Mayer v. Alexander and Baldwin, Inc.

532 P.2d 1007, 56 Haw. 195, 1975 Haw. LEXIS 86
CourtHawaii Supreme Court
DecidedMarch 3, 1975
Docket5468-5471
StatusPublished
Cited by9 cases

This text of 532 P.2d 1007 (Mayer v. Alexander and Baldwin, Inc.) is published on Counsel Stack Legal Research, covering Hawaii Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mayer v. Alexander and Baldwin, Inc., 532 P.2d 1007, 56 Haw. 195, 1975 Haw. LEXIS 86 (haw 1975).

Opinion

OPINION OF THE COURT BY

LEWIS, J.

Alexander and Baldwin, Inc., through its division A & B Commercial Company, hereinafter referred to as “A & B,” became surety on performance bonds for the construction by Abe Construction, Inc. of homes for appellants, hereinafter referred to as “owners. ” There were four separate contracts. *197 After partial performance of each contract, the contractor, in July, 1969, abandoned the work and ceased doing business. On July 10, 1969, A & B notified the several owners that, as surety, it would complete the work. Litigation ensued, and the four cases were consolidated for trial and disposition on appeal. Only A & B and the owners are involved in this appeal.

A principal question in all the cases is the liability of the surety for damages for delay in performance. It is undisputed that the homes were not completed within the time agreed in the contracts.

Each of the performance bonds provided in pertinent part:

NOW THEREFORE, the condition of this obligation is such that if the above named Principal shall, in all things well and truly keep, observe and perform the covenants, condition and agreements of said Contract, and at the time and in the manner and form therein specified, * * * then this obligation shall be void; otherwise it shall be and remain in full force and effect.
*****
PROVIDED, ALSO, that the Surety shall not be liable * * * for the furnishing of any bond or obligation other than this instrument, nor for damages caused by delay in finishing such Contract.

The court held that under the express provisions of these bonds the surety was not liable for delay. We agree. The owners contend that the provisions above quoted are in conflict with each other, hence ambiguous, but that is not the case. Attention now will be given to the condition of the bond.

We need not go into the question whether “time is of the essence” in a building contract. As stated in 6 WlLLlSTON, CONTRACTS, § 846, p. 183 (3d ed.): “Even where time is not of the essence, it is generally true that an unreasonable lapse of time may be fatal. ” When timéis of the essence or a delay has become so serious as to justify discharge of the contractor, an *198 owner may assume control of the work, cause it to be completed, and hold the contractor for his reasonable expenditures if in excess of the unpaid balance of the contract price. McKnight v. Renfro, 371 S.W.2d 740 (Tex. Civ. App. 1963) (time of the essence); Phillips v. Green Street Corporation, 143 Ind. App. 30, 237 N.E.2d 590 (1968) (upholding a general contractor’s right to discharge the sub-contractor); Johnson v. Slaymaker, 18 Ohio Cir. Ct. Reps. 104 (1898) (allowing the remedy of taking over the work, and holding the contractor for the excess cost of completion and also the remedy of damages for delay in completion. 1

Here the contractor concededly abandoned the work, and the remedy of taking over the work and holding the contractor for the excess cost of completion did not come into play. It did not come into play for another reason also, that is, the surety undertook the completion of the work. It is conceded that the surety had the option to do that. 2 The fact remains that under the provisions of the bond as to performance of the work “at the time * * * specified,” the circumstances might have been such as to permit the owners to look to the surety for the completion of the contracts on account of the contractor’s delay, the same as in a case of abandonment. The provision of the bond that the surety would not be liable for “damages caused by delay in finishing such Contract” simply deleted from the bond the remedy of damages for the delay itself. There is no conflict or ambiguity. As to the contention that “an exculpatory clause for delay in a construction contract is strictly construed against exculpation, and is not absolute,” we do not deem this rule applicable if indeed there is such a rule. “There is no principle of law better settled than that a surety has the right to stand upon the very terms of his contract.” Territory v. Pacific Coast Casualty Co., 22 Haw. 446, 450 (1915). 3

*199 The court found that the work undertaken by the surety through the contractors it employed, was completed within a reasonable time. The owners do not contest this finding except on a point of law. They contend that “the exculpatory clauses in the bond were [not] intended to apply to an exercise by the surety of its right to complete the contract * * This contention would be well taken if the surety had failed to render timely performance after taking over the work. However, that is not the case. To contend that the surety’s time for performance was limited to the 120 working days from the date of start of construction stipulated in the contract and that the surety is liable in damages for time elapsed beyond that point, is to argue full circle. What has been said disposes of the question of damages for delay except for the owners’ contention that: “Regardless of the limitations upon the liability of the surety contained in the bond, by electing to complete the contract the surety subjected itself to all claims of the obligees against the contractor, arising under the contract. ’ ’

If the surety had not elected to complete the contract, each owner’s recourse on the bond would have been, after completion of the contract, a suit to recover his reasonable expenditures to the extent they were in excess of the unpaid balance of the contract price. For example, if the contract price was $25,000 of which $23,500 had been paid to the contractor before he abandoned the work, and $3,100 was expended by the owner to complete the work, the damages sustained by reason of the abandonment of the work would have been $1,600. In a suit on the bond the unpaid balance of the contract price, $1,500, would have been applied against the $3,100, 4 and the excess of $1,600 would have been recovered. Thus the loss to the surety would have been a total of $1,600.

*200 Since the surety did elect to complete the contract, it is the surety who put up the money required for completion instead of the owner. In essence the question is: In this situation, can the owner accomplish indirectly what he could not accomplish directly, by recouping or offsetting against the surety’s claim for the unpaid balance of the contract price damages for delay in the amount found by the court, for which the surety is not liable? 5 We hold that he cannot.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marchesseault v. Jackson
611 A.2d 95 (Supreme Judicial Court of Maine, 1992)
T. Ferguson Construction, Inc. v. Sealaska Corp.
820 P.2d 1058 (Alaska Supreme Court, 1991)
Pacific Employers Insurance v. City of Berkeley
158 Cal. App. 3d 145 (California Court of Appeal, 1984)
Associated Engineers & Contractors, Inc. v. State
567 P.2d 397 (Hawaii Supreme Court, 1977)
Abramson v. Board of Regents, University of Hawaii
548 P.2d 253 (Hawaii Supreme Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
532 P.2d 1007, 56 Haw. 195, 1975 Haw. LEXIS 86, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mayer-v-alexander-and-baldwin-inc-haw-1975.