Hardin County Sav. Bank v. United States

65 F. Supp. 1017, 106 Ct. Cl. 577
CourtUnited States Court of Claims
DecidedJune 3, 1946
StatusPublished
Cited by21 cases

This text of 65 F. Supp. 1017 (Hardin County Sav. Bank v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hardin County Sav. Bank v. United States, 65 F. Supp. 1017, 106 Ct. Cl. 577 (cc 1946).

Opinions

LITTLETON, Judge.

This case is now before the court under section 148, Judicial Code, Title 28, U.S. C.A. § 254, on the merits of the conflicting claims of the Hardin County Savings Bank and the Massachusetts Bonding and Insurance Company to a balance of $Z8,655.12 due in whole or in part to one of these parties under a construction contract between one Ben B. Hogenson and the United States, acting through the Quartermaster Corps, U. S. Army, War Department. See Hardin County Savings Bank et al. v. United States, 102 Ct.Cl. 815.

The contract between Hogenson and the Government was dated June 28, 1941, and called for the construction and completion by Hogenson of a C. M. field office, including the utilities thereto, at the Savanna Ordnance Depot, Proving Ground, Illinois, for a lump sum consideration, as modified, of $42,130. The plaintiff, Massachusetts Bonding and Insurance Company, hereinafter sometimes referred to as the “Bonding Co.,” and as the “Surety,” became surety on this contract and on July 19, 1941 executed and delivered to the Government a payment bond and a performance bond each in the sum of $21,446 (finding 4). Hogenson entered upon the performance of the contract but was unable to complete the work called for thereby because of financial difficulties and on or about October 19, 1941, the plaintiff, Bonding Co., had to take over and complete the work, and it did so at its own expense under the terms and conditions of its bonds (findings [1019]*101915-23). Prior thereto and during the last part of July 1941, Hogenson carried on negotiations with plaintiff, Hardin County Savings Bank, hereinafter sometimes referred to as the “Bank,” for a loan or loans and agreed to give the Bank, among others, an assignment under his contract with the Government for the Savanna job. Hogenson’s formal application for credit was presented to the Bank late in July and the first loan by the Bank of $5,000 was made August 5, 1941, (finding 6) which, together with further loans to and including October 14, 1941, amounted to a total of $20,012.50 (findings 6-13). Certain payments amounting to $6,762.50 on these loans were received by the Bank between October 10 and 18, 1941, as tabulated in finding 13, which reduced the totals of the loans to $13,250, and no further payments have been received by the Bank. In the meantime, as agreed in July, the assignment by Hogenson to the Bank, under authority of article 22 of the Contract and the Assignment of Claims Act of 1940, Act of Oct 9, 1940, 54 Stat. 1029, 41 U.S. C.A. § 15, was prepared and executed by Hogenson on August 16, 1941 (finding 9). This assignment was, so far as here material, as follows:

“Whereas, Hogenson Construction Company of Belmond, Iowa, has entered into a contract to construct a C. M. Field Office, Savanna Ordnance Depot, Proving Ground, Illinois, which building is now in the process of construction, and which has not yet been finally accepted, by the Government of the United States of America, and

“Whereas, Ben B. Hogenson desires to assign all funds now due or to become due, including both the retained percentage and all monthly estimates under said contract to the Hardin County Savings Bank, of Eldora, Iowa, for the purpose of obtaining credit at said bank.

“Now, Therefore, the Constructing Quartermaster, Savanna Ordnance Depot, Proving Ground, Illinois, is hereby directed to make payment of all funds due and to become due under said contract, to the Hardin County Savings Bank, of Eldora, Iowa, at such times as the said retained percentage and monthly estimates shall, by the terms of said contract, the completion of the work, and the payment of claims for material and labor, become due and payable.”

Article 16 of Hogenson’s contract provided that “partial payments will be made as the work progresses at the end of each calendar month, or as soon thereafter as practicable, on estimates made and approved by the contracting officer,” less 10 percent of each estimate to be retained until final completion and acceptance of all work. This article further provided that “upon completion and acceptance of all work required hereunder, the amount due the contractor under this contract will be paid upon the presentation of a properly executed and duly certified voucher * * Hogenson’s operations under the Government contract for the Savanna job continued until sometime during the week of October 15-22, when work under the contract stopped and Hogenson’s employes left the job because Hogenson was without funds and the plaintiff Bank had stopped payment on certain payroll checks which had been given by Hogenson because Hogenson’s funds in the bank had been exhausted. A number of subcontractors were unable to meet their pay rolls.

At this point the plaintiff Bonding Company, upon finding that Hogenson could not and did not intend to complete the work, began making arrangements to take over and complete the contract and was advised by the constructing officer about October 22 (finding 19), “that there was nobody on the job and that unless something was done immediately the army would have to make arrangements to take over the job and have it completed, or to complete the job itself.”

Pursuant to the assignment of August 16, supra, defendant paid to the plaintiff Bank progress payment estimates Nos. 1, 2 and 3, totaling $13,474.88, for work performed and material placed on the job by Hogenson prior to his default in the amounts of $4,566.33 on September 3; $2,-109.46 on September 9, and $6,799.09 on October 8, 1941, and, with the exception of $6,312.50 out of progress payment No. [1020]*10203, the Bank placed these three payments to Hogenson’s credit in his checking account in that bank. On October 18, 1941, before any further progress estimate and payment under Hogenson’s contract was prepared or was due by the Government, plaintiff Bank, as its president testified, became nervous about Hogenson’s financial condition and when it “found out that he [Hogenson] was busted on October 18th,” it thereupon closed out Hogenson’s checking account in the Bank by crediting the balance of $450 therein to the unpaid loans. This, with the other credits on the loans from progress payment No. 3, supra, which had been made October 10, 1941, left a balance of $13,250, not including interest, due and unpaid by Hogenson on account of loans totaling $20,012.50 between August 5 and October 14, 1941.

It is this amount of $13,250 plus interest from March 31, 1942, until paid, at the rate of 7 percent per annum, as provided in Hogenson’s notes, which plaintiff Bank seeks to recover out of the contract balance of $28,655.12 in defendant’s hands. The balance of Hogenson’s indebtedness to the Bank plus interest at 7 percent from March 31, 1942, to June 3, 1946 (date of judgment), is $17,122.58,

The question presented by the facts of this case, so far as the Bank’s rights under the assignment are concerned, is the same in principle as the question presented and decided in the case of Modern Industrial Bank v. United States, 101 CtCL 808. In that case the contractor, after commencing work about July 15, 1941, made an assignment on August 5, similar in all respects to the assignment here involved, of “all monies due or to become due from the United States.” This assignment was made to the Industrial Bank as security for a loan and on the basis of which the Bank advanced a total of $38,500 to the contractor between August 8 and October 8, 1941.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rochester Gas & Electric Corp. v. United States
65 Fed. Cl. 431 (Federal Claims, 2005)
United California Discount Corp. v. United States
36 Cont. Cas. Fed. 75,804 (Court of Claims, 1990)
Unity Bank & Trust Co. v. United States
32 Cont. Cas. Fed. 72,612 (Court of Claims, 1984)
Sigmon Fuel Co. v. Tennessee Valley Authority
531 F. Supp. 80 (E.D. Tennessee, 1982)
Great American Insurance v. United States
481 F.2d 1298 (Court of Claims, 1973)
Produce Factors Corp. v. United States
467 F.2d 1343 (Court of Claims, 1972)
Hartford Accident & Indemnity Co. v. State Public School Building Authority
26 Pa. D. & C.2d 717 (Dauphin County Court of Common Pleas, 1961)
National City Bank of Evansville v. United States
163 F. Supp. 846 (Court of Claims, 1958)
Levinson v. Linderman
322 P.2d 863 (Washington Supreme Court, 1958)
National Surety Corp. v. United States
132 Ct. Cl. 724 (Court of Claims, 1955)
National Surety Corporation v. United States
133 F. Supp. 381 (Court of Claims, 1955)
Peterman Lumber Co. v. Adams
128 F. Supp. 6 (W.D. Arkansas, 1955)
Royal Indemnity Co. v. United States
93 F. Supp. 891 (Court of Claims, 1950)
Hardin County Sav. Bank v. United States
65 F. Supp. 1017 (Court of Claims, 1946)

Cite This Page — Counsel Stack

Bluebook (online)
65 F. Supp. 1017, 106 Ct. Cl. 577, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hardin-county-sav-bank-v-united-states-cc-1946.