Gray v. Cotton

134 P. 1145, 166 Cal. 130, 1913 Cal. LEXIS 294
CourtCalifornia Supreme Court
DecidedAugust 28, 1913
DocketSac. No. 1963.
StatusPublished
Cited by33 cases

This text of 134 P. 1145 (Gray v. Cotton) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gray v. Cotton, 134 P. 1145, 166 Cal. 130, 1913 Cal. LEXIS 294 (Cal. 1913).

Opinion

SLOSS, J.

Defendants, copartners under the firm name of Cotton Brothers & Co., entered into a contract with the city of Sacramento whereby they agreed to construct a main sewer and laterals in said city. The plaintiff is a subcontractor who entered into an agreement with the- defendants whereby he undertook to do the excavation and back filling necessary for such sewers.

This action was brought to recover the balance claimed to be due under such subcontract, together with certain other sums claimed to be due for extra work done, and damages alleged to have been occasioned by the defendants’ failure to do certain things which they agreed to do.

The plaintiff claimed-on account of excavation and back filling done under the agreement $2,993.70; for extra work in digging a subdrain two thousand dollars; for extra work in excavating for sheet piling two thousand dollars; and for like extra work in digging sumps four hundred and eighty dollars.

The court found in favor of the plaintiff on these items, amounting in all to $7,473.70, and rendered judgment in his favor for this amount. Prom this judgment defendants appeal. The findings were against the plaintiff on the items of damage claimed by him and these matters, therefore, present no question to be considered on this appeal.

*132 The specifications under which the defendants were to do the work for the city are attached to the complaint. They show that the work consisted of furnishing the requisite labor and materials and constructing a trunk line sewer along certain streets in the city of Sacramento and ten lateral sewers. The trunk line sewer was divided into eleven sections. The first four sections and five lateral sewers are those involved in the contract between the parties to this action. The specifications contained the following clauses bearing upon the controversy before us:

“The city engineer shall have full charge and superintendence of the proposed work, set off stakes indicating line of grade and extent of work, make final measurements and estimates and in ease of dispute as to the intent or meaning of these specifications, his interpretation shall be final.
“Excavations shall be made along the lines shown on plan and to the depth necessary for constructing the sewer at the grade indicated on profile. For all vitrified iron stone pipe sewers and re-enforced concrete pipe sewers twenty-four (24) inches in diameter they shall be at least one foot wider at the bottom than the outside diameter of the pipe, and for the re-enforced monolithic concrete and plain monolithic concrete sewers as wide as the greatest external horizontal width of the structure to be placed therein, without any undercutting of the banks . . .
“The contractor shall provide all sheathing, rangers and braces necessary to prevent caving of banks or settlement or disarrangement of any telephone conduits, gas or water-pipes, . . . and shall pump, bail, drain or otherwise prevent water from running or accumulating in the trenches while the foundation is being constructed or while 'concrete or pipe is being laid. . . .
“Where the diameter of the trunk line sewer is twenty-seven (27) inches or over, excavation will be paid for by the cubic yard, the estimate to be made only for the volume included within lines drawn vertically from the ground surface to the exterior surface of the sewer at the springing line and between lines forming the exterior dimensions of the sewer below the springing line. The cost of all excavation of sewers twenty-four (24) inches in diameter or less shall be included in the price per foot of completed sewer.”

*133 The agreement between the plaintiff and the defendants was in the form of a written offer by plaintiff, accepted by the defendants. The material parts of this writing read as follows:

Cotton Bros. & Company,
Oakland, Cal.
Gentlemen:
I hereby agree to furnish the necessary plant, teams and machinery to do all the excavation and back filling necessary for trunk line sewer and lateral main sewers on the contracts as awarded you by the city of Sacramento in accordance with plans and specifications as prepared by city engineer at the rate of forty cents per cubic yard; it being understood that you are to do all necessary pumping and cribbing. The approximate estimate of excavation is 40,000 cu. yds. more or less. . . .
“Payments to be made at the rate of seventy-five per cent monthly upon engineer’s estimate. Balance upon completion and acceptance of each section by the city.
“It is distinctly understood that time shall be of the essence of this contract and all must be prosecuted diligently.
“Respectfully submitted,
“Harry J. Gray.
“Accepted: Cotton Bros. & Co.”

The first count of the complaint alleged, and the court found, that in pursuance of said agreement the plaintiff excavated and back filled on sections 1, 2, 3, and 4 of the trunk line sewer 14,937 cubic yards of earth, and on the five lateral sewers 9,906.3 cubic yards of earth, making a total of 24,843.3 cubic yards. At the agreed rate of forty cents per cubic yard the amount due for these items was $9,937.32, of which it is alleged and found only $6,943.62 has been paid, leaving a balance of $2,993.70. The appellants attack these findings, their position being that the specifications above quoted were expressly referred to and made a part of the contract between the plaintiff and defendants, and that under these specifications the defendants were entitled to claim from the city, and the plaintiff was entitled to claim from the defendants, payment for such excavation only as was shown by the estimates of the city engineer. It appears that the city engineer had made an estimate of 14,238.43 cubic *134 yards for the excavation on main line sewer, and that he estimated the excavation necessary for laterals at 7,515.5 cubic yards. The position of the respondent is that, under his agreement, he was entitled to forty cents for each cubic yard of earth which he actually excavated, irrespective of the estimate of the city engineer.

There can be no doubt of the validity of a provision in a contract for work that the amount to be paid shall be determined by the estimate or certificate of an engineer or other person agreed upon. (Holmes v. Richet, 56 Cal. 309, 313, [38 Am. Rep. 54]; Loup v. California Southern R. R. Co., 63 Cal. 97; Cox v. McLaughlin, 63 Cal. 196 207; City Street Imp. Co. v. Marysville, 155 Cal. 427, [23 L. R. A. (N. S.) 317, 101 Pac. 308].) In the absence of averment and proof of fraud or mistake, the estimate or certificate of such engineer is conclusive upon both parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marriage of Gill CA2/1
California Court of Appeal, 2023
Rodas v. Dept. of Transportation CA4/1
California Court of Appeal, 2021
Shalabi v. City of Fontana
489 P.3d 714 (California Supreme Court, 2021)
Sierra Club v. County of Fresno
California Court of Appeal, 2020
Vardanyan v. Amco Ins. Co.
California Court of Appeal, 2016
Bertoli v. Dennis CA1/5
California Court of Appeal, 2015
Beavers v. Allstate Insurance
225 Cal. App. 3d 310 (California Court of Appeal, 1990)
Austero v. National Casualty Co. of Detroit
84 Cal. App. 3d 1 (California Court of Appeal, 1978)
Hasson v. Ford Motor Co.
564 P.2d 857 (California Supreme Court, 1977)
In Re Marriage of Steinberg
66 Cal. App. 3d 815 (California Court of Appeal, 1977)
O'KELLY v. Willig Freight Lines
66 Cal. App. 3d 578 (California Court of Appeal, 1977)
Turner v. Wexler
538 P.2d 877 (Court of Appeals of Washington, 1975)
Alvarez v. Felker Manufacturing Co.
230 Cal. App. 2d 987 (California Court of Appeal, 1964)
Bohman v. Berg
356 P.2d 185 (California Supreme Court, 1960)
Patrick J. Ruane, Inc. v. Parker
185 Cal. App. 2d 488 (California Court of Appeal, 1960)
Levinson v. Linderman
322 P.2d 863 (Washington Supreme Court, 1958)
Cook v. Saltzer
257 P.2d 228 (Idaho Supreme Court, 1953)
Wilson v. Rhoades
247 P.2d 727 (California Court of Appeal, 1952)
Wilke v. Crofton
209 P.2d 790 (California Supreme Court, 1949)
Valley Construction Co. v. City of Calistoga
165 P.2d 521 (California Court of Appeal, 1946)

Cite This Page — Counsel Stack

Bluebook (online)
134 P. 1145, 166 Cal. 130, 1913 Cal. LEXIS 294, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gray-v-cotton-cal-1913.