Callan v. Empire State Surety Co.

129 P. 978, 20 Cal. App. 483, 1912 Cal. App. LEXIS 250
CourtCalifornia Court of Appeal
DecidedDecember 3, 1912
DocketCiv. No. 1102.
StatusPublished
Cited by21 cases

This text of 129 P. 978 (Callan v. Empire State Surety Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Callan v. Empire State Surety Co., 129 P. 978, 20 Cal. App. 483, 1912 Cal. App. LEXIS 250 (Cal. Ct. App. 1912).

Opinion

KERRIGAN, J.

The plaintiffherein entered into a building contract with certain contractors, by the terms of which the latter promised and agreed for and in consideration of the sum of seven thousand dollars to furnish all the material and labor necessary to build and complete, according to plans and specifications, a two-story frame building within seventy-five working days. Plaintiff agreed to pay in installments as the work progressed. Upon the execution of the contract the defendant Empire State Surety Company (appellant), as surety, executed a bond in the sum of $1,750, which recited that the contractors had entered into this contract with plaintiff, describing it and having a copy thereof attached, and which was conditioned that if the principals “shall well, truly and faithfully comply with all the terms, covenants and con *485 ditions of said contract on their part to he kept and performed according to its tenor, then this obligation to be null and void, otherwise to be and remain in full force and virtue in law.”o The contractors, after performing a portion of the work and receiving the first payment as prescribed in the contract, abandoned it, leaving debts for materials and labor, for which liens and claims accrued. These were paid by the plaintiff, who completed the structure.

The action was brought to recover the sum of $921.80 as damages from the Empire State Surety Company and the contractors, such sum being claimed to be the reasonable and necessary excess cost to plaintiff of completing the building, together with the further sum of three hundred and eighty dollars damages for loss of rentals caused by the delay and failure of the contractors to complete the structure within the time fixed by the contract. No appearance was made on behalf of the contractors.

Plaintiff recovered judgment against the appellant herein as surety upon its bond in the sum of $1,301.80, the full amount prayed for in the complaint.

Several points are urged by the appellant for a reversal of the judgment and order denying a new trial, the main contention, however, being that the surety company is not bound, by the terms of its undertaking, to indemnify the plaintiff against loss arising from the payment by him of claims and mechanics ’ liens. It is contended by appellant that its bond and undertaking was for the performance of the agreement of the contractors to furnish materials and labor, and that as neither the agreement nor the bond provided that the contractors or surety should pay or discharge any claims or liens for materials or labor furnished upon the structure, it is not ineuim bent upon appellant to perform this condition. In other words, the appellant claims that when the material and labor were furnished their contract was complied with, and that it had not obligated itself to protect the owner against the costs of material and labor used in the construction of the building.

In support of this contention we are cited to the elementary proposition of law that sureties are never bound beyond the strict letter of their contract; that they have a right to stand upon the precise terms of their agreement, and that there is *486 no authority for extending their liability beyond the stipulation to which they have chosen to bind themselves.

What was the contract? Upon the execution of the bond appellant became a party to the contract and was bound by its provisions. A bond may incorporate, by reference expressly made thereto, other contracts or written instruments; or it may be conditioned for the performance of agreements set forth in such instruments, in which case the bond and papers referred to should be read together and construed as a whole (5 Ency. of Law and Proc., 757, and cases cited). This being so, what construction should be put upon the agreement, of which the bond was a part, to furnish all labor and material necessary to build and complete the house? Can it be said that where a contractor agrees to furnish all the labor and materials necessary to build and complete a house, he may comply with this requirement by simply placing the materials upon the ground, engaging the labor, and leaving the owner to pay therefor, or permit a lien to stand against his property?

Under its contract the surety company bound itself that the contractors would furnish the materials and erect the structure, and faithfully comply with all the terms, covenants, and conditions of the contract. To our mind this case would be easy of solution were it not for the decision in Boas v. Maloney, 138 Cal. 105, [70 Pac. 1004], where the precise question arose and was determined. There the contract provided that in consideration of a sum to be paid in certain installments, Maloney was to furnish the necessary labor and materials, and perform and complete in a workmanlike manner all the new work and repair, etc., according to plans and specifications. The bond given, after reciting certain conditions o'f the contract, provided: “Now, therefore, if saidjMaloney shall well and truly perform, observe, abide by each and all the covenants, provisions and obligations contained in said contract, then this obligation shall be discharged and of no further force or effect, but otherwise it shall remain in full force and effect,” etc. It will be noticed that the facts are on all fours with the present case so far as the contract itself is concerned. The court said:

‘ ‘ The sureties are to be held according to the strict terms of their contract, and it cannot be extended by implication so as to make them liable beyond its terms. Maloney agreed to build and construct the house for $2.850. He did the work *487 according to the contract, and has not claimed any more than the $2,850. He furnished the labor and materials, and did not pay for them, and hence the liens were' filed. The amount due for the labor and materials was due from Maloney, and not by the plaintiff. The bond did not provide that the building should’ be delivered up free from liens. The plain- ■ tiff did not require nor did Maloney put such clause in the bond. The fact that the debts due by Maloney became, by virtue of the statute, liens upon the plaintiff’s property did not make the sureties liable. They had not agreed to pay such liens nor to be responsible therefor. ’ ’

The court cited to sustain this conclusion the ease of Gato v. Warrington, 37 Fla. 542, [19 South. 883].

The Maloney case has not been followed in this state or elsewhere, and it, with the Gato case, have been referred to with disapproval in various jurisdictions.

In view of the conclusion we have reached that the Maloney case does not lay do'wn the correct doctrine, a somewhat extended review of the authorities seems appropriate.

In the case of American Bonding Co. v. Pueblo Inv. Co., 150 Fed. 17, [10.Ann. Cas. 357, 9 L. R. A. (N. S.) 557, 80 C. C. A. 97], the court rejects the doctrine expressed in Boas v. Maloney, 138 Cal. 105, [70 Pac. 1004], and Gato v. Warrington, 37 Fla. 542, [19 South.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Amerson v. Christman
261 Cal. App. 2d 811 (California Court of Appeal, 1968)
Balfour, Guthrie & Co. v. Hansen
227 Cal. App. 2d 173 (California Court of Appeal, 1964)
Harm v. Frasher
181 Cal. App. 2d 405 (California Court of Appeal, 1960)
Bekins Moving & Storage Co v. Maryland Cas. Co.
244 P.2d 1100 (Idaho Supreme Court, 1952)
Crane Co. v. Borwick Trenching Corp.
32 P.2d 387 (California Court of Appeal, 1934)
Hollerman Mfg. Co. v. Standard Accident Insurance
239 N.W. 741 (North Dakota Supreme Court, 1931)
Storm & Butts v. Lipscomb
3 P.2d 567 (California Court of Appeal, 1931)
Ryan v. Shannahan
285 P. 1045 (California Supreme Court, 1930)
City of Oakland v. De Guarda
272 P. 779 (California Court of Appeal, 1928)
Sunset Lumber Co. v. Smith
267 P. 738 (California Court of Appeal, 1928)
Fickling v. Jackman
265 P. 810 (California Supreme Court, 1928)
Roberts v. Security Trust & Savings Bank
238 P. 673 (California Supreme Court, 1925)
Somers v. United States Fidelity & Guaranty Co.
217 P. 746 (California Supreme Court, 1923)
Maryland Casualty Co. v. Shafer
208 P. 192 (California Court of Appeal, 1922)
Terry v. Southwestern Building Co.
185 P. 212 (California Court of Appeal, 1919)
W. P. Fuller & Co. v. Alturas School District
153 P. 743 (California Court of Appeal, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
129 P. 978, 20 Cal. App. 483, 1912 Cal. App. LEXIS 250, Counsel Stack Legal Research, https://law.counselstack.com/opinion/callan-v-empire-state-surety-co-calctapp-1912.