Central Trust Co. v. Richmond, N., I. & B. R.

68 F. 90, 41 L.R.A. 458, 1895 U.S. App. LEXIS 2848
CourtCourt of Appeals for the Sixth Circuit
DecidedMay 7, 1895
DocketNo. 240
StatusPublished
Cited by28 cases

This text of 68 F. 90 (Central Trust Co. v. Richmond, N., I. & B. R.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Central Trust Co. v. Richmond, N., I. & B. R., 68 F. 90, 41 L.R.A. 458, 1895 U.S. App. LEXIS 2848 (6th Cir. 1895).

Opinion

LTJRTON, Circuit Judge,

after stating the facts as above, delivered the opinion of the court.

The first question presented upon the appeal of the Central Trust Company involves the existence of a mechanic’s Tien in favor of any of the subcontractors. The contention of the trust company is that the contract company agreed to accept for its work, bonds constituting a first lien upon the same property, and maturing 30 years from their date, and thereby waived any mechanic’s lien in its favor, and that subcontractors are bound by the waiver, and cannot assert any lien in consequence. It may be admitted that lien laws do not, in general, create a lien in favor of one who accepts in full a different security at the time the contract or agreement is made, or who has entered into any other agreement which manifestly indicates a clear purpose and intention to waive the benefit of the statutory lien. A contract for a security which is inconsistent with the intention that a mechanic’s lien should exist will be held, generally, as a waiver of the statutory lien; but it is well settled that though the owner obligate himself to give a security inconsistent with the intention that a mechanic’s lien should exist, or where the contract is to pay in land, or other specific article of property, yet if the owner fail to fulfill the agreement for such mode of payment, or for different security, it will not be taken as an agreement to waive the mechanic’s lien in case payment is not made in the manner provided for, or the security is not given according to the obligation of the owner. Grant v. Strong, 18 Wall. 623; Reiley v. Ward, 4 G. Greene, 22; McMurray v. Brown. 91 U. S. 257. “If the labor has been performed, or the materials furnished, no matter in what the owner agreed to pay, if he has not paid in any way, the laborer or mechanic [95]*95lias a right: to resort to the security provided by law, unless the lights of third parties intervene before he gives the required notice. Liens of the hind, except where the statute otherwise provides, arise by the operation of law, independent of the express terms of the contract, in case the stipulated labor is performed, or the promised materials are furnished; the principle being that the parties are supposed to contract on the basis that if the stipulated labor is performed, or the promised materials are furnished, the laborer or material man is entitled to the lien which the law affords, provided hé gives the required notice within the specified time.” McMurray v. Brown, 91 U. S. 266; Chicago & A. R. Co. v. Union Rolling-Mill Co., 109 U. S. 702, 721, 722, 3 Sup. Ct. 594; Van Stone v. Manufacturing Co., 142 U. S. 136, 12 Sup. Ct. 181. It may be admitted that the agreement of the contract company to accept, in payment for work and materials, the bonds of the company, ^secured by a first mortgage, and payable in 30 years, and the shares of the eajfifal stock of the company, was an agreement to take a security, which, when actually accepted, would be inconsistent with the retention of a mechanic’s lien. And it may be conceded that, to the extent that payment was made and accepted in bonds and shares, to that extent the debt for work and materials was satisfied, and the mechanic’s lien waived. It is very clear, however, that under the Kentucky statute a lien is originated with the beginning of the work, or the delivery of the materials. The provision in the third section of the act that no lien “shall attach unless the person who performs the labor or .furnishes the labor, materials, or teams, shall within sixty days after the last day of the last month in which any labor was performed, or materials or teams were furnished, furnish a statement in writing * * * and file the same with the clerk of the county court,” is not in conflict with this view. This filing of the claim is necessary to the continuance and perfection of the lien. Tf this is not the meaning, and the lien has its inception when the work has been completed and the claim filed, then the contractor would have no protection against a bona fide purchaser who bought or fixed a lien before the statutory registration. The lien, under such statutes, lias been uniformly held to begin with the delivery of materials, or the beginning of the work. It is not a lien originating in a contract for a lien, but arises out of the statute, independent of any agreement for a lien, and is based upon the equity of paying for work done or materials delivered. It is an incipient or inchoate lien until it is completed or perfected by compliance with the statute, and is lost utterly if those acts be not done, required for its completion, within the time and in the manner required by the statute. Thus, although the contract company had a contract for payment in such securities, which, when accepted, would be inconsistent with the retention of a statutory lien, yet it had an inchoate lien from the time it began work or the delivery of ma terial, which inchoate lien was only waived when the owner complied with his agreement, and gave the security or made the payment contracted for. But, independently of the existence of an incipient or perfected lien in favor of the contract company, we are quite agreed that a subcontractor in the first degree is [96]*96given a direct lien under this statute. It is difficult, as observed by counsel, to add anything by way of argument which will make this contention any more obvious than is apparent from the plain language of the statute. The first section of the act gives the lien to “all persons who perform labor or furnish labor or materials by contract express or implied with the owner * * or by subcontract thereunder.” The clear purpose of the Kentucky statute was to make the liens of the contractor and subcontractor independent direct liens, the latter limited only by the amount of the original contract price. The lien of the subcontractor does not spring but of the lien of the contractor; is not derived therefrom, or subordinate thereto. The aggregate of all the liens is not to exceed the contract price agreed to be paid by the owner, but this limitation concerns, not the fact of a lien, but the extent thereof. Being a direct lien, its existence does not depend upon the existence or nonexistence of a contractor’s lien, and the waiver of a lien by a contractor will not affect the subcontractor’s lien.

Opinions of other courts, construing other statutes, are of little importance, without a careful comparison of the statute in question with that construed. But upon this question, as to whether a subcontractor has a direct lien, the case of Green v. Williams, reported in 92 Tenn. 220, 21 S. W. 520, is in point, for the reason that the Tennessee statute gives a lien to the contractor, “and every person employed by the contractor to work on the building or to furnish materials.” The Tennessee supreme court, in the case cited, said that the lien of a furnisher of materials, under that statute, was distinct, and independent of that of the original contractor, saying:

“Tlie statute gives the lien to several classes of persons, and the lien of each depends upon the statute, and is not derived from the right, or dependent upon the existence or nonexistence of the lien, of any other. The contractor may, by contract or conduct, waive or estop himself. But his subcontractor may nevertheless bring himself within the protection of the statute, and independently assert a lien for his work or materials.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robinson v. Herrell Construction Co.
7 Va. Cir. 308 (Winchester County Circuit Court, 1986)
Campbell & Summerhays, Inc. v. Greene
381 S.W.2d 531 (Court of Appeals of Kentucky (pre-1976), 1964)
Baker Sand & Gravel Co. v. Rogers Plumbing & Heating Co.
154 So. 591 (Supreme Court of Alabama, 1934)
Vollmer Clearwater Co. v. Union Warehouse & Supply Co.
248 P. 865 (Idaho Supreme Court, 1926)
Republic Supply Co. v. Allen
262 S.W. 113 (Court of Appeals of Texas, 1924)
Carl Miller Lumber Co. v. Meyer
196 N.W. 840 (Wisconsin Supreme Court, 1924)
Baldwin Locomotive Works v. Edward Hines Lumber Co.
125 N.E. 400 (Indiana Supreme Court, 1919)
New York Trust Co. v. Detroit, T. & I. Ry. Co.
251 F. 514 (Sixth Circuit, 1918)
Arizona Eastern Railroad v. Globe Hardware Co.
129 P. 1104 (Arizona Supreme Court, 1913)
Lucas v. Hustace
20 Haw. 693 (Hawaii Supreme Court, 1911)
Price v. Hosterman Lumber Co.
73 S.E. 55 (West Virginia Supreme Court, 1911)
Millett v. Swift
128 S.W. 312 (Court of Appeals of Kentucky, 1910)
Sprague v. Provident Savings & Trust Co.
163 F. 449 (Sixth Circuit, 1908)
Fossett v. Rock Island Lumber & Manufacturing Co.
92 P. 833 (Supreme Court of Kansas, 1907)
In re Bennett
153 F. 673 (Sixth Circuit, 1907)
Prince v. Neal-Millard Co.
53 S.E. 761 (Supreme Court of Georgia, 1906)
Baumhoff v. St. Louis & Kirkwood Railroad
71 S.W. 156 (Missouri Court of Appeals, 1902)
H. Hackfeld & Co. v. Hilo Railroad
14 Haw. 448 (Hawaii Supreme Court, 1902)

Cite This Page — Counsel Stack

Bluebook (online)
68 F. 90, 41 L.R.A. 458, 1895 U.S. App. LEXIS 2848, Counsel Stack Legal Research, https://law.counselstack.com/opinion/central-trust-co-v-richmond-n-i-b-r-ca6-1895.