Elgin v. Housing Authority

52 F. Supp. 250, 1943 U.S. Dist. LEXIS 2123
CourtDistrict Court, D. Maryland
DecidedOctober 15, 1943
DocketCiv. No. 1302
StatusPublished

This text of 52 F. Supp. 250 (Elgin v. Housing Authority) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elgin v. Housing Authority, 52 F. Supp. 250, 1943 U.S. Dist. LEXIS 2123 (D. Md. 1943).

Opinion

COLEMAN, District Judge.

The question here presented is whether a subcontractor is to be preferred to his contractor’s surety in an attachment suit instituted by the subcontractor against funds in the hands of the obligee under the surety’s bond for completion of a housing project by the contractor in the City of Frederick, Maryland.

The present litigation was commenced in. the Circuit Court for Frederick County, Maryland, by the laying of a nonresident attachment on the Housing Authority of the City of Frederick, a statutory agency of that municipality, against all credits and funds due by the Housing Authority to Sofarelli Bros., Inc., a New York corporation, the contractor, incident to the claim which was brought against the latter by the subcontractor, W. Lee Elgin, trading as Potomac Heating & Supply Company. Thereupon, Sofarelli Bros., Inc., by virtue of diversity of citizenship of the parties, caused the attachment and the statutory, companion direct suit, commonly known as the short-note case, to be removed to this court, where trial of the short-note case was had before a jury, resulting in a verdict in favor of the plaintiff for $2,128.-68. An appeal was taken to the Circuit Court of Appeals from the judgment entered upon this verdict, and the judgment was affirmed.

The garnishee, the Housing Authority, filed its plea of nulla bona in the present, that is, the attachment suit, setting forth an assignment from Sofarelli Bros., Inc., to its surety, the Fidelity & Deposit Company of Maryland, this assignment being dated May 13, 1941, that is, thirteen days before the attachment was laid.

The claim of the plaintiff is based upon the following provision in the bond: “Now, therefore, the condition of this obligation is such that, * * * if the Principal shall pay all lawful claims of all persons, firms or corporations for all labor performed, or materials furnished for the performance of this contract failing which such persons shall have a direct right of action against the Principal and Surety under this obligation, then this obligation shall be null and void, otherwise, it shall remain in full force and effect.”

The Housing Authority, garnishee, admits that it now retains and has had in its hands at all times since the laying of the attachment, $3,211.12, being balance due Sofarelli Bros., Inc., under their construction contract, which amount is more than sufficient to satisfy plaintiff’s judgment obtained as previously explained. Plaintiff contends that the assignment by Sofarelli Bros., Inc., to its surety is void as to it, the plaintiff, and judgment creditor of the defendant-assignor, on the ground that plaintiff is, by the express language of the bond above quoted, one of those persons given “a direct right of action against the principal and surety” for all labor performed or material furnished in the performance of the contract.

Plaintiff did not attempt to make the surety a party to the short-note case, but after obtaining judgment in that case, plaintiff moved this court to have the surety made a third-party defendant in this, the attachment suit, but this motion was denied because the surety had not been made a party to the short-note case. The surety contends that it is entitled to a trial before a jury, if it so elects, and thereby to have it determined whether or not plaintiff has performed any labor or furnished any material in the completion of the contract in question, for which plaintiff has not been paid. In other words, the surety contends that the fact that the subcontractor has obtained a judgment against the contractor does not make the liability of the surety on the bond res adjudicata; that plaintiff [252]*252should have sued the surety in the first instance, instead of proceeding by way of nonresident attachment; and that, had it done so, both the question of the main contractor’s liability to the plaintiff as a subcontractor, and the question of the surety’s liability on the bond, could have been determined in one proceeding, but that since plaintiff did not elect so to do, the surety has not yet had an opportunity to assert its defense to the claim of liability on the bond.

With these contentions of the surety we do not agree when asserted for the purpose of defeating the right of the plaintiff to recover in the present attachment suit. We are to be governed by the Maryland law on the subject, and we find nothing in the Maryland decisions, or in any decision of the Supreme Court or of the Circuit Court of Appeals for this Circuit, which requires us to deny recovery to the plaintiff.

It is true the assignment by the main contractor, Sofarelli Bros., Inc., to the latter’s surety, was made prior to the laying of the present attachment by the plaintiff; and notice of such assignment to the garnishee, the Frederick Housing Authority, was also prior. However, since the present plaintiff holds, as a subcontractor, an unsatisfied judgment against Sofarelli Bros., Inc., which judgment has been affirmed by the Court of Appeals and now stands incontestable as to its validity, we believe that plaintiff’s right to reach any assets of his judgment-debtor, that is to say, Sofarelli Bros., Inc., cannot validly be thwarted by any action which the latter’s surety may take with a view to protecting itself under its bond.

This is not a suit on the bond, so we are not called upon to determine whether the judgment which the plaintiff has obtained against Sofarelli Bros., Inc., alone makes the liability of the surety on the bond res adjudicata. We agree that had the plaintiff sued the surety in the first instance, instead of proceeding against his principal debtor by way of nonresident attachment, that would have been the quickest, most direct way to have a determination as to the surety’s liability. Also, we may assume thát the rule here applies that an indemnity insurer will not be estopped to set up the defense that the insured’s loss was not covered by the contract or bond of indemnity, by the fact that the insurer participated in the action against the insured, —as did the surety in the present case, because it assumed charge of the suit brought by the plaintiff against Sofarelli Bros., Inc., in which the plaintiff obtained the judgment in question, — if at the same time the insurer gives notice to the insured, — as was done in the present case, — that it does not waive the benefit of such defense. But this does not mean that a surety, in the protection of his own interest as between himself and the debtor, may, under such circumstances as we here have, set up such a priority with respect to the debtor’s assets that a judgment creditor of the debtor is forced to seek satisfaction of his judgment exclusively against the surety. In short, the subcontractor, having obtained his judgment against the main contractor, is not required to look to the latter’s surety for payment, even though under Maryland law a bond such as the present one, covers not only any loss sustained by the obligees, but also any loss suffered by those who furnished labor or materials directly to the principals, by reason of nonpayment therefor. See Hartford Accident & Indemnity Co. v. W. & J. Knox Net & Twine Co., 150 Md. 40, 132 A. 261.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCandless v. Furlaud
296 U.S. 140 (Supreme Court, 1935)
Prudence Realization Corp. v. Geist
316 U.S. 89 (Supreme Court, 1942)
Hartford Accident & Indemnity Co. v. W. & J. Knox Net & Twine Co.
132 A. 261 (Court of Appeals of Maryland, 1926)
Rody v. Doyle
29 A.2d 290 (Court of Appeals of Maryland, 1942)
Stehle v. United Surety Co.
68 A. 600 (Court of Appeals of Maryland, 1908)
American Surety Co. of New York v. Finletter
274 F. 152 (Third Circuit, 1921)
Maryland Casualty Co. v. Gates
290 F. 65 (Fourth Circuit, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
52 F. Supp. 250, 1943 U.S. Dist. LEXIS 2123, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elgin-v-housing-authority-mdd-1943.