Amerson v. Christman

261 Cal. App. 2d 811, 68 Cal. Rptr. 378
CourtCalifornia Court of Appeal
DecidedMay 6, 1968
DocketCiv. 11352
StatusPublished
Cited by13 cases

This text of 261 Cal. App. 2d 811 (Amerson v. Christman) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Amerson v. Christman, 261 Cal. App. 2d 811, 68 Cal. Rptr. 378 (Cal. Ct. App. 1968).

Opinion

REGAN, Acting P. J.

These appeals arise out of a building construction contract. Defendant Christman agreed to construct a home for plaintiff Amerson for the sum of $24,594.92. Defendant Hartford Accident and Indemnity Company, hereinafter called “Hartford,” was Christman’s surety under a performance bond. Defendant Department of Veterans’ Affairs, hereinafter called “Department,” supplied financing in the sum of $14,000. The trial court awarded damages to Amerson against Christman and Hartford in the amount of $11,931.62.

This ease involves four separate appeals. Amerson first appeals from the trial court’s order sustaining Christman’s demurrer without leave to amend in Action No. 134351, and dismissing the action. Secondly, he appeals from the trial court’s judgment in Action No. 121514 insofar as it declares or adjudicates Amerson's rights and duties with respect to the Department. Thirdly, Amerson appeals from said judgment insofar as it adjudicates or denies his rights to additional compensatory relief against Christman and Hartford. Christman and Hartford also appeal from the judgment and the order denying their motion for a new trial.

*815 Amerson contends that he was denied due process and equal protection of the laws under the Fourteenth Amendment to the United States Constitution in that:

(1) The trial court erred in dismissing his Action No. 134351, and in refusing to allow an amendment to complaint conforming to proof in Action No. 121514, thereby depriving plaintiff of a hearing on distinct and different causes of action;
(2) The trial court erred in finding no contractual breach on the part of Department and denying plaintiff relief where:
(a) Plaintiff duly performed all conditions of the basic agreements;
(b) Department made progress payments to Christman knowing that Christman had not duly performed and knowing of plaintiff’s objections;
(c) Department, with due notice that Christman was in default and that Hartford would take no action to remedy the default, refused to provide funds and allow plaintiff to engage another building contractor pursuant to the contract or a stipulation of the parties;
(d) Department maintains it still has the right to charge plaintiff sums due under the contract even though plaintiff’s right to possession has been delayed and defeated; and
(e) Plaintiff is barred from maintaining an action against Department either to recover his property or to be compensated for its wrongful taking.
(3) The trial court erred in not allowing damages for detriment incurred in addition to the extra cost (calculated in the year 1964) of constructing his home.
Christman and Hartford, on their appeals, contend as follows :
(1) There was a novation on February 17, 1961, 1 limiting any damages plaintiff might recover to the terms of the stipulation entered into on such date.
(2) Findings of fact and conclusions of law are defective and are insufficient to support the judgment.

Facts

Amerson was desirous of constructing a home on a lot he owned in the City of Sacramento pursuant to the provisions of the Veterans’ Farm and Home Purchase Act of 1943. (Mil. & Vet. Code, § 984 et seq.) Under this act, there is a plan whereby the Department may finance the construction of *816 improvements on a lot owned by a California veteran by giving financial aid and by making progress payments to a licensed contractor in installments as the work progresses.

In accordance with the statutory requirements for this plan (Mil. & Vet. Code, § 986.3), Amerson deposited with the Department plans and specifications prepared by an architect; a contract executed by Amerson and Christman, as the contractor, for the construction of improvements in accordance with the plans and specifications (calling for completion of the home within 120 days after commencement of work); and a performance bond executed by Christman and Hartford. The approved plans and specifications also included by reference a document entitled “Description of Materials” to be used in the construction.

Pursuant to the construction contract, Amerson agreed to pay Christman the sum of $24,594.92 for the completion of the improvements. Under the progress payment plan, where the contract cost of the proposed improvements exceeds the amount authorized by the department for financial aid, the veteran must deposit the cash difference in escrow before construction starts. Since the Department was willing to advance only $14,000 toward the cost of construction, funds of Amer-son were deposited with the Department to make up the difference. On April 3, 1959, the Department and Amerson executed a “Building Agreement” wherein Department agreed to advance $14,000 and Amerson agreed to deposit in escrow $10,594.92 for the total construction cost.

Christman commenced construction on April 9, 1959. Thereafter, progress payments were made to Christman on April 27, May 25, and October 9, all in 1959. Each of such payments required the owner’s approval and Amerson signed all three.

However, on the May 25 payment certificate, Amerson listed several exceptions to the materials being used. These defects included: (1) 2x12 support beams were standard grade rather than specified select structural grade; (2) exterior wall sheathing was interior-type plywood of C-D grade rather than specified exterior plywood of better grade; (3) lathing on exterior walls was installed stucco netting rather than specified metal lathe; (4) insulation was mineral wool foiled batts of 2-inch thickness rather than specified Fiberglass-cored foiled batts “compo 3/58”; and (5) drain tile was Orange-burg pipe rather than specified terra cotta.

On the October 9 payment certificate, Amerson crossed out the words signifying his approval and typed in: “See my letter addressed to Mr. M. A. Main on August 15, 1959, and *817 memoranda addressed to the contractor on September 28, 1959, and October 9, 1959.”

Amerson became disenchanted with the materials used in construction and the workmanship on or before May 15, 1959, and dispatched several letters to Christman, complaining of defects and pointing out deviations from the plans and specifications. The parties were unable to get together and sometime on or before June 12, 1959, Christman ceased work. On June 11, Amerson sent a letter to Christman advising him that he had breached the contract, and on June 17, he also advised Hartford that Christman was in default.

According to a settled statement made pursuant to rule 7, the Department did not regard Christman in default, would not make available money to a different contractor, declared it would be the sole judge of whether to make payments to Christman, that it would not allow Amerson to proceed with another contractor, and advised Amerson to get together with Christman and resolve their dispute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mulitz v. L.A. Stucco, Inc. CA2/4
California Court of Appeal, 2016
Consumer Watchdog v. Department of Managed Health Care
225 Cal. App. 4th 862 (California Court of Appeal, 2014)
Hubbard v. State Farm Indemnity Co.
584 S.E.2d 176 (West Virginia Supreme Court, 2003)
Cates Construction, Inc. v. Talbot Partners
980 P.2d 407 (California Supreme Court, 1999)
American Home Assur. Co. v. Larkin Gen. Hosp., Ltd.
593 So. 2d 195 (Supreme Court of Florida, 1992)
Arbor Club of Boca Raton, Inc., Ltd. v. OMEGA CONST. CO.
565 So. 2d 357 (District Court of Appeal of Florida, 1990)
Lawrence Tractor Co. v. Carlisle Insurance Co.
202 Cal. App. 3d 949 (California Court of Appeal, 1988)
Davies MacHinery Co. v. Pine Mountain Club, Inc.
39 Cal. App. 3d 18 (California Court of Appeal, 1974)
Jackson v. Teachers Insurance
30 Cal. App. 3d 341 (California Court of Appeal, 1973)
Lortz v. Connell
273 Cal. App. 2d 286 (California Court of Appeal, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
261 Cal. App. 2d 811, 68 Cal. Rptr. 378, Counsel Stack Legal Research, https://law.counselstack.com/opinion/amerson-v-christman-calctapp-1968.