National City Bank of Evansville v. United States

163 F. Supp. 846, 143 Ct. Cl. 154, 1958 U.S. Ct. Cl. LEXIS 168
CourtUnited States Court of Claims
DecidedJuly 16, 1958
Docket245-56
StatusPublished
Cited by48 cases

This text of 163 F. Supp. 846 (National City Bank of Evansville v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National City Bank of Evansville v. United States, 163 F. Supp. 846, 143 Ct. Cl. 154, 1958 U.S. Ct. Cl. LEXIS 168 (cc 1958).

Opinion

LARAMORE, Judge.

This case comes before the court on cross-motions for summary judgment.

Plaintiff, as assignee on three defaulted contracts, sues for the alleged unpaid balance due at the time of termination for default, plaintiff’s claim being that the defendant could not use any of such balances for completion of the work, since it would in effect be a benefit to the sureties, who had given plaintiff a subrogation agreement.

The facts are summarized as follows: ■On November 26, 1952, Regent Contracting Company, a co-partnership consisting of Raymond W. Ewell, Henry 'Tuller, Julie Tuller and Ralph I. Tuller, ■entered into Contract NOy-74886 with the United States Department of the iNavy, Bureau of Yards and Docks, for the construction of an enlisted men’s barracks and subsistence building at the •United States Naval Air Station, Oceana, Virginia, at a contract price of $2,700,-000, which was subsequently increased to .$2,762,089.15. The contractor gave performance and payment bonds in the respective amounts of $2,700,000 and $1,->080,000, on which Seaboard Surety Company, Employers Reinsurance Corporation, Manufacturers Casualty Insurance Company and Pacific National Fire Insurance Company were co-sureties.

Under the terms of the contract the contractor was to commence work on December 1, 1952, and complete the work on December 1, 1953, which latter date was modified to July 14, 1954; and provision was made for the assessment, in accordance with article 11 of the contract, of liquidated damages in the amount of $995 for each calendar day of delay.

Defendant received notice of assignment to plaintiff of all moneys due to become due under said contract, and receipt of said notice, together with an accompanying instrument as assignment, was acknowledged by defendant on December 15, 1952. Thereafter certain progress payments on said contract were made to plaintiff pursuant to said assignment.

On August 26, 1953, said Regent Contracting Company, a co-partnership, entered into Contract NOy-75695 with the United States Department of the Navy, Bureau of Yards and Docks, for the construction of a 10-bed infirmary at the United States Naval Air Station, Oceana, Virginia, at a contract price of $270,000, which was subsequently decreased to $269,853. The contractor gave performance and payment bonds in the respective amounts of $270,000 and $135,000, on which said Pacific National Fire Insurance Company was the surety.

Under the terms of the contracts the contractor was to commence work on September 1, 1953, and complete the work on May 9, 1954, and provision was made for the assessment, in accordance with article 11 of the contract, of liquidated damages in the amount of $100 per each calendar day of delay.

Defendant received notice of assignment to plaintiff of all moneys due or to become due under said contract, and receipt of said notice, together with an accompanying instrument of assignment, was acknowledged by the defendant on October 5, 1953. Thereafter certain progress payments on said contract were *848 made to plaintiff pursuant to said assignment.

On January 15, 1954, Regent Contracting Company, Inc. entered into Contract NOyr-74835 with the United States Department of the Navy, Bureau of Yards and Docks, for the construction of a steam generating plant at the United States Naval Air Station, Oceana, Virginia, at a contract price of $338,000, which was subsequently increased to $350,423. The contractor gave performance and payment bonds in the respective amounts of $338,000 and $169,000, on which American Fidelity Company and The New Hampshire Fire Insurance Company were co-sureties.

Defendant received notice of assignment to plaintiff of all moneys due or to become due under said contract, and receipt of said notice, together with an accompanying instrument of assignment, was acknowledged by defendant on February 17,1954. Thereafter certain progress payments on said contract were made to plaintiff pursuant to said assignment.

All of the Contracts NOy-74886, NOy75695, and NOy-74835 contained the following provisions:

“Article 6. — Payment and Release
“(a) The Contractor shall be entitled to partial payments hereunder as the work progresses upon the basis of estimates made by the Contracting Officer of the degree of completion. * * *
“(b) The Contractor may submit monthly, or at more frequent intervals, as approved by the Contracting Officer, to the Officer in Charge an itemized request for partial or final payment as the case may be. The Officer in Charge will recommend for the approval of the Contracting Officer an amount which he believes the Contractor is entitled to be paid. Payment shall be made of the amount approved by the Contracting Officer subject to reduction for overpayments or increase for underpayments on preceding payments to the Contractor. The Contracting Officer may in his discretion reseiwe or withhold a percentage (not exceeding 10 percent) of each payment hereunder until the completion of the work and acceptance thereof by the Government or until such earlier time as he may determine.
******
“(d) The obligation of the Government to make any of the payments required under any of the provisions of this contract (including those of Articles 25 and 26) shall, in the discretion of the Contracting Officer, be subject to (1) any unsettled claims against the Contractor for labor or materials, (2) reasonable deductions on account of defects in material or workmanship, and (3) any claims which the Government may have against the Contractor under or in connection with this contract. Any over-payments to the Contractor shall, unless otherwise adjusted, be repaid to the Government upon demand.” “Article 11. — Liquidated Damages
“(a) If the Contractor fails to complete the work or any part thereof within the time specified in Article 1, or applicable extension thereof, it will be difficult or impossible to ascertain the actual damages for the delay and in lieu thereof the Contractor shall pay to the Government as fixed, agreed, and liquidated damages for each calendar day until the delayed work is completed or accepted, the amount as set forth in the specifications or in Article 1. If, after the expiration of the time specified in Article 1, or applicable extension thereof, the Government terminates the right of the Contractor to proceed and does not elect to complete the work, liquidated damages shall be paid as above provided for each calendar day after the time specified in Article 1, or applicable extension thereof, until the effective *849 date of 'the termination of the Contractor’s right to proceed. If the Government terminates the right of the Contractor to proceed and elects to complete the work as provided in Article 25, liquidated damages shall, if the Government exercises due diligence in completing the work, be paid as above provided for each day after the time specified in Article 1, or applicable extension thereof, until the delayed work is completed or accepted. The Contractor and his sureties shall be liable for all such liquidated damages accruing as hereinabove provided.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Collins v. United States
Federal Claims, 2026
Beesley v. United States
Federal Claims, 2023
Kaetz v. United States
Federal Claims, 2022
Jones v. United States
Federal Claims, 2022
Jarvis v. United States
Federal Claims, 2021
Schaeffer v. United States
Federal Claims, 2021
Harper v. United States
Federal Claims, 2020
Fanelli v. United States
Federal Claims, 2020
Dharia v. United States
Federal Claims, 2019
Portnov v. United States
Federal Claims, 2017
Proxtronics Dosimetry, LLC v. United States
128 Fed. Cl. 656 (Federal Claims, 2016)
Jordan v. United States
128 Fed. Cl. 46 (Federal Claims, 2016)
Davis v. United States
Federal Claims, 2016
Widtfeldt v. United States
122 Fed. Cl. 158 (Federal Claims, 2015)
Thompson v. United States
99 Fed. Cl. 21 (Federal Claims, 2011)
Capelouto v. United States
99 Fed. Cl. 682 (Federal Claims, 2011)
Duncan v. United States
98 Fed. Cl. 318 (Federal Claims, 2011)
Hall v. United States
91 Fed. Cl. 762 (Federal Claims, 2010)
Woodson v. United States
89 Fed. Cl. 640 (Federal Claims, 2009)
Kalos v. United States
87 Fed. Cl. 230 (Federal Claims, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
163 F. Supp. 846, 143 Ct. Cl. 154, 1958 U.S. Ct. Cl. LEXIS 168, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-city-bank-of-evansville-v-united-states-cc-1958.