Sundheim v. Philadelphia School District

166 A. 365, 311 Pa. 90, 1933 Pa. LEXIS 492
CourtSupreme Court of Pennsylvania
DecidedJanuary 6, 1933
DocketAppeal, 354
StatusPublished
Cited by31 cases

This text of 166 A. 365 (Sundheim v. Philadelphia School District) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sundheim v. Philadelphia School District, 166 A. 365, 311 Pa. 90, 1933 Pa. LEXIS 492 (Pa. 1933).

Opinion

Opinion by

Mr. Justice Kephart,

The question involved in this appeal concerns the right of a surety, who has paid the claims of labor and materialmen, to funds in the hands of the owner as against the claims of other creditors.

In 1929 the Weiss Construction Company, hereinafter called contractor, entered into three separate contracts dated January 7th with the School District, of Philadelphia, hereinafter called owner, for the construction of three school buildings. The contracts authorized the owner to notify the contractor to discontinue work under the contract in case he neglected, delayed, or defaulted in the performance of it, or to declare the contract null and void, in which case the security bond, *93 retained percentages, and material on the premises should become the property of the owner. Eighty-five per cent of the contract price was to be paid as the work progressed, 12% was to be held until the buildings Avere accepted, and .3% retained by the owner for twelve months, subject to the completion of the buildings, as security against any loss arising from defective Avorkmanship, materials and settling.

Three bonds, hereinafter termed construction bonds, were executed and delivered, each bearing the same date as the contract. These bonds were to save, protect, and indemnify the owner from and against all loss, damage, and expense by reason of failure to comply with the contract and specifications.

In compliance Avith the Act of May 10, 1917, P. L. 158, as amended by the Act of May 6, 1925, P. L. 546, the surety and contractor executed three additional bonds similarly dated to secure the payment of labor and materialmen.

On January 17, 1930, one of the school buildings was accepted by the owner, and on February 11th of the same year, the other buildings were accepted, Avith the exception of the work of terracing, sodding, and seeding the grounds, and subject to the provision of the contract requiring maintenance of the buildings for one year after acceptance. The OAvner paid to the contractor all the money called for by the contract with the exception of the retained 3%, amounting to $36,253.52, and the sum of $10,000. The latter sum was held to pay for the work of terracing, etc., as above stated. The contractor, having failed to go ahead with this work, was notified on February 24th that unless he proceeded to finish the work, he would be ordered to withdraAV from the premises. On March 3d, the contractor, having done nothing, was ordered to withdraw, and the OAvner stated it Avould finish the work and deduct the cost from the money in its hands. A copy of this letter was sent to the surety.

*94 The surety, after the owner started, to do the unfinished work, asked that it he permitted to complete it. The sodding, etc., was finished by the surety at a cost of $1,975. The $10,000, retained as above stated by the owner, was paid to the surety less $415 retained to reimburse owner for expenditures for repairs. The surety used $1,975 of that sum to repay it for sodding, etc., and applied the balance to other items it was compelled to assume under its bonds because the contractor had failed to pay them. The cost to surety for maintenance of the building for one year after the date of acceptance was $6,275. It also paid some $72,000 that the contractor failed to pay for labor and material on the buildings that had been accepted.

A creditor, who had furnished coal to the contractor during construction, having obtained a judgment, secured the appointment of a receiver for the contractor who had become insolvent. The receiver demanded from the owner the $36,000 retained percentage which it was holding, and which was admitted to be then due. The surety made claim to this sum and a suit was instituted by the receiver against the owner, in which the surety interpleaded. The money was paid into court, and the case proceeded between the surety and the receiver. The court below entered judgment for the receiver.

The surety claims the fund because the failure of the contractor to complete the unfinished work or to pay labor and materialmen was such a default in the general contract that under the “equitable doctrine of subrogation,” it succeeded to the contractor’s rights in the contract and to the owner’s right in any securities held by it, as well as to the owner’s right against the contractor ; and, second, because the contract of suretyship or the general indemnity contract obtained by surety operated as an assignment of the retained percentages or created an equitable lien on that fund in the hands of the owner.

*95 To determine the questions involved, it is necessary to ascertain the status of the general contract for the construction of the buildings after they were accepted in January and February, 1930. One building was accepted absolutely, and the other two were accepted but for the work of terracing, sodding, and seeding, ánd subject to the requirement of maintenance for one year from the date of acceptance, to pay for which $10,000 was retained by the owner. By these acts the owner indicated that he considered the buildings entirely completed. As to the work of terracing, sodding, etc., while the provisions of the general contract may apply as to manner and method of performance, once the buildings were accepted, such work may be regarded as the subject of an agreement having the status of a new contract. The surety cannot regard it otherwise as it consented to the arrangement between contractor and owner.

Under these circumstances, there was no default in the contract to complete the buildings; they had been accepted. Nor could there be as to any part of the work that had been performed in connection with the buildings prior to their acceptance. If there was a later default, it was in connection with the unfinished terracing, sodding, etc., and the owner had taken a specific sum to pay for the cost of this work. After paying for it there remained a balance of $1,300 over its cost, such cost including the maintenance item of $6,275.

May the surety now take the $36,000 the percentage retained by the owner as security against any loss from defective workmanship, etc., because of the contractor’s failure to complete the sodding, terracing, etc.? While the failure of the contractor to complete these items and maintain the buildings for a year after they were accepted may have been a default as to such work, it was not one as to the general contract for the completion of the buildings. Such default, even if the surety had been required to complete the unfinished work of sodding, etc., under the terms of the general contract between *96 tlie owner and contractor, or was likewise required to complete under tlie terms of its bond, would not entitle the surety to the retained percentage to reimburse itself for the sums paid for labor and material on the general contract. The obvious reason is that as to such unfinished work the surety was fully paid and did not lose a dollar. The surety, in completing without loss the unfinished work, stands exactly in the same position as to the retained percentages as if the contractor had completed his contract and had failed to pay labor and materialmen, whom the surety had thereafter paid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Topaz Mutual Co. v. Marsh
839 P.2d 606 (Nevada Supreme Court, 1992)
Pittsburgh National Bank v. Lomb (In Re Lomb)
74 B.R. 711 (W.D. Pennsylvania, 1987)
U. S. Steel Homes Credit Corp. v. South Shore Development Corp.
419 A.2d 785 (Superior Court of Pennsylvania, 1980)
B. Bornstein & Son, Inc. v. R. H. MacY & Co.
420 A.2d 477 (Superior Court of Pennsylvania, 1980)
United States v. Commonwealth of Pa., Dept. of Highways
349 F. Supp. 1370 (E.D. Pennsylvania, 1972)
Armour Rentals, Inc. v. General State Authority
287 A.2d 862 (Commonwealth Court of Pennsylvania, 1972)
American Seating Co. v. Philadelphia
256 A.2d 599 (Supreme Court of Pennsylvania, 1969)
Arkwright Mutual Insurance Co. v. Bargain City, USA, Inc.
251 F. Supp. 221 (E.D. Pennsylvania, 1966)
Jacobs v. Northeastern Corp.
206 A.2d 49 (Supreme Court of Pennsylvania, 1965)
Hartford Accident & Indemnity Co. v. State Public School Building Authority
26 Pa. D. & C.2d 717 (Dauphin County Court of Common Pleas, 1961)
Atlantic Refining Co. v. Continental Casualty Co.
183 F. Supp. 478 (W.D. Pennsylvania, 1960)
Philadelphia Industrial Corp. v. Upper Dublin Township
169 F. Supp. 725 (E.D. Pennsylvania, 1959)
White v. New York State Natural Gas Corp.
191 F. Supp. 38 (W.D. Pennsylvania, 1958)
Union National Bank of Pittsburgh v. Dillsburg Borough Authority
81 Pa. D. & C. 404 (York County Court of Common Pleas, 1951)
Continental Casualty Co. v. City of Pittsburgh
68 F. Supp. 805 (W.D. Pennsylvania, 1946)
McHugh v. Landherr
52 Pa. D. & C. 481 (Philadelphia County Court of Common Pleas, 1945)
In Re L. H. Duncan & Sons
127 F.2d 640 (Third Circuit, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
166 A. 365, 311 Pa. 90, 1933 Pa. LEXIS 492, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sundheim-v-philadelphia-school-district-pa-1933.