In Re L. H. Duncan & Sons

127 F.2d 640, 1942 U.S. App. LEXIS 3939
CourtCourt of Appeals for the Third Circuit
DecidedApril 14, 1942
Docket7862
StatusPublished
Cited by8 cases

This text of 127 F.2d 640 (In Re L. H. Duncan & Sons) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re L. H. Duncan & Sons, 127 F.2d 640, 1942 U.S. App. LEXIS 3939 (3d Cir. 1942).

Opinion

BIGGS, Circuit Judge.

On January 5, 1938, the partners, now bankrupt, entered into a written contract with the Commonwealth of Pennsylvania for the construction and improvement of a section of state highway. The contract provided, “The contractor further covenants and agrees that all of said work and labor shall be done and performed in the best and most workmanlike manner and that prompt payment will be made in full for labor and material used in the work.”

At the same time the partners made a written application to Maryland Casualty Company, the appellant, for the bonds required by statute. See Highways and Bridges, 36 P.S. § 142. In this application the partnership agreed to indemnify the appellant for any liability which it might incur under the bonds. The application provided in part: “In the event of claim or default under the bonds herein applied for, or in the event the undersigned shall fail to fulfill any of the obligations assumed under the said contract and bonds * * * executed for us or at our instance, and request all payments due or to become due under the contract covered by the bonds herein applied for, shall be paid to the company * * * and this covenant shall operate as an assignment thereof. * * * The company shall * * * be subrogated to all rights, properties and interest of the undersigned in said contract * * At the same time the partnership and Maryland Casualty Company executed and delivered to the Commonwealth of Pennsylvania the two bonds required by law, viz., a contract bond guaranteeing performance of the contract and a bond for the payment of materialmen and laborers. Thereafter the partnership entered upon the performance of the work required by the contract and completed it in September, 1938.

During the progress of the work the partnership contracted debts for materials supplied and labor performed in the prosecution of the construction. On September 28, 1938, the partners filed a voluntary petition in bankruptcy and were adjudicated bankrupts. Thereafter the appellant, as surety, paid the claims for materials furnished and labor performed in the prosecution of the work, and, obtaining assignments of proofs of debt from the individuals paid, filed these claims in the bankruptcy proceeding.

When the partners were adjudicated bankrupts the Commonwealth of Pennsylvania had not paid the sum of $6,912.27 which was the balance due on the contract between the Commonwealth of Pennsylvania and the partners. The claims of laborers and materialmen paid by the appellant exceeded this amount. The sum unpaid was claimed both by the partnership’s trustee in bankruptcy and by the appellant. The trustee and the appellant thereupon entered into a written agreement providing that Pennsylvania should pay the sum of $6,912.27 to the trustee without prejudice to the right of either the trustee or the appellant to claim the fund. Shortly thereafter the appellant executed the release of final payments which is required by Pennsylvania before payments will be made on account of construction of a state highway and the Commonwealth paid to the trustee the sum referred to. Maryland Casualty Company then filed a petition with the referee claiming the fund. After hearing the referee dismissed the petition without prejudice and ordered the trustee to file an account. At the hearing upon the trustee’s account the appellant again set up its claim to the fund. The referee disallowed the claim and found that the appellant was entitled to priority only in the matter of wage claims paid by it and assigned to it in the sum of $2,159.28, and that by the payment of the sums due to the materialmen the casualty company got the status only of a general creditor. Upon petition for review, the court below affirmed the referee’s decision. An appeal was taken to this court.

Two points are raised for our determination. The appellant claims that it is entitled to the fund by way of subrogation under the contract between the Commonwealth and the bankrupts and also by reason of the equitable assignment contained *642 in the application for the bonds which we have heretofore quoted.

Pennsylvania law governs the case. Erie R. Co. v. Tompkins, 304 U.S. 64, 58 S.Ct. 817, 82 L.Ed. 1188, 114 A.L.R. 1487. The difficulty is to fit the facts at bar into the pattern of the decisions of the Supreme Court of Pennsylvania. The appellee contends that the case is ruled by DuBois v. United States Fidelity & Guaranty Company, 341 Pa. 85, 18 A.2d 802, and Sundheim v. Philadelphia School District, 311 Pa. 90, 166 A. 365. The appellant contends that it is governed by Lancaster County National Bank’s Appeal, 304 Pa. 437, 155 A. 859, 861.

In the Sundheim case there were construction contracts by reason of which the contractor undertook to build certain buildings in accordance with plans and specifications, but did not obligate itself to the School District to pay materialmen and laborers. The contractor executed construction bonds conditioned for the completion of the work. These bonds were for the benefit of the owner, the School District. The contractor executed other bonds to secure the payment of labor and materialmen in compliance with the provisions of the Act of May 6, 1925, P.L. 546, 53 P.S. § 521. The Supreme Court of Pennsylvania held that the surety was paid fully for the work which it had had to perform in order to complete the contract and that there was no obligation in the construction bonds or the construction contracts running to the owner to pay labor and materialmen. The court thereupon concluded that the provisions of the Act of May 6, 1925 were not a part of the construction contracts and the failure of-the contractor to pay labor and materialmen was not a breach of the construction contracts. Justice Kephart said, at page 368 of 166 A.: “The acts simply required an ‘additional bond’ for the protection of labor and materialmen and it was under that obligation the surety was required to pay. The contractor’s obligation to pay labor and materialmen came through the agreements between the contractor and such claimants. • Therefore, when the surety paid these claims, without other facts (Lancaster County National Bank’s Appeal, supra), it can predicate no right through the construction contract with the owner, or the bond given for that construction, or the statutes referred to, to any part of the funds in the owner’s hands due under the construction contract.” The court would not permit subrogation by the surety to the contractor’s claim to the unpaid balance due on the contract and held that the contractor’s receiver was not entitled to prevail against the contractor’s creditors.

Contrasting the federal cases which follow a different rule, Justice Kephart stated, at page 367 of 166 A.: “Under federal statutes a single bond is required which must provide for the completion of the contract and the payment of labor and matrialmen. 40 U.S.C. § 270 (40 U.S. C.A. § 270), 36 Stat. 1167. It has been held by federal courts that there is a direct contractual obligation to the government as a party to the contract, binding on the contractor and surety, to pay labor and materialmen. Consequently, when the contractor fails to pay labor and material-men, it is tantamount to a breach of its contract with the United States government.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Federal Insurance v. Constructora Maza, Inc.
500 F. Supp. 246 (D. Puerto Rico, 1979)
Philadelphia Industrial Corp. v. Upper Dublin Township
169 F. Supp. 725 (E.D. Pennsylvania, 1959)
United States Ex Rel. Greer v. G. P. Fleetwood & Co.
165 F. Supp. 723 (W.D. Pennsylvania, 1958)
In Re Cummins Const. Corporation
81 F. Supp. 193 (D. Maryland, 1948)
Continental Casualty Co. v. City of Pittsburgh
68 F. Supp. 805 (W.D. Pennsylvania, 1946)
In Re Flotation Systems, Inc.
65 F. Supp. 698 (S.D. California, 1946)
In Re Webber Motor Co.
52 F. Supp. 742 (D. New Jersey, 1943)
Maryland Casualty Co. v. City of Pittsburgh
51 F. Supp. 459 (W.D. Pennsylvania, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
127 F.2d 640, 1942 U.S. App. LEXIS 3939, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-l-h-duncan-sons-ca3-1942.