City of Ashland v. Ben Williamson & Co.

171 S.W.2d 968, 294 Ky. 446, 1943 Ky. LEXIS 443
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedMarch 16, 1943
StatusPublished
Cited by5 cases

This text of 171 S.W.2d 968 (City of Ashland v. Ben Williamson & Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Ashland v. Ben Williamson & Co., 171 S.W.2d 968, 294 Ky. 446, 1943 Ky. LEXIS 443 (Ky. 1943).

Opinion

Opinion of the Court by

Judge Ratliff

Affirming in part and reversing in part.

On May 6, 1930, the City of Ashland, Kentucky,, through its Commission of Waterworks, entered into a. contract with L. E. Payne to construct a filter plant addition to its waterworks system for the sum of $39,630.. Payne executed bond for the performance of the contract with the Standard Accident Insurance Company as surety. Payne sublet the plumbing and heating construction to the Ashland Plumbing and Heating Company (hereinafter called the plumbing company), and subcontracted the electrical work to the J. C. Williams Electric Company (hereinafter called the electric company). Payne-purchased some of the materials used in the performance of the contract from appellee Ben Williamson and Company (hereinafter called Williamson and Company) which was charged directly to the account of Payne. The plumbing company also purchased its materials-used in the performance of its subcontract, from Williamson and Company which was charged on its books-to the plumbing company, but according to the contention of Williamson and Company Payne authorized the-sale of the materials to the plumbing company and became responsible to Williamson and Company therefor. The contract was completed in December, 1930, or late in January, 1931, the exact date being in dispute, which is the basis of the principal issue in this case.

The money appropriated by the city for the performance of the contract was distributed and paid to-Payne, the principal contractor, but he failed to pay Williamson and Company for the materials furnished to him, Payne, and also to the plumbing company. On February 27, 1931, Williamson and Company filed a notice of lien with the city, and on February 28, 1931, filed a lien statement in the office of the clerk of the Boyd county court as provided in sections 2463 and 2492, Carroll’s Kentucky Statutes, now appearing as sections 376.010 and 376.210, respectively, KRS, relating to *449 materialman’s liens, seeking to recover of them the snm Of $3,114.33 with interest from February 28, 1931, for materials furnished to Payne and his subcontractor, the Plumbing Company, and asked that it be adjudged a lien against the waterworks plant. The electric company furnished its own material and labor in the performance of its subcontract with Payne and its accounts have no connection with that of Williamson and Company. The electric company also brought a similar action against the city and Payne to recover of them the sum of $1,270.40 for the material, labor, etc., furnished by it and also sought a materialman’s lien and that action was consolidated with the Williamson and Company action and the consolidated actions were heard and tried together and disposed of in the same judgment.

Payne filed a demurrer to the petition of Williamson and Company, which demurrer was overruled. The city filed an answer and cross-petition in which, because of insufficient knowledge, it denied the allegations of the petition and further alleged that the Standard Accident .and Insurance Company executed for Payne a performance bond and that it should be made a party. It denied that Williamson and Company filed its notice of lien within thirty-five days after the last item of material was furnished. The insurance company filed an answer in which it denied the account of plaintiff (Williamson and Company) and pleaded affirmatively that the waterworks is public property and a lien could not be asserted against it, and further, that the work was completed and payment made in full before the city had any knowledge or notice of plaintiff’s claim. A demurrer was sustained to that part of the answer. On January 31, 1933, a personal judgment was entered against Payne and the action was proceeded with as against the city. Many other pleadings were filed and numerous demurrers filed thereto, some of which were sustained and others overruled, and the issues finally made and the case submitted to the chancellor whereupon judgment was rendered in favor of Williamson and Company for the sum of $2,249.30 for material furnished by it directly to Payne, and the further sum of $716.33 for the material furnished to the plumbing company, and $48.70 interest which had accumulated at the time the suit was filed, making a total of $3,014.33, and also entered judgment in favor of the electric company for the sum of $1,270.40, and to secure the payment of the said judgments, interest and costs to *450 the plaintiffs in each case, awarded a mechanic’s and materialman’s lien against the pumping station property of the Ashland Water Works and that in lieu of enforcement thereof against the property, ordered and directed appellant, city, to provide funds and make payment of the said judgments, interest and costs in full satisfaction of the said liens.

It is the contention of appellant that the last material furnished by Williamson and Company to Payne was on December 2, 1930, and the last material furnished by it to the plumbing company was on January 30, 1931. But it is insisted that Williamson and Company cannot include in its account against Payne its claim against the plumbing company, and hence the lien notices were given more than thirty-five days after it had furnished the last item of material and for that reason it is not entitled to any lien at all.. It is conceded, however, that if the plumbing company account is properly included in the Williamson and Company account with Payne, then the notices were in time even under section 2463, Carroll’s Kentucky Statutes. And, it is further conceded that if section 2492, which requires sixty days’ notice, is applicable the lien notices were in time, but appellant insists that that section is not applicable and that the time to give notice of lien runs from December 2, 1930, the date of the last material furnished by Williamson and Company directly to Payne, rather than January 30, 1931, the date it furnished the last material to the plumbing company.

It is the contention of Williamson and Company that although the material furnished by it was charged on the-books to the plumbing company rather than to Payne, it was agreed and understood that Payne would be responsible for the material furnished to the plumbing-company. Ben Williamson, Jr., the treasurer of Williamson and Company, H. M. Lewis, president of the plumbing company, and L. B. Burke, credit manager for Williamson and Company, testified that Lewis sought to-purchase materials from Williamson and.Company but it refused to extend the plumbing company any further-credit because it already owed $3,500 on an unsecured account which was long past due. Burke referred Lewis to Ben Williamson, Jr., and Lewis contacted Mr. Williamson and was advised by him to bring in the contractor, Mr. Payne, and they would discuss the situation *451 together; that they eonld not furnish Mr. Lewis material without some definite arrangement as to the payment of same. Later Mr. Payne wrote Williamson and Company a letter either guaranteeing or authorizing it to charge purchases by Lewis to him (Payne). He did not produce the letter, stating that it had been misplaced. He said that they furnished the materials to Lewis (the plumbing company) and either charged it to Payne or sent him duplicate invoices of the same, all of which were included in the account sued on.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Viking Builders, Inc. v. Felices
391 So. 2d 302 (District Court of Appeal of Florida, 1980)
McLean County v. Meuth Carpet Supply
573 S.W.2d 340 (Kentucky Supreme Court, 1978)
SANDUSKY FOUNDRY & MACHINE CO. v. City of Wickliffe
369 F. Supp. 439 (W.D. Kentucky, 1972)
Walker v. Valley Plumbing, Inc.
370 S.W.2d 136 (Court of Appeals of Kentucky, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
171 S.W.2d 968, 294 Ky. 446, 1943 Ky. LEXIS 443, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-ashland-v-ben-williamson-co-kyctapphigh-1943.