Castro v. Malcolm

226 P. 976, 66 Cal. App. 635, 1924 Cal. App. LEXIS 486
CourtCalifornia Court of Appeal
DecidedApril 19, 1924
DocketCiv. No. 2700.
StatusPublished
Cited by4 cases

This text of 226 P. 976 (Castro v. Malcolm) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Castro v. Malcolm, 226 P. 976, 66 Cal. App. 635, 1924 Cal. App. LEXIS 486 (Cal. Ct. App. 1924).

Opinion

PLUMMER, J.

On the thirteenth day of June, 1916, an agreement was entered into between the county of Kern, acting through its board of supervisors, as the party of the first part, and the Coast Construction Company, a partnership consisting of Stephen V. R. Malcolm and others, as party of the second part, for the construction and improvement of 7.56 miles of that certain highway in the county of Kern known as and called the McKittrick-Marieopa road, for the estimated sum of $44,766.15, to which was thereafter added, as extras, the sum of $1,017.42. At the same time, and as a part of the same transaction, there was delivered to the board of supervisors of said county, of Kern and made a part of said agreement two certain bonds, executed by the American Surety Company of New York, the cross-complainant and respondent *637 in this action. One of said bonds was for the faithful performance of said contract and executed in the sum of $11,191.54. The second bond was given for the security of materialmen and laborers and was in the sum of $22,383.08.

The agreement was conditioned in the usual form and provided for progress payments in the sum of seventy-five per cent of the estimated value of the work and the retention by the county of Kern of the sum of twenty-five per cent until thirty-five days after the final completion of the work agreed to be performed. The bonds were conditioned as is usual in such cases.

Thereafter, and on or about the thirtieth day of June, 1916, the Coast Construction Company, the contractor in the agreement above mentioned, entered into an agreement with the Empire Securities Company, the appellant in this action, whereby the execution of the contract for the work above provided to be done by the Coast Construction Company was set forth, also the execution of the two bonds given by the American Surety Company of New York. The amount of the contract and other matters were set forth. It was mentioned that the contractor desired to borrow money for the purpose of enabling the contractor to carryout the aforesaid contract and the Securities Company was willing to lend money for that purpose. It was agreed that the Securities Company would advance to the contractor in installments, as requested from time to time, money not in excess of seventy-five per cent of the work done and materials furnished under the aforesaid contract, etc.; it was further provided that an agent of the Securities Company might be at all times upon the work with authority limited to the keeping of the time of employees, the paying of bills for labor and material and seeing that all labor and material previously furnished had been paid for, etc. As security for such advances, the agreement assigned to the Securities Company all the right, title and interest of the contractor in and to the moneys that might become due and payable under the agreement for the improvement of the road above mentioned.

Under this agreement with the contractor the Securities Company loaned the sum of $32,284.65, all of which was *638 entered into and became a part of the general banking account of the Coast Construction Company.

The contractor entered upon the performance of the work early in July, 1916, and proceeded with the same until on or about the eleventh day of December, 1916, when it abandoned the same and discontinued work thereunder. At the time of the abandonment of the work, five units, upon which seventy-five per cent estimates, had been made, were completed. Of these, four estimates in the aggregate of $20,304.94 had been paid. The fifth estimate, approved by the highway commission, but not by the board of supervisors, in the sum of $3,867.25, remained unpaid. It is this sum that is in controversy in this action. The trial court awarded this sum to the American Surety Company, and it is from this part of the judgment or decree of the trial court that the Securities Company appeals.

At the conclusion of the trial it was adjudged that laborers and materialmen had enforceable claims against the Surety Company in the total sum of $15,703.38. It was also found by the trial court that, at the time of the abandonment of the contract the status of the contract and the amount of money still in the county treasury in the county of Kern was as follows:

“Contract price ............................$44,766.15
Extras ..................................... 1,017.42
Total .....................................$45,783.57
Payments to contractor....................... 20,304.94
Balance available for completion............$25,478.63

The amount last stated was made up as follows:

Retained percentages ...............$ 8,057.39
Fifth estimate, approved by Highway Commission but not by Supervisors, exclusive of retained percentage of 25 per cent ...................... 3,867.25
Unearned balance of contract price... 13,553.99
Unexpended balance .........................$25,478.63
It was further established that the county of Kern had forfeited such *639 contract and had elected to and did complete the work therein provided for, expending in connection therewith, after allowance of certain credits, the sum of.........................$18,660.26
[Tr. 615]
Leaving in the hands of the county for such disposition as the court might direct, the sum of..........................$ 6,818.37”

As to the payment made by the contractor for labor and material, the trial court found as follows: “Approximately the sunn of $20,000 was proven by said contractors to have been expended in connection with, said contract, but a substantial part of said last-named amount was expended for purposes other than material and labor. Whether such sum was paid from the fund so furnished by said Empire Securities Company, or from moneys borrowed by said contractors from other sources, because of the mingling of said funds, to the knowledge, and with the consent of said, Empire Securities Company, it is impossible to determine.”

The trial court also found that the Securities Company, at the time of the assignment of $3,867.25 was made to it by the Coast Construction Company, advanced nothing of value and did not pay out any money represented or covered by said assignment towards the discharge of the claims of the materialmen for the payment of labor on account of the improvement of said highway; that the only promise made by the Empire Securities Company was that, if a representative of the Coast Construction Company would go to Bakersfield and there assign to the Empire Securities Company said claim or estimate in the sum of $3,867.25, the Empire Securities Company would then consider the making of a further advance. This advance was desired to meet a pay-roll of the Construction Company then due. This advance was never made.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Fid. & Guar. Co. v. OAK GROVE UNION SCH. DIST. OF SONOMA CTY.
205 Cal. App. 2d 226 (California Court of Appeal, 1962)
Street v. Pacific Indemnity Co.
79 F.2d 68 (Ninth Circuit, 1935)
Fairbanks v. Crump Irrigation & Supply Co.
291 P. 629 (California Court of Appeal, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
226 P. 976, 66 Cal. App. 635, 1924 Cal. App. LEXIS 486, Counsel Stack Legal Research, https://law.counselstack.com/opinion/castro-v-malcolm-calctapp-1924.