Mfg. Co. v. . Blaylock

135 S.E. 136, 192 N.C. 407, 1926 N.C. LEXIS 307
CourtSupreme Court of North Carolina
DecidedOctober 27, 1926
StatusPublished
Cited by12 cases

This text of 135 S.E. 136 (Mfg. Co. v. . Blaylock) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mfg. Co. v. . Blaylock, 135 S.E. 136, 192 N.C. 407, 1926 N.C. LEXIS 307 (N.C. 1926).

Opinion

On 12 July, 1924, R. L. Blaylock, contractor, entered into a written agreement with the board of education of Lenoir County for the erection of a public school building at Moss Hill, N.C. in which it was stipulated, among other things, that, in consideration of the sum of $26,316.00, payable up to 85% of the contract price in monthly installments on estimates of the architect, with 15% to be retained and held until the completion of the building, "the contractor shall and will provide all materials and perform all the work" necessary for the erection of said school building; and on the same day, for a valuable consideration, the board of education of Lenoir County took from the contractor, as principal, and the American Surety Company, as surety, a bond of indemnity in the sum of $4,579.00 to "indemnify the obligee against any loss or damage directly arising by reason of the failure of the principal faithfully to perform said contract," etc.

On 18 February, 1925, the contractor defaulted, having received prior to that time $22,244.84 of the contract price for work on said building. Thereafter the board of education, on order of the bonding company, expended $277.41 for the completion of the building, leaving a balance of $3,716.06 due under the contract, and held by the school board as the 15% retained percentage.

At the time of default by the contractor, claims for work done on and materials furnished for said building, amounting to $8,284.96, were outstanding and unpaid.

On 28 April, 1926, the surety paid into court the sum of $4,579.00, the full penalty of its bond (unless it be liable for interest thereon), for distribution pro rata among the laborers and materialmen as provided by the statute.

The American Surety Company now contends that the retained percentage, amounting to $3,716.06, in the hands of the board of education of Lenior County, should be turned over to it by reason of its contract of suretyship which contains, inter alia, a stipulation to the effect that in case of default by the contractor, the surety "shall also be subrogated to all of the rights of the principal; and any and all moneys or property that may at the time of such default be due, or that thereafter may become due to the principal under said contract, shall be credited upon any claim which the obligee may then or thereafter have against the surety, and the surplus, if any, applied as the surety may direct."

The plaintiffs, on the other hand, contend that said amount should be applied to the payment of their claims, being, as they are, laborers and materialmen. The appeal presents the single question as to who is entitled to this fund. The trial court held that it should be paid to the *Page 410 American Surety Company. We think the judgment is correct, and that it must be affirmed.

It is conceded by all the parties that the bond executed by R. L. Blaylock and the American Surety Company was taken and given in view of the provisions of C. S., 2445, as amended by chapter 100, Public Laws 1923, requiring every county, city, town or other municipal corporation, which lets a contract for building, repairing or altering any building, public road or street, to take from the contractor of such work (when the contract price exceeds $500) a bond, with one or more solvent sureties, before beginning any work under the contract, payable to said county, city, town or other municipal corporation, and conditioned "for the payment of all labor done on and materials and supplies furnished for the said work," and upon which suit may be brought for the benefit of laborers and materialmen having claims. Warner v. Halyburton, 187 N.C. 414.

The statute, as amended, provides that every bond given to any county, city, town or other municipal corporation, for the building, repairing or altering of any public building, public road or street, as required by this section, "shall be conclusively presumed to have been given in accordance therewith, whether such bond be so drawn as to conform to the statute or not, and this statute shall be conclusively presumed to have been written into every such bond so given." The amount of the bond is to be equal to the contract price when over five hundred and not more than two thousand dollars; when the contract price is between two and ten thousand dollars, the amount is to be determined by adding to two thousand dollars, thirty-five per cent of the excess of the contract price over two thousand dollars; and when the contract price is over ten thousand dollars, the amount of the bond is required to be two thousand dollars plus twenty-five per cent of the excess of the contract price over the sum of two thousand dollars. It is further provided in the amended law that only one action may be brought on such bond, all claimants to be duly notified, which was done in the instant case, and if the aggregate sum exceed the amount of the bond, the payments are to be prorated. "If the recovery on the bond shall be inadequate to pay the amounts found due to all the claimants, judgment shall be given to each claimant pro rata of the amount of the recovery."

The surety is also allowed, by paying into court in such suit the full amount of the penalty of the bond, to be relieved from any other or further liability thereon. Electric Co. v. Deposit Co., 191 N.C. 653.

The principle is well established by many authoritative decisions, here and elsewhere, that in determining the surety's liability to third persons, on a bond given for their benefit and to secure the faithful *Page 411 performance of a building contract as it relates to them, the contract and bond are to be construed together. Mfg. Co. v. Andrews, 165 N.C. 285. The obligation of the bond is to be read in the light of the contract it is given to secure, and ordinarily the extent of the engagement, entered into by the surety, is to be measured by the terms of the principal's agreement.Brick Co. v. Gentry, 191 N.C. 636, and cases there cited.

It is stipulated in the present bond that "this bond is subject to the provisions of section 2445 of the Revised Statutes of North Carolina and amendments thereto." The right of the laborers and materialmen to recover on said bond is conceded, and it has been paid in full. The contest is over the retained percentages withheld under the contract and now in the hands of the owner.

In this connection, it may be well to bear in mind the distinction between the remedies afforded and intended to be afforded by the present statute, being applicable, as it is, to public works, and those given by the lien statutes which apply only to private works of a similar nature.Noland Co. v. Trustees, 190 N.C. 250.

C. S., 2437, one of the lien statutes, in terms provides that all subcontractors and laborers who are employed to furnish, or who do furnish, labor or material for the building, repairing or altering of any house or other improvement on real estate, shall have a lien on said house and real estate for the amount of such labor done or material furnished, when notice thereof has been given as required by law; "but the sum total of all the liens due subcontractors and materialmen shall not exceed the amount due the original contractor at the time of notice given." Supply Co. v. EasternStar Home, 163 N.C. 513.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carolina Builders Corp. v. AAA Dry Wall, Inc.
259 S.E.2d 364 (Court of Appeals of North Carolina, 1979)
SALEM REALTY COMPANY v. Batson
123 S.E.2d 744 (Supreme Court of North Carolina, 1962)
American Bridge Division United States Steel Corp. v. Brinkley
120 S.E.2d 529 (Supreme Court of North Carolina, 1961)
AMERICAN BRIDGE DIVISION US STEEL CORP. v. Brinkley
120 S.E.2d 529 (Supreme Court of North Carolina, 1961)
Carolina Builders Corp. v. New Amsterdam Casualty Co.
73 S.E.2d 155 (Supreme Court of North Carolina, 1952)
Hochevar v. Maryland Casualty Co.
114 F.2d 948 (Sixth Circuit, 1940)
Bank of Northampton v. Town of Jackson
200 S.E. 444 (Supreme Court of North Carolina, 1939)
Pearson v. . Simon
177 S.E. 124 (Supreme Court of North Carolina, 1934)
Fidelity & Deposit Co. v. Board of Education
162 S.E. 763 (Supreme Court of North Carolina, 1932)
Beeson Hardware Co. v. Burtner
155 S.E. 733 (Supreme Court of North Carolina, 1930)
Crouse v. . Stanley
154 S.E. 40 (Supreme Court of North Carolina, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
135 S.E. 136, 192 N.C. 407, 1926 N.C. LEXIS 307, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mfg-co-v-blaylock-nc-1926.