Guthrie Investments, Inc. v. Bennett

388 P.2d 955, 63 Wash. 2d 697, 1964 Wash. LEXIS 531
CourtWashington Supreme Court
DecidedJanuary 30, 1964
Docket36676
StatusPublished
Cited by1 cases

This text of 388 P.2d 955 (Guthrie Investments, Inc. v. Bennett) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Guthrie Investments, Inc. v. Bennett, 388 P.2d 955, 63 Wash. 2d 697, 1964 Wash. LEXIS 531 (Wash. 1964).

Opinion

Rosellini, J.

On June 17, 1958, one Russell B. Owens, doing business as Russ Owens Plumbing & Heating Service, hereafter referred to as Owens, entered into a contract with Burl Johnson and Associates, a partnership, by the terms of which Owens as a subcontractor agreed to do certain *698 plumbing work required under a housing contract with the federal government. The Owens contract price was payable in monthly estimates with 10 per cent of each estimate to be retained by Burl Johnson and Associates until completion of the work to its satisfaction. Burl Johnson and Associates reserved the privilege of paying materialmen and laborers directly if, in its opinion, there was cause for such action.

For the purpose of financing the work under this subcontract, Owens established a line of credit with the First National Bank in Spokane, and pursuant thereto the bank advanced money from time to time to Owens. Repayment of the loans was guaranteed by the respondent. As security, Owens assigned all proceeds and earnings under his subcontract. This assignment was accepted by Burl Johnson and Associates on July 3, 1958. At this time, there was on file in the office of the Secretary of State an effective Notice of Assignment of Accounts Receivable, duly executed by Owens.

Owens failed to repay all of the money advanced by the bank, and the respondent was required to pay to the bank the total sum of $41,106.80. It recovered a judgment against Owens for this amount.

In the meantime, on August 4, 1958, the appellant Carl Bennett became the surety for Owens on a payment and performance bond agreement in favor of Burl Johnson and Associates. On August 14, 1959, Owens defaulted on his subcontract. At this time, Burl Johnson and Associates had in its possession the sum of $59,223.17, this sum having been earned by Owens and retained by Burl Johnson and Associates as provided by their agreement. Burl Johnson and Associates called upon the appellant Carl Bennett to complete the Owens subcontract; but he declined to do so and required Burl Johnson and Associates to complete the work and charge the expense for accumulated bills and completion work against the retained fund. This use of the fund exhausted it so that the respondent could not recover from it the sum advanced under its guaranty agreement.

*699 Thereafter the respondent brought this action alleging that the appellant had been unjustly enriched when Burl Johnson and Associates paid completion costs out of the retained fund to which the respondent had a prior claim. The trial court held that, while Burl Johnson and Associates had a right under its contract with Owens to pay these costs directly, as between the respondent and appellants, the respondent’s right to reimbursement from the retained fund took precedence over any right of the appellants to have the costs of completion paid from the fund.

The appellants contend that the trial court erred in so holding. They rely upon the cases of United States Fidelity & Guar. Co. v. Montesano, 160 Wash. 565, 295 Pac. 934, and Levinson v. Linderman, 51 Wn. (2d) 855, 322 P. (2d) 863. In the first of these cited cases, a contract to construct a bridge for the city of Montesano provided for the retention of 15 per cent of the amount earned for a period of 30 days following the completion and acceptance of the entire work by the city. This was in accordance with Rem. Comp. Stat., § 10320, which required that such a percentage be retained, and which gave to labor and materialmen a lien on the fund. We held that the surety who was required to pay claims of labor and materialmen was subrogated to their rights in the retained fund. There is no statutory lien involved in this case.

In the case of Levinson v. Linderman, supra, a school construction contract provided that the proceeds could not be assigned without the consent of the school district. When the contractor defaulted, the surety completed the contract. In an action to determine rights to moneys which the school district deposited in court, an assignee or a single progress payment contended that it was entitled to earned funds which had been in the hands of the school district at the time of the default. This court held that the assignment, having been given without the consent of the school district, was void. In this case, there was no restriction on the right to assign and the contractee consented to the assignment of Owens’ earnings under the contract. The Levinson case, *700 therefore, does not provide the answer to the question presented here.

The applicable rule is found in Northwestern Nat. Bank of Bellingham v. Guardian Cas. & Guar. Co., 93 Wash. 635, 161 Pac. 473. In that case a bank took from a contractor on public works, prior to notice of nonpayment for labor and materials, assignments of all moneys to become due to the contractor as security for advances to the contractor. The contract contained no provision for a reserve of any percentage as security for labor and material claims but merely permitted the city to withhold payment until satisfied that all labor and material claims had been paid. This court held that the assignments were valid appropriations of the balance due upon the contract, paid into court by the city upon completion of the work, and were' prior and superior to any rights of laborers and materialmen, and hence superior, to any right of subrogation in the surety on the contractor’s bond. After quoting language from Maryland Cas. Co. v. Washington Nat. Bank, 92 Wash. 497, 159 Pac. 689, we said:

“. . . This is a distinct holding that it is only where there is á clear and express reservation in the contract of a fund to be held up for the benefit of laborers and material-men that there is any . fund the contractor may not effectually assign by an assignment made prior to his default and notice of such default to the board or, as in this case, to the city, and that it is only as tó such reserve fund that the labor and material claims have any priority over such assignments, hence only as to such.reserve funds that'there is any right of subrogation in favor of the bondsmen. ...”

In that case, as in this, the contractee reserved the right to pay laborers and materialmen direct, but there was no provision for the withholding of part of the earned amount for the express purpose of paying them. It is true that in this case the contract unlike' that involved in the Northwestern Nat. Bank case, supra, provided for the retention of a percentage of the earnings, but it was retained for the protection of the contractee, not the laborers and material-men, and therefore the same rule is applicable:

*701 Under their suretyship undertaking, the appellants were obliged to pay the laborers and materialmen if Owens did not do so; and the assignment of earnings held by the respondent was not subject to the claims of such creditors.

In the case of Hall & Olswang v. Aetna Cas. & Surety Co., 161 Wash. 38, 296 Pac.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Partee
170 P.3d 60 (Court of Appeals of Washington, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
388 P.2d 955, 63 Wash. 2d 697, 1964 Wash. LEXIS 531, Counsel Stack Legal Research, https://law.counselstack.com/opinion/guthrie-investments-inc-v-bennett-wash-1964.