Holiday Inns of America, Inc. v. Peck

520 P.2d 87, 1974 Alas. LEXIS 340
CourtAlaska Supreme Court
DecidedMarch 26, 1974
Docket1858
StatusPublished
Cited by115 cases

This text of 520 P.2d 87 (Holiday Inns of America, Inc. v. Peck) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Holiday Inns of America, Inc. v. Peck, 520 P.2d 87, 1974 Alas. LEXIS 340 (Ala. 1974).

Opinion

OPINION

BOOCHEVER, Justice.

Appellant Holiday Inns suffered a judgment of $51,000 against it in the superior court for damages arising out of an alleged breach of a franchise contract Holiday Inns had made with Leonard Peck for the construction of a Holiday Inn facility in Anchorage. The original franchise contract was entered into in November of 1965, with Peck tendering a deposit of $10,000 and the parties executing a contract in the form of a “commitment letter”.

The commitment letter contained a condition that Peck begin construction by 6 months from November 10, 1965. After Peck was unable to comply with this condition, a long series of correspondence and negotiations took place between the parties. After extending the construction commencement deadline several times, Holiday Inns advised Peck on October 2, 1967 that either he could have his deposit back (less Holiday Inn’s expenses) or Holiday Inns would grant him an extension to January 15, 1968 to enable him to demonstrate that he had secured the necessary long-term financing, 1 in which case the deadline for commencing construction would be further extended to May 1, 1968.

Peck apparently satisfied Holiday Inns that he had obtained financing, 2 and, as a result, he received a new commitment letter dated February 23, 1968 superseding the former agreement. It is this new commitment letter that is the subject of the instant suit.

Peck and two associates (not parties to this suit) signed the February commitment letter on March 4, 1968, and an additional associate signed it on March 6, 1968. John M. Greene, Jr. then signed the letter on behalf of Holiday Inns.

In addition to superseding the former commitment letter, the new commitment letter contained two interlineated conditions. In paragraph 5, dealing with a new construction commencement date, a line was drawn through “within nine (9) months from the date of this Commitment letter” and the term “by May 1, 1968” interlineated. In paragraph 6 dealing with a *89 final deadline for the completion of the facility, the term “within eighteen (18) months from the date of this commitment” is crossed out and the term “February 1, 1969” interlineated. The interlineations bore only the initials JMG.

Additional correspondence referring to the May 1, 1968 deadline was received from Holiday Inns and acknowledged by Peck. Holiday Inns subsequently advised Peck by a letter dated June 14, 1968 that the commencement deadline would be extended to July 1, 1968 with a completion deadline of April 1, 1969, and requested Peck to make these changes in his commitment letter. Peck did not respond to the request.

On June 20, 1968, Peck advised Holiday Inns that he was unable to secure long-term financing and asked Holiday Inn’s assistance in securing it. In a letter dated July 1, 1968, Holiday informed Peck that his request would be denied, and that his commitment letter of February 23, 1968 was null and void under its “own terms and conditions”, since the July 1, 1968 construction commencement date had not been met. The $10,000 was never returned. Peck filed suit for breach of contract on August 6, 1971.

In his complaint, Peck alleged in substance that Holiday Inns breached its agreement to issue a franchise to his associates and himself, and that, as a result, he was entitled to recover out-of-pocket expenses, the reasonable value of time spent on the project, legal and secretarial expenses incurred, and his $10,000 deposit, in a total amount of $63,269.64. In addition, he alleged that he had been deprived of a participating interest in the Floliday Inn worth $500,000. Holiday Inns answered, with a general denial of the material allegations of the complaint and affirmative defenses of failure to state a claim and failure to comply with the conditions set forth in the commitment letter.

During the trial of the case, it became apparent that major issues were whether the alteration in commencement date had been made subsequent to Peck’s signing the agreement; and if so, whether it was binding on him.

It was the plaintiff’s contention at trial that the interlineation had been made after he signed the commitment letter, and that he therefore had nine months to commence performance (as the commitment letter originally specified). Accordingly, the commencement date would have been November 23, 1968, not May 1, 1968 as stated in the interlineation, or July 1, 1968 as subsequently extended by Holiday Inns. Holiday Inns’ July 1, 1968 declaration that the commitment letter was null and void would therefore have constituted an anticipatory breach of the contract entitling Peck to damages. 3

The jury returned a verdict for Peck in the amount of $51,000. The trial judge had previously denied a motion for a directed verdict. After the jury’s decision, he denied a motion for judgment notwithstanding the verdict, and a motion for a new trial.

Holiday Inns contends on appeal, inter alia, that Peck did not substantially comply with the commencement deadline provision of the contract, and that the judge’s instructions concerning substantial performance were erroneous. But if the July 1 deadline did not bind Peck, then Holiday Inns would have had no right to repudiate the contract, and Peck would be entitled to damages for anticipatory breach. Thus, only if the July 1 deadline is applicable would it be necessary to reach the issue of *90 substantial performance. At the close of trial the judge submitted the interrogatories to the jury, including the following:

1 — Do you, the jury, find that Leonard W. Peck knew of and was bound by any May 1, 1968 deadline for the commencement of the construction prior to any extension thereof ?
2 — Do, you, the jury, find that Leonard W. Peck knew of, and was bound by an extension or change in the time to commence construction to July 1, 1968?

The jury responded to each in the negative so that the answers to those interrogatories indicate that the jury found that the July 1 date did not apply to Peck on the basis that he either did not know of it, or was not bound by it. If there was no reversible error in that finding, the general verdict consistent with it must be upheld. 4 Therefore, our initial inquiry is directed to determining whether the July 1 deadline was effective.

I

THE PROPRIETY OF THE SPECIAL INTERROGATORIES

Although Holiday Inns alleges that it objected to the proposed interrogatories in chambers because of their compound and legal nature, it waived any objections at trial when counsel stated: “I have no objection to the interrogatories in their present form, Your Honor.”

Civil Rule 51 (a) provides in part:

No party may assign as error the giving or the failure to give an instruction unless he objects thereto before the jury retires to consider its verdict, stating distinctly the matter to which he objects and the grounds of his objection.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Christopher R. Stacy v. State of Alaska
500 P.3d 1023 (Court of Appeals of Alaska, 2021)
in the Interest of K.I.B.C., a Child
Court of Appeals of Texas, 2015
City of Hooper Bay v. Bunyan
359 P.3d 972 (Alaska Supreme Court, 2015)
Vera Rosier v. Hugh W. Fleischer
Alaska Supreme Court, 2015
Jones v. Bowie Industries, Inc.
282 P.3d 316 (Alaska Supreme Court, 2012)
L.D.G., Inc. v. Brown
211 P.3d 1110 (Alaska Supreme Court, 2009)
Noffke v. Perez
178 P.3d 1141 (Alaska Supreme Court, 2008)
MacDonald v. Riggs
166 P.3d 12 (Alaska Supreme Court, 2007)
Mooney v. State
105 P.3d 149 (Court of Appeals of Alaska, 2005)
In the Interest of J.F.C.
96 S.W.3d 256 (Texas Supreme Court, 2002)
Willis v. State
57 P.3d 688 (Court of Appeals of Alaska, 2002)
Dobberke v. State
40 P.3d 1244 (Court of Appeals of Alaska, 2002)
Heaps v. State
30 P.3d 109 (Court of Appeals of Alaska, 2001)
Baker v. State
22 P.3d 493 (Court of Appeals of Alaska, 2001)
City of Fairbanks v. Rice
20 P.3d 1097 (Alaska Supreme Court, 2000)
Wal-Mart, Inc. v. Stewart
990 P.2d 626 (Alaska Supreme Court, 1999)
Alaska Marine Pilots v. Hendsch
950 P.2d 98 (Alaska Supreme Court, 1997)
Hughes v. Foster Wheeler Co.
932 P.2d 784 (Alaska Supreme Court, 1997)
Ahwinona v. State
922 P.2d 884 (Alaska Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
520 P.2d 87, 1974 Alas. LEXIS 340, Counsel Stack Legal Research, https://law.counselstack.com/opinion/holiday-inns-of-america-inc-v-peck-alaska-1974.