom. There are two questions involved: (1) Whether under tbe disclosed facts defendants were personally liable for tbe amount of tbe claim recovered by tbe judgment, and (2) whether tbe claim was and is a lienable one under our Mechanics’ and Materialmen’s Lien Statute (Ky. St. sec. 2463 et seq.)?

Tbe facts are these: Floyd county entered into a contract with defendants Steele & Lebby to construct, according to specifications, two bridges in tbe city of Prestonsburg, across Big Sandy river, a part of which work was the making of a passway under tbe tracks of tbe Chesapeake & Ohio Railway Company. Tbe contract was entered into on October 3, 1928, and tbe amount agreed to be paid defendants for tbe work was $159,791. Following the letting of the contract and on the same day, tbe contractors sublet to C. Y. Ligón, designated and prescribed portions of tbe work at so much per unit, i. e., for lineal feet of piling, dimensions of concrete work done, cubic yards of dirt and material removed, etc., but tbe work included in tbe sub-contract was confined to specified portions of tbe entire job. Both tbe contractor and sub-contractor immediately began preparations for tbe prosecution of tbe work and to assemble material, tools, and equipment for that purpose. At that time there was a partnership in Charleston, W. Va., composed of J. T. Flynn and W. C. Stalnaker, who were doing business under tbe firm name of Acme-Crane Service Company. A part of tbe busi *774 ness in which it was engaged was the renting of cranes to contractors in the prosecution of work similar to that involved in this case, the crane being employed to lift, move, load, and unload heavy material as well as the operation of a shovel in moving dirt, stone, etc., and also as a pile driver, each of which classes of work was performed by different attachments adaptable for the purpose.

Following the obtention of his subcontract, Ligón appeared in the office of the Acme-Crane Service Company in Charleston, W. Ya.,and entered into a contract with it whereby it rented to him a crane to be shipped to Prestonsburg, and to be employed by him in the work of performing his subcontract, and he thereafter used it for that purpose until his death, which occurred on December 18, 1928; the use of the crane having commenced the latter part of the preceding October or the first part of November. Ligoij was murdered, and at the time of his death he had performed only about 10 per cent, of the work necessary to complete his undertaking. Defendants, as the contractors of the entire job, waited several days to ascertain whether the estate or representatives of Ligón would carry out his contract, the result of which was that they entirely withdrew from the undertaking and abandoned it, and thereby made default. Some of the excavations he had commenced before his death were-only partially completed and which would be destroyed by the winter overflows of the river, and to prevent that being done it was absolutely necessary for the work to be finished before the floods came. Therefore, Steele & Lebby took charge thereof, and in doing so they paid for some material, and, perhaps, for some minor equipments that Ligón had procured for the purpose of fulfilling his contract.

Immediately following the death of Ligón, and after defendants had taken over his work, Flynn appeared upon the scene and defendants inquired of him if his firm would permit them to use the crane in finishing the immediate piece of work to which it was adjusted at the time of Ligón’s death, and he declined to do so, unless defendants would assume and pay the amount due under Ligón’s rental contract of the crane,, and which was and is the amount sued for and recovered by the' judgment appealed from, and which included freight and other minor items in. addition to the rent, but which were embraced in Ligón’s rental contract. *775 Defendants declined to assume that account, and tbe Acme Company loaded tbe crane in tbe cars and shipped it to their home office at Charleston, W. Ya. Later, and within the time prescribed by law, it filed and perfected a materialman’s lien for the amount of its account against Ligón, and following that it assigned and- transferred all of its interest therein to the newly formed corporation of Flynn-Sullivan Company, the plaintiff and appellee herein.

The latter filed this action in the Floyd circuit court against Steele & Lebby, Floyd county, its fiscal court, and the members thereof, to recover the claim so assigned to it and to enforce the lien by impounding and subjecting a sufficient amount of the funds due to Steele & Lebby for that purpose, with the result already stated ; and which brings us to a discussion of the questions above recited.

But preliminary thereto a question is raised by attorney for defendants which should, perhaps, first be disposed of. It is, that finder -the doctrine announced in the case of Frailey v. Winchester & B. R. Co., 96 Ky. 570, 29 S. W. 446, 16 Ky Law Rep. 645, plaintiff, corporation, as assignee of the claim may not assert the lien contended for, since it did not personally furnish the appliance, the rental value of which forms the claim sued on. The inapplicability of the Frailey opinion is made manifest by the fact that the assignor of' the claim there involved had not perfected the lien at the time of the assignment therein, nor was it ever done by the assignor. In this case the Acme Company, who leased or let the crane to Ligón, completed its lien before the assignment thereof to plaintiff, and that assignment carried with it, not only the claim itself, but also the securities for its payment that had been legally acquired at that time. We will now take up and dispose of the two questions supra.

1. The first is one purely of fact, since the personal judgment rendered against defendants was improper, unless they in some manner were in privity with Ligón’s agreement to pay, or unless they in some manner became personally obligated .to pay it. The endeavor is made throughout the preparation of the case to fasten personal liability on appellants for the payment of the claim upon the theory that Ligón was their agent in performing the work that he undertook to *776 do in Ms subcontract. But that effort was a most dismal failure, since the rent contract between defendants and Ligón, and the one between the latter and the Acme Company, clearly demonstrate that Ligón was a subcontractor and that the Acme Company under which plaintiffs acquired title to the claim contracted with and exclusively looked to him for payment, notwithstanding its members, at the time of entering into the written rental contract, knew that the original contractors were Steele & Lebby.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southeastern Steel Erectors, Inc. v. Inco, Inc.
424 S.E.2d 433 (Court of Appeals of North Carolina, 1993)
Dirt & Rock Rentals, Inc. v. Irwin & Powell Construction, Inc.
838 S.W.2d 412 (Court of Appeals of Kentucky, 1992)
D. H. Overmyer Warehouse Co. v. W. C. Caye & Co.
157 S.E.2d 68 (Court of Appeals of Georgia, 1967)
Traylor Bros. v. Indiana Equipment Co.
336 S.W.2d 590 (Court of Appeals of Kentucky, 1960)
In re Heat 'N' Eat Brands, Inc.
174 F. Supp. 598 (W.D. Kentucky, 1959)
City of Ashland v. Ben Williamson & Co.
171 S.W.2d 968 (Court of Appeals of Kentucky (pre-1976), 1943)
Southern Exchange Bank v. American Surety Co. of New York
144 S.W.2d 203 (Court of Appeals of Kentucky (pre-1976), 1940)
Bond v. W. T. Congleton Co.
129 S.W.2d 570 (Court of Appeals of Kentucky (pre-1976), 1939)
Bank of Earlsboro v. J. E. Crosbie, Inc.
1938 OK 48 (Supreme Court of Oklahoma, 1938)
Thew Shovel Co. v. Massachusetts Bonding & Insurance
88 S.W.2d 960 (Court of Appeals of Kentucky (pre-1976), 1935)
Massachusetts Bonding & Insurance v. C. B. Duff & Co.
87 S.W.2d 363 (Court of Appeals of Kentucky (pre-1976), 1935)
Marion Steam Shovel Co. v. Union Indemnity Co.
75 S.W.2d 541 (Court of Appeals of Kentucky (pre-1976), 1934)
Century Indemnity Co. v. Shunk Manufacturing Co.
68 S.W.2d 772 (Court of Appeals of Kentucky (pre-1976), 1934)
Steel Lebby v. Horn
61 S.W.2d 623 (Court of Appeals of Kentucky (pre-1976), 1933)
Union Indemnity Co. v. Pennsylvania Boiler Works
55 S.W.2d 367 (Court of Appeals of Kentucky (pre-1976), 1932)
Steele Lebby Co. v. Ayer Lord Tie Co.
55 S.W.2d 52 (Court of Appeals of Kentucky (pre-1976), 1932)

Cite This Page — Counsel Stack

Bluebook (online)
54 S.W.2d 325, 245 Ky. 772, 1932 Ky. LEXIS 676, Counsel Stack Legal Research, https://law.counselstack.com/opinion/steele-lebby-v-flynn-sullivan-co-kyctapphigh-1932.