Allen County v. U. S. Fidelity & Guaranty Co

122 Ky. 825
CourtCourt of Appeals of Kentucky
DecidedApril 15, 1906
StatusPublished
Cited by22 cases

This text of 122 Ky. 825 (Allen County v. U. S. Fidelity & Guaranty Co) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allen County v. U. S. Fidelity & Guaranty Co, 122 Ky. 825 (Ky. Ct. App. 1906).

Opinion

[828]*828OPINION OF THE COURT BY

JOHN D. CaRROLL, Commissioner.

These two appeals are prosecuted on the same record and from the same judgment. The facts involved in this litigation are substantially these: In March, 1903, Allen county entered into' a, contract with one B. P. Manley to erect a courthouse, in consideration for which the county obligated itself to pay Manley $12,987. The contract contains several articles. Those that are pertinent to an understanding .and disposal of this case are as follows:

“Article 3. No alteration shall be made in the wiork shown or described by the drawings and specifications except upon a written order of the architects'. "When so made the value of the work added or omitted shall be computed by the architects, and the amount so ascertained shall be added or deducted from the contract price.”

“Article 5. Should the contractor fail in any respect to prosecute the work with promptness and diligence, or fail in the performance of any of the agreements herein contained, such refusal, neglect, or failure being certified by the architects, the owner shall be at liberty after ten days’ written notice to the contractor to provide any such labor or material and to deduct the cost thereof from any money then due, or thereafter to become due, to the contractor under this contract. And if the architect shall certify that such' refusal, neglect, or failure is sufficient ground for such action, the owner shall also be at liberty to terminate the employment of the contractor for said work,' and to employ any other [829]*829person or persons to finish the work and to1 provide the materials therefor, and the expense incurred by the ow!ner as herein provided either for furnishing materials or for finishing the work, and any damage incurred through such default shall be audited and certified by the architects, whose certificate therefor shall be conclusive upon the parties.

“Article 6. The contractor shall complete said building on or before October 31, 1903, and in default of his completing the courthouse on or before October 31, 1903, he agrees to pay the owners $2.50 per day on each day thereafter.” ,

“Article 9. If at any time there shall be evidence of any lien or claim for which, if established, the owner of said premises might become liable, and which is. chargeable to the contractor, the owner shall have the right to retain out of any payment then due and thereafter to become due an amount sufficient to completely indemnify him against such lien or claim. Should there prove to be any such claim after all payments are made, the contractor shall refund to. the owner all such moneys that the latter may be compelled to pay in discharging any lien on said premises made obligatory in consequence of the contractor’s default.”

For the faithful performance of this contract the county required the contractor to execute to it a bond, which he did, with the United States Fidelity & Guaranty Company as surety. This bond provides that the company is bound to Allen county in the sum of $6,000 conditioned that “if the said principal (Manley) shall well and truly indemnify and save harmless the said obligee (county) from any pecuniary loss, resulting from the breach of any of [830]*830the terms, covenants, and conditions of said contract on the part of said principal to be performed, then this obligation shall be void; otherwise, to remain in full force and effect:” Provided, first, that the county shall notify, the company within 30 days after the breach of the contract by Manley; and, second, that in case of such default the company shall have the rght, if it so desires-, to complete or procure the completion of the contract.

The contractor commenced to work some time in April, and abandoned the contract on August 10, 1903, previous to which time he had been paid on the contract the sum of $9,974. A few days thereafter the county notified the guaranty company of the abandonment of the contract by Manley, and about October 1, 1903, the architects certified to the county that Manley had abandoned the contract, and the county' had a right to terminate it upon notice to Manley. Thereupon the county wrote and addressed to Manley at his last known place of address several letters, and also endeavored to ascertain his location that notice might be given him. The letters addressed to Manley were not delivered, nor was the county able to learn of his whereabouts. The c-ounty also wrote two or three letters to the guaranty company, informing it of the inability to locate Manley, and asking its advice as to what should be done in view? of the situation of affairs. The company took no action, however, and on October 31st the county canceled the contract with Manley and entered into a new contract with another contractor .to complete the building. In January, 1904, the county instituted this action on the bond to> recover from the surety $987, the excess it wfas obliged to [831]*831pay to have the building completed over the contract price agreed on with Manley, and $49.35, the architects’ .commission on this excess $115 penalty for delay of forty-six days in completion of the building, $90 incurred in reletting the contract, and $3,132 paid by it to discharge liens of laborers and materialmen employed by Manley and to whom he was indebted in this sum. Mechanics’ liens for these claims had been duly filed in the clerk’s office, and they had been found by the fiscal court of the 'county to be just, but no suit had been instituted on any of them. The guaranty company resisted payment of the $3,132 on the ground that in paying these claims the county was a mere volunteer; that until compelled by process of law to pay them the county suffered no loss, and that, as no lien could be asserted against the courthouse and the county had no funds in its hands that could be reached by these, lien creditors, it coidd not be required to pay these claims; that the architect had not certified to the correctness of the items of $115 and $90 — and sought to avoid liability for any amount upon the ground that material changes had been made in the contract by the county and Manley without the direction of the architect, and that the county committed a breach of its contract in. taking charge of the work and canceling the: contract without giving to Manley .ten days’ notice. Upon the trial of the case the lower court adjudged that the county recover of the guaranty company the sum, of $1,241.35, being the full amount claimed by it on the items independent of the .$3,132. As to this, item, the court found in favor of the guaranty company. From this ' judgment, both parties asked and were granted an appeal by the low'er court.

[832]*832Counsel for Allen County insist that this court cannot take cognizance of the appeal prayed by the guaranty company from the judgment against it for .$1,241.35, because they say that this is a cross-appeal from that portion of the judgment, and that a cross-appeal cannot he granted in or by the Circuit Court.. It is true that the Circuit Court cannot grant a cross-appeal. It must be granted by the Court of Appeals. Murphy v. Blandford, 11 S. W., 715, 11 Ky. Law Rep., 125; Mudd v. Mullican, 12 S. W., 263. 385, 11 Ky. Law Rep., 417; Hancock v. Hancock’s Adm’r, 69 S. W., 757, 24 Ky. Law Rep., 664. But the-guaranty company prayed an original and not a cross-appeal; the judgment of the lower court reciting: “The plaintiff prays an appeal to' the Court of Appeals which is granted.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McLean County v. Meuth Carpet Supply
573 S.W.2d 340 (Kentucky Supreme Court, 1978)
Ferguson Contracting Co. v. Charles E. Story Construction Co.
417 S.W.2d 228 (Court of Appeals of Kentucky (pre-1976), 1967)
City of Ashland v. Ben Williamson & Co.
171 S.W.2d 968 (Court of Appeals of Kentucky (pre-1976), 1943)
Steele Lebby Co. v. Ayer Lord Tie Co.
55 S.W.2d 52 (Court of Appeals of Kentucky (pre-1976), 1932)
Steele & Lebby v. Flynn-Sullivan Co.
54 S.W.2d 325 (Court of Appeals of Kentucky (pre-1976), 1932)
American Surety Co. of N.Y. v. Noe
53 S.W.2d 178 (Court of Appeals of Kentucky (pre-1976), 1932)
Young Men's Christian Association's Assignee v. Indemnity Insurance Co. of North America
51 S.W.2d 463 (Court of Appeals of Kentucky (pre-1976), 1932)
Vanover v. Cline
39 S.W.2d 477 (Court of Appeals of Kentucky (pre-1976), 1931)
Aetna Casualty & Surety Co. v. United States Gypsum Co.
39 S.W.2d 234 (Court of Appeals of Kentucky (pre-1976), 1931)
Standard Oil Co. of N.J. v. National Surety Co.
29 S.W.2d 29 (Court of Appeals of Kentucky (pre-1976), 1930)
B. B. Wilson Company v. Van Diver
18 S.W.2d 308 (Court of Appeals of Kentucky (pre-1976), 1929)
Mid-Continent Petroleum Corp. v. Southern Surety Co.
9 S.W.2d 229 (Court of Appeals of Kentucky (pre-1976), 1928)
Knott County Board of Education v. Martin
291 S.W. 1062 (Court of Appeals of Kentucky (pre-1976), 1927)
Blatz Co. v. Stivers
255 S.W. 699 (Court of Appeals of Kentucky, 1923)
Empire Coal Co. v. Empire Coal Mining Co.
222 S.W. 947 (Court of Appeals of Kentucky, 1920)
National Surety Co. v. Price
172 S.W. 1072 (Court of Appeals of Kentucky, 1915)
Young Men's Christian Ass'n v. Ritter
133 P. 894 (Supreme Court of Kansas, 1913)
City of Mt. Sterling v. Montgomery County
153 S.W. 952 (Court of Appeals of Kentucky, 1913)
Blanton v. Howard
146 S.W. 1089 (Court of Appeals of Kentucky, 1912)
Day v. Amburgey
143 S.W. 1033 (Court of Appeals of Kentucky, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
122 Ky. 825, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allen-county-v-u-s-fidelity-guaranty-co-kyctapp-1906.