H. Hackfeld & Co. v. Hilo Railroad

14 Haw. 448, 1902 Haw. LEXIS 54
Hawaii Supreme Court·Decided November 10, 1902·Published·Cited by 6 cases

Opinion

OPINION OF THE COURT BY

PERRY, J.

H. Hackfeld & Go., Ltd., brought an action in the Circuit Court of the Fourth Circuit to enforce a lien claimed against certain property of the defendant. The case was tried without a jury and judgment rendered for the defendant. Thereupon a petition for a writ of error was filed,' error being assigned in. certain findings of fact and rulings of law made by the trial court. Undisputed evidence shows the following facts:

On April 5, 1900, J. H. Smith and W. W. Corey, copartners, entered into a contract with the Hilo E. E. Co1, whereby they agreed to do, according to certain specifications, all the grading, necessary for the construction of “the Hilo railroad for a distance of about ten miles, being from station 431 at the southerly limit of the Olaa Cane Land to the Lava Flow of [450]*4501840.” On the 10th of the same month, Herman Elderts agreed with Smith and Corey to grade all of that portion of the road lying between stations 431 and 642. Thereafter Iiackfeld & Co-., the present plaintiffs, agreed to furnish and did furnish to Elderts certain wheelbarrows, tools, blasting powder, lumber and other material, to be used in the construction of said road-bed, and also furnished .cash with which Elderts was to pay the laborers employed. The bill of particulars made a part of the notice of lien and declaration in this action is a correct statement of the items so furnished by the plaintiff to Elderts. The work done by Elderts was completed on October 4, 1900. A part of the cash advanced was repaid, but the balance of the debt due for the money loaned and for the materials furnished is still due and unpaid. Eor the amount of all of such unpaid balance the plaintiff claims a lien upon the railroad' and its appurtenances. Notice of such lien was filed on December 19, 1900.

The trial court found, in substance, the foregoing facts. The following findings of facts and rulings of law were also made:

“10. That the evidence in this case shows quite clearly and satisfactorily that the pláintiff herein never had a contract, written or oral, expressed or implied, with the defendants Smith and Corey or the Hilo R. R. Co., Limited.
“11. That no privity existed between the plaintiff herein and the Hilo R. R. Co., Limited, or Smith and Corey, in respect of the transaction out of which this litigation grew.
“13. That no assignment of his contract or agreement with Smith and Corey by the sub-contractor, Herman Elderts,’ co-defendant herein, was made to the plaintiff, nor was any substitution of parties plaintiff sought ’or obtained by said plaintiff prior to the filing of the lien by the plaintiff, or prior to the bringing of this suit, or at any other time, or at all.
“1. The court concludes that in the absence of an assignment to which the owners- or original contractors consented in writing to- the sub-contract or agreement by and between the co-defendant, or sub-contractor, Elderts, and the plaintiff herein, that plaintiff cannot be substituted to the rights or liabilities of the- co-defendant, Herman Elderts.
“2. That it is essential in order for plaintiff to- maintain its [451]*451action that there should exist a privity between the plaintiff and defendants Hilo E. E. Co., limited, and Smith and Corey in respect of the matter sued on.
“3. That the filing of the lien and notice by the plaintiff herein did not make plaintiff a party to the contract nor bring it within the statute in the absence of the assignment and consent referred to' in conclusion number 1 herein, nor does' our statute work a subrogation of the sub-contractor’s rights to the rights of any one else.”

The plaintiff was the. material-man of a sub-contractor. If it falls within the class designated by our statute to which a lieu is given for certain materials, it is entitled to such lien even though no contract was entered into by it with the owner of the railroad or with the original contractor. In the ordinary sense, the lien does not arise out of contract but is given by law to those who are placed under certain stated conditions; it arises out of contract in the sense only, that, the statute declaring that a lien shall exist under those circumstances for the price of certain materials, the owner, when he awards a contract for the erection of a structure of his, is conclusively presumed to have so contracted with reference to the law and to have voluntarily subjected his property to the rights thus given to material-men and contractors. “This argument rests upon a misconception as to the nature and character of a'mechanic’s lien. This lien is a creature of the statute, and was not recognized at common law. It may be defined to be a claim created by law for the purpose of securing a priority of payment of the price and value of work performed and materials furnished in erecting or repairing a building or other structure, and as such it attaches to the land as well as the buildings erected thereon. * * * Now, it is not the contract for erecting or repairing the building which creates the lien, but it is the use of the materials furnished and the work and labor expended by the contractor,, whereby the building becomes a part of the freehold, that gives the material-man and laborer his lien under the statute. The lien is brought into operation by virtue of the statute, and the contract for building is entered into presumably in view of, or wnth reference to, the statute.” — Van Stone v. Stillwell & [452]*452Bierce Mf'g Co., 142 U. S. 128, 136. See also McMurray v. Brown, 91 U. S. 257, 266; Central Trust Co. v. R. R. Co., 68 Fed. 90, 94, 95; Phillips Mech. Liens) §118; Allen & Robinson v. Redward, 10 Haw. 151.

The class to which the benefit of such liens is granted, is, of course, broader in some jurisdiction and more limited in others. Just how large it is. in any particular case is to be determined in view of the provisions of the statute in force in that jurisdiction. Section 1 of our statute (Chapter 21, Laws of 1888) reads: “Any person or association of persons furnishing labor or material to be used in the construction or repair of any building, structure, railroad or other undertaking, shall have a lien for the price agreed to be paid for such labor or material (if it shall not exceed the value thereof) upon such building, structure, railroad, or other undertaking, as well as upon the interest of the owner of such building, structure, railroad or'other undertaking in tire land upon which the same is situated.” This language is very broad, broader, perhaps, than that of the statutes in many of the states. Any person, with but two limitations, shall have a lien. Those limitations are (1) that such person shall furnish the labor or material and (2) that such labor or material shall be furnished specifically to be used in the construction or repair of the structure sought to. bé charged with the lien. In Allen & Robinson v. Redward, supra, the lien of a material-man of an original contractor was recognized and enforced, and, while the point was, perhaps, not necessary to be determined, the Court would seem to have been of the opinion that any material-man or sub-contractor had a. lien.

Free access — add to your briefcase to read the full text and ask questions with AI

H. Hackfeld & Co. v. Hilo Railroad, 14 Haw. 448, 1902 Haw. LEXIS 54 (haw 1902).

14 Haw. 448 (H. Hackfeld & Co. v. Hilo Railroad) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hawaii Carpenters' Trust Funds v. Aloe Development Corp.
633 P.2d 1106 (Hawaii Supreme Court, 1981)
Reliable Collection Agency, Ltd. v. Aquarius Industries, Inc.
535 P.2d 129 (Hawaii Supreme Court, 1975)
Tropic Builders, Ltd. v. United States
41 Cont. Cas. Fed. 77,073 (Hawaii Supreme Court, 1970)
Lewers & Cooke, Ltd. v. Wong Wong
22 Haw. 765 (Hawaii Supreme Court, 1915)
Lucas v. Hustace
20 Haw. 693 (Hawaii Supreme Court, 1911)