Terry v. Southwestern Building Co.

185 P. 212, 43 Cal. App. 366, 1919 Cal. App. LEXIS 753
CourtCalifornia Court of Appeal
DecidedSeptember 26, 1919
DocketCiv. No. 3032.
StatusPublished
Cited by12 cases

This text of 185 P. 212 (Terry v. Southwestern Building Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Terry v. Southwestern Building Co., 185 P. 212, 43 Cal. App. 366, 1919 Cal. App. LEXIS 753 (Cal. Ct. App. 1919).

Opinion

*368 BRITTAIN, J.

The appellants, owners of real property in Los Angeles, on which a building had been constructed, commenced this action in the nature of a suit in interpleader, joining as defendants the building contractor, its surety, and numerous lien claimants. The surety was dismissed from the action by the trial court, certain lien claimants were given judgment against the contractor, and the amounts of their several judgments were decreed to be liens on the plaintiffs’ property, which was ordered to be sold to satisfy them. The plaintiffs’ appeal is on two grounds; first, that the court erred in dismissing the action as to the surety, and, second, that the judgment is not supported by the findings in three particulars which will be defined later in .this opinion.

The action is of such an unusual character that it is necessary to an understanding of the appellants’ contentions to state the essential facts upon which the suit was brought, as well as briefly to indicate the salient features of the litigation.

The Southwestern Building Company contracted to erect on the plaintiffs’ property a building to cost six thousand dollars. The last one thousand five hundred dollars payment was to be made thirty-five days after the completion. [1] On the day the contract was executed the contractor, Southwestern Building Company, as principal, and National Surety Company, as surety, executed a bond running to the plaintiffs, for three thousand dollars. It referred to the contract and contained numerous conditions relating to the work and limiting the liability of the surety. It was not “conditioned for the payment in full of the claims of all persons performing labor upon or furnishing materials to be used in such work,” and it was not by its terms “made to inure to the benefit of any and all persons” who might perform labor upon or furnish materials to be used in the work described in the contract, as provided by section 1183 of the Code of Civil Procedure. On the other hand, it contained the express condition “that no right of action shall accrue upon or by reason hereof to or for the use or benefit of any one other than the obligee herein named, and that the obligation of the company is and shall be construed strictly as one of suretyship only.” This was not such a bond as relieved *369 the owner from liability of his property for liens under the statute.

Before the final payment the owners began this action. They alleged they had the fund of one thousand five hundred dollars retained under the contract, which was set forth with a copy of the bond. They alleged the defendants other than the Surety Company claimed interests in the fund and claimed liens, that the plaintiffs were ignorant concerning the defendants’ respective rights, and that the defendants threatened a multiplicity of suits. They prayed the defendants be restrained from taking any proceedings on account of their demands and liens, that they be required to interplead, that the one thousand five hundred dollars be adjudged to be the sum to be paid by the plaintiffs, that upon payment of that sum they and their property be relieved of all further obligations, and that judgment be entered in favor of the plaintiffs “and in favor of said defendants who establish their claims of lien against said premises, against the defendant, National Surety Company, for any amount which they may be entitled to in excess of said fund of one thousand five hundred dollars,” and for general relief.

The demurrer of the National Surety Company was overruled. The lien claimants, or at least some of them, answered and cross-complained upon their respective liens. There was no formal order of interpleader. The case was sent to a referee to take evidence, which is not before this court. The report of the referee, which was adopted as the findings of fact, while perfectly clear in its meaning, was not drawn with the technical nicety of language which might have been used. For instance, the report stated “that the following claimants furnished repairs or materials, or both, on the property of the plaintiffs, and that said repairs and materials were actually used in the construction of said building, and' that the charge for said materials was a reasonable charge thereon, and said mechanics’ liens were recorded within the time required by law,” following which was a list referring to the respective claims by exhibit letters, giving the respective dates of filing the liens to which the reference was made, and tabulating the respective amounts for which claims were approved.

[2] The appellants contend that these findings do not support the judgment because they do not contain the direct *370 statement that the amounts of the claims listed were owing or unpaid. It appears from the record that no exceptions were filed to the findings of the referee, and the court adopted them as its own, adding thereto what were designated as conclusions of law, in which, among other things, it is stated “that said lien claimants are entitled to enforce liens upon the real property described in plaintiffs’ complaint for the payment of the several amounts found due them respectively as hereinbefore set forth.” This statement amounts to a finding of fact that the sums were due, although included with the conclusions of law, and in such a case the judgment should not be reversed. (Lange v. Waters, 156 Cal. 142, [19 Ann. Cas. 1207, 103 Pac. 889].) [3] The entire findings and conclusions of law are to be construed to uphold the judgment when, from the facts found, other facts may be inferred which will support the judgment. (Breeze v. Brooks, 97 Cal. 72, [22 L. R. A. 257, 31 Pac. 742]; Pacific States Corp. v. Arnold, 23 Cal. App. 672, [139 Pac. 239].) [4] A judgment will not be 'reversed for want of a finding unless it appears there was evidence, or lack of evidence which required the court to make a finding in favor of the appellant. (Bliss v. Sneath, 119 Cal. 529, [5.1 Pac. 848].) The evidence is not before this court. The appellants make no argument upon this point and do not suggest in their brief that the lien claims were not justly due and unpaid. [5] On the other hand, in their complaint the plaintiffs alleged that they did not know the aetnal amounts due the various claimants, nor whether or not their claims of lien were valid. The lien claimants respectively in their cross-complaints alleged that the labor and material furnished went into the plaintiffs’ building, and that there were due, owing, and unpaid, after deducting all just credits and offsets, the sums claimed by them. The plaintiffs did not deny these allegations, but stipulated that their complaint should stand as their answer to the cross-complaints respectively. The substantial facts were thus admitted by the pleadings, and no finding was necessary. (Higgins v. San Diego Sav. Bank, 129 Cal. 184, [61 Pac. 943].)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Strahorn v. Ellis
165 P.2d 294 (Idaho Supreme Court, 1945)
Mau v. McManaman
85 P.2d 209 (California Court of Appeal, 1938)
Ramey v. Hopkins
33 P.2d 443 (California Court of Appeal, 1934)
Sannes v. McEwan
10 P.2d 81 (California Court of Appeal, 1932)
Luke v. Southern Surety Co.
286 P. 490 (California Court of Appeal, 1930)
Sunset Lumber Co. v. Smith
267 P. 738 (California Court of Appeal, 1928)
Kammerer v. Marino
245 P. 432 (California Court of Appeal, 1926)
Stanward v. Yellow Taxicab Co.
241 P. 902 (California Court of Appeal, 1925)
Levy v. Superior Court
239 P. 1100 (California Court of Appeal, 1925)
Continental National Bank v. Stoltz
189 P. 712 (California Court of Appeal, 1920)
Fawcett v. Nampa & Meridian Irrigation District
187 P. 946 (Idaho Supreme Court, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
185 P. 212, 43 Cal. App. 366, 1919 Cal. App. LEXIS 753, Counsel Stack Legal Research, https://law.counselstack.com/opinion/terry-v-southwestern-building-co-calctapp-1919.