T. Ferguson Construction, Inc. v. Sealaska Corp.

820 P.2d 1058, 1991 Alas. LEXIS 128
CourtAlaska Supreme Court
DecidedNovember 15, 1991
DocketS-3648
StatusPublished
Cited by6 cases

This text of 820 P.2d 1058 (T. Ferguson Construction, Inc. v. Sealaska Corp.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
T. Ferguson Construction, Inc. v. Sealaska Corp., 820 P.2d 1058, 1991 Alas. LEXIS 128 (Ala. 1991).

Opinions

OPINION

BURKE, Justice.

This is an appeal from a decision of the superior court after a bench trial. The court determined that Sealaska Corporation was justified in withholding a progress payment due to T. Ferguson Construction Company under two related construction contracts and awarded damages to Sealas-ka. Ferguson appeals. We affirm.

I

The facts of this case are largely undisputed. In late April 1988, T. Ferguson Construction, Inc. (Ferguson) entered into three road construction contracts with Sea-laska Corporation. The contracts involved construction and rehabilitation of logging [1059]*1059roads at Tolstoi Bay, Copper Mountain, and Cabin Creek, three sites on Sealaska land located on the west side of Prince of Wales Island. In addition to the roads, the Tolstoi and Cabin Creek contracts called for construction of “sort yards,” which are used for the stacking and storage of cut timber. The contracts emphasized that time was of the essence and established a completion date of September 15, with a default date of September 25.

Because Sealaska did not have the permits required to begin the work at Tolstoi, it directed Ferguson to begin with the Copper Mountain and Cabin Creek projects first. The jobs almost immediately fell behind schedule, largely because Ferguson had inadequate equipment for the projects and inadequate financial resources to mobilize for the operation. A dispute also arose as to whether Sealaska was required to pay per unit of road completed1 or based on Ferguson’s bid schedule.2 Despite the dispute, Sealaska consistently made “measure-ups” on the twenty-fifth of each month and made payment based on these measure-ups by the tenth of the following month.3

In September 1988, the parties entered into an “Agreement for Termination and Modification of Construction Contracts.” This agreement, effective September 20, terminated the Tolstoi contract. It also modified the Cabin Creek and Copper Mountain contracts in several ways. First, as held by the superior court, “Ferguson, by necessary implication, acknowledged the correctness of Sealaska’s contract interpretation and method of payment.”4 The parties also agreed that through August 25, Ferguson had earned $205,344.42 on the Cabin Creek contract, but had been paid $278,949.65. On the Copper Mountain contract Ferguson had earned $52,992.72, but had been paid $78,530.92. Thus, this new accord reflected both parties’ agreement that Sealaska had paid Ferguson $99,143.43 more than it was owed. The agreement specified that $60,000 of that overpayment was an advance made by Sealaska on September 6 to allow Ferguson to buy three dump trucks. The rest of the excess apparently arose from overpayments made by Sealaska intended to alleviate Ferguson’s cash flow problems.

The modification established a new completion date of November 15 and default date of November 25. Sealaska also agreed to advance Ferguson another $50,-000 in cash. The agreement specified that the $110,000 from the truck loan and the cash advance would be paid in equal installments out of funds due to Ferguson on October 10, November 10, and December 10.5

This modification proved to be short-lived. On October 10, Thorne Ferguson, Sr., called Sealaska’s project manager, Jack Coady, to inquire whether the September payment had been mailed and how much it was. Coady indicated that the check was in the mail and that the amount was $52,-000. There was apparently a dispute over how much was actually due. Although Coady claimed that Mr. Ferguson then told [1060]*1060him that Ferguson could not or would not continue performing, the court found that Mr. Ferguson did not make any such statement.

The next day Coady and Sealaska’s chief engineer, Andy Mendenhall, flew over the work sites to see if work was continuing; they observed virtually no activity at either location. As it turned out, the check had not been mailed out due to the Columbus Day holiday. Sealaska decided on the evening of October 11 to withhold the check and so informed Mr. Ferguson. No work was done on either project after October 11. The issue at trial was whether Sealas-ka breached its contracts with Ferguson by withholding the payment or whether such withholding was justified.

A bench trial was held in Juneau in July 1989. In a Memorandum Decision issued August 15, 1989, the superior court found in favor of Sealaska and assessed damages at $57,449.70 plus interest, costs, and fees.6 Although the court found that Mr. Ferguson had not told Coady his company was ceasing performance, it did find that withholding the payment was justified based on a number of facts known to Sealaska at the time:

Sealaska knew that the equipment Ferguson had available was too light for the work, that there was not enough of it, that most of the equipment available at either site was not operable and that very little progress had been made during the last pay period so that the work remained behind even the new schedule. That Ferguson lacked the necessary resources was not the fault of Sealaska. Sealaska had already advanced substantial funds to Ferguson over and above what Ferguson had earned. Sealaska was under no obligation to advance further funds, particularly when it appeared that even with further advances, Ferguson would probably not be able to meet the new completion date agreed to by the parties in the termination and modification agreement.
The court, therefore, concludes that Sealaska did not breach the contract when the October 10,1988, progress payment was withheld, but that Ferguson was in breach of the contract by failing to perform the work in a timely manner due to a lack of equipment suitable for the work.

The superior court denied Ferguson’s motion for reconsideration, and this appeal followed.

II

Ferguson appeals and argues that the superior court erred as a matter of law in finding that Ferguson, rather than Sealas-ka, breached the contract.7 The first part of this discussion thus considers whether Sealaska was justified in withholding payment in light of the factual determinations of the superior court. Although Ferguson is at great pains to characterize the question as one of law, the thrust of its argument is really that the superior court’s factual finding that Ferguson could not perform was in error. The second part of this discussion thus considers whether the superior court clearly erred in its factual determination that Ferguson could not perform its obligations.

A

Although Sealaska primarily argued that Mr. Ferguson’s repudiation of the contract to Coady justified its withholding of the payment, the superior court found that Mr. Ferguson did not repudiate the contract in that phone conversation. The court went on to hold, however, that “[ultimately, it is not necessary to determine the factual issues of who said what as between Mr. Coady and Mr. Ferguson on October 8, 9, and 10, 1988, because the issue is whether Sealaska was justified in withholding the October payment, based on the information then available to it.” The court then found [1061]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brotherton v. Warner
240 P.3d 1225 (Alaska Supreme Court, 2010)
Jourdan v. Nationsbanc Mortgage Corp.
42 P.3d 1072 (Alaska Supreme Court, 2002)
Joyner v. Vitale
926 P.2d 1154 (Alaska Supreme Court, 1996)
T. Ferguson Construction, Inc. v. Sealaska Corp.
820 P.2d 1058 (Alaska Supreme Court, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
820 P.2d 1058, 1991 Alas. LEXIS 128, Counsel Stack Legal Research, https://law.counselstack.com/opinion/t-ferguson-construction-inc-v-sealaska-corp-alaska-1991.