Stoddard v. Hibbler

120 N.W. 787, 156 Mich. 335, 1909 Mich. LEXIS 591
CourtMichigan Supreme Court
DecidedApril 24, 1909
DocketDocket No. 86
StatusPublished
Cited by11 cases

This text of 120 N.W. 787 (Stoddard v. Hibbler) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stoddard v. Hibbler, 120 N.W. 787, 156 Mich. 335, 1909 Mich. LEXIS 591 (Mich. 1909).

Opinion

Montgomery, J.

The defendant Hibbler entered into a contract with the plaintiffs, by the terms of which he promised and agreed, for and in consideration of the sum of $3,700, to furnish all labor and material necessary to build and complete, according to plans and specifications furnished by party of the first part, a two-family double house. Plaintiffs undertook, in consideration of the [336]*336premises, to pay the consideration price in installments. Upon the execution of this contract the defendant Kibbler, as principal, and the defendant company, as surety, executed a bond in the sum of $2,000, reciting that the principal had entered into a certain contract with the obligee, describing it, and a copy of which was attached to the bond, and conditioned that the principal “shall well and truly indemnify and save harmless.the said obligee from any pecuniary loss resulting from the breach of any of the terms, covenants and conditions of said contract on the part of the said principal to be performed.” The defendant Hibbler abandoned the work after entering upon it, leaving unpaid in the hands of the plaintiffs about $1,300, of which $987.32 was expended in completing the work, but liens amounting to $1,595.94 were filed against the property. This action is brought to recover the amount of these liens. The circuit judge directed a verdict for the plaintiffs, and the defendant surety company brings error.

The sole question raised is whether the surety company is bound by its obligation to indemnify the plaintiffs against loss arising from the payment of mechanics’ liens. It is strenuously insisted that the bond of the defendant is not broad enough to make it liable for mechanics’ liens. Defendant cites, as sustaining this contention, City of Sterling v. Wolf, 163 Ill. 467; Gato v. Warrington, 37 Fla. 542; Boas v. Maloney, 138 Cal. 105; Hughes v. Smith, 114 La. 297; L'Hote Lumber Manfg. Co. v. Dugue, 115 La. 669; Dunlap v. Eden, 15 Ind. App. 575. The case of City of Sterling v. Wolf presents the single question of whether, under a provision in a contract between the city and a sewer contractor that he should furnish all materials, his surety became liable to a third person for materials furnished him. This question was answered in the negative. The case of Hughes v. Smith was an action brought to recover because of the failure to take a sufficient bond as required by the statute of the State. It was held that the bond accepted was not a [337]*337compliance with the terms of the statute. It throws no light upon the question involved in this case. The same thing is true of the case of L’Hote Lumber Manfg. Co.v. Dugue. The case of Dunlap v. Eden was likewise an action brought by a third person, not a party to the bond, and it was held that its terms were not such as to authorize an action brought by such third person. It is obvious, therefore, that none of the cases so far referred to bear . directly upon the question presented.

The case of Gato v. Warrington does give some support to the claim made. In that case one McClatchy entered into an agreement with the appellant by which he agreed to erect, finish, and deliver, on or before January 1,1891, in true, thorough, artisan, perfect, and substantial manner, certain buildings, according to plans and specifications attached. The appellant agreed on his part to pay the sum of #8,260 as follows, viz.: As the work progressed the said J. McClatchy was to submit his weekly pay rolls, duly signed and receipted, also for such material as might be on the ground. McClatchy secured Warrington and Kernan as sureties. They entered into a separate obligation on the same date, whereby they acknowledged themselves held and bound in the sum of #2,000 upon condition that McClatchy would fulfill in every particular the said contract for the erection of the buildings according to plans and specifications, and to deliver the same on or before the date mentioned in the contract, finished in a thorough, artisan, perfect, and substantial manner. It appeared in the case that appellant had not, in making the payments, insisted in all cases upon the pay rolls being presented signed and receipted, and had not limited his payments to material which was on the ground. This departure was urged as one ground of defense. It was also claimed that the bond did not obligate the sureties to indemnify the appellant against liens of mechanics and others. The court said:

“The sureties have a right to stand upon the strict [338]*338terms of their engagement, and we discover no specific agreement on their part to indemnify appellant against liens for work done and material furnished in the construction of the buildings, nor is such a liability contained in the reasonably necessary import of the terms of the obligation.”

Whatever may be said of this reasoning, there was another and sufficient reason given by the court for the conclusion reached. That was, that it was apparent from the contract that, in paying for the construction of the buildings, appellant reserved the right to pay McClatchy, as the work progressed, upon signed and receipted weekly pay rolls, and for material on the ground; and the proof showed that appellant advanced over $3,000 to McClatchy to pay laborers, and not on receipted pay rolls. If appellant paid this rhoney in disregard of the contract, he could not hold the sureties responsible for it, as any material departure from the agreement had the effect of releasing them.

The case of Boas v. Maloney may also be said to be in point. In that case the contract provided that, in consideration of the sum of $2,850, to be paid in certain installments as designated in the contract, Maloney was to furnish the necessary labor and materials, including tools, implements, and appliances required, and perform and complete in a workmanlike manner all the new work and repairing, plumbing, painting, plastering, etc., according to the plans and specifications. The bond given, after reciting certain conditions of the contract, provided:

“ Now, therefore, if said P. Maloney shall well and truly perform, observe, and abide by each and all of the covenants, provisions, and obligations contained in said contract, then this obligation shall be discharged and of no further force or effect, but otherwise it shall remain in full force or effect,” etc.

The court said:

“The sureties are to be held according to the strict terms of their contract, and it cannot be extended by im[339]*339plication so as to make them liable beyond its terms. Maloney agreed to build and construct the house for $2,850. He did the work according to the contract, and has not claimed any more than the $2,850. He furnished the labor and materials, and did not pay for them, and hence the liens were filed. The amount due for the labor and materials was due by Maloney, and not by the plaintiff. The bond did not provide that the building should be delivered up free from liens. The plaintiff did not require, nor did Maloney put such clause in the bond. The fact that the debts due by Maloney became, by virtue of the statute, liens upon plaintiff’s property, did not make the sureties liable. They had not agreed to pay such liens, nor to be responsible therefor.”

The court cited to sustain this contention the case of Gato v. Warrington, supra.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seaboard Surety Co. v. Standard Accident Insurance
14 N.E.2d 778 (New York Court of Appeals, 1938)
Seaboard Surety Co. v. Standard Accident Insurance
252 A.D. 285 (Appellate Division of the Supreme Court of New York, 1937)
Shaner v. Swind
92 F.2d 153 (Third Circuit, 1937)
Anderson Lumber Co. v. Miner Township School District
230 N.W. 23 (South Dakota Supreme Court, 1930)
Howard v. Fisher
283 P. 1042 (Supreme Court of Colorado, 1929)
Village of Argyle v. . Plunkett
124 N.E. 1 (New York Court of Appeals, 1919)
Fellows v. Errington
186 Iowa 322 (Supreme Court of Iowa, 1919)
Empire State Surety Co. v. Lindenmeier
54 Colo. 497 (Supreme Court of Colorado, 1913)
Callan v. Empire State Surety Co.
129 P. 978 (California Court of Appeal, 1912)
City of Alpena ex rel. Zess v. Title Guaranty & Surety Co.
123 N.W. 536 (Michigan Supreme Court, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
120 N.W. 787, 156 Mich. 335, 1909 Mich. LEXIS 591, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stoddard-v-hibbler-mich-1909.