Loup v. California Southern Railroad

63 Cal. 97, 1883 Cal. LEXIS 368
CourtCalifornia Supreme Court
DecidedJanuary 26, 1883
StatusPublished
Cited by30 cases

This text of 63 Cal. 97 (Loup v. California Southern Railroad) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Loup v. California Southern Railroad, 63 Cal. 97, 1883 Cal. LEXIS 368 (Cal. 1883).

Opinions

McKee, J.

The complaint in this case contains four counts: The first and fourth are founded upon two special contracts, the third upon a quantum meruit, and the second upon a cause of [98]*98action in the nature of an action on the case for alleged wrongful acts or omissions by the defendant.

There was a demurrer to the complaint, on the grounds that several causes of action had been improperly united, and that none of the counts contained facts sufficient to constitute a cause of action; but the demurrer was overruled.

Several causes of action are unitable in one complaint when they arise upon contract express or implied; and as the first, third, and fourth counts arise out of the. special contracts upon which the action is founded, they belong to the same class and were properly united in the complaint.

But the second count in the complaint is not founded on the contract. Its allegations are, substantially, that the defendant had, according to the terms of the contract, the right to enter at any time, by itself or its agents, upon the premises covered by the contract, and perform any work thereon; that about the 1st of April, 1881, it elected to avail itself of the right, and after notifying the plaintiffs entered upon the premises for the purpose of constructing some culverts on the road; that it kept and held possession of the premises for the space of three months, and unnecessarily delayed and neglected and refused to proceed in a prompt or reasonable manner, or in a reasonable time, to construct said culverts, so as to permit the plaintiffs to do their part of the work, and thereby hindered and delayed plaintiffs in and' about the doing of their work aforesaid; . . . . and by reason of the hinderance and delay caused by the negligent and wrongful acts and omissions of the defendant the plaintiffs have sustained damages in the sum of one thousand dollars,” for which they ask judgment.

In entering upon the premises covered by the contracts the defendant was not guilty of a breach of contract, for the right to enter was reserved by the contracts; but the charge is that the defendant, in exercising its right, “ neglected and refused to proceed in a prompt or reasonable manner, or in a reasonable time,” to perform its work; and for these wrongful acts or omissions the plaintiffs sue. But such acts or omissions constituted a breach of duty, not of contract, out of which arose an obligation and a liability on the part of the defendant to respond to the plaintiffs in damages.

[99]*99A person commits a tort, and renders himself liable to an action for damages, who commits some act not authorized bylaw, or who omits to do something AVhich he ought to do by law, and by such an act or omission either infringes some absolute right, to the enjoyment of which another is entitled, or causes to such other some substantial loss of money, health, or material comfort. (Underhill on Torts, 4.) So Avhenever there is a contract and something to be done in the course of the employment which is the subject of that contract, if there be a breach of duty in the course of the employment, the persons injured by the breach may recover damages in tort. (Cooley on Torts, 91; Courtenay v. Earl, 10 Com. B. 73.)

It therefore seems clear that the cause of action stated in the second count Avas founded on a neglect of duty. The plaintiffs allege that the defendant by its wrongful acts and omissions occasioned them injury, and the action was tried and determined as an action ex delicto; for the court found that the defendant had the right, under the contract, to enter upon the premises and construct the culverts. Where a person has authority to do an act no action Avill lie for doing it, unless in the performance of the act he has violated some duty Avhich he owed to the plaintiffs. And the court finds that there was such a violation of duty, because, in performing the act Avhich it had authority to perform, “the defendant did not proceed in a reasonably diligent or expeditious manner, but greatly delayed in building the culverts, and refused to proceed in a reasonably prompt or expeditious manner thereAvith.” The defendant was therefore guilty of a wrong to the plaintiffs which occasioned damages to them in the sum of one thousand dollars, and that sum the court awarded to the plaintiffs in the general judgment on the causes of action on the contracts. Damages for breaches of contracts and for neglect of duty were thus assessed in the same case; but an action founded on neglect of duty cannot be united in the same complaint Avith actions founded on contracts. (Bowman v. Purtell, 47 N. Y. Supr. Ct. 403; Thompson v. St. Nicholas Bank, 61 How. 163.) The demurrer to the complaint should therefore have been sustained.

Besides, the defendant is sued as a corporation, and in the fourth count of the complaint there is no aATerment of the defendant’s corporate existence.

[100]*100It is a settled rule of pleading that each count must contain in itself facts sufficient to constitute a cause of action; it cannot be helped out by reference to other counts or parts of the complaint for averments which are essential to it as a cause of action. (Collins v. Bartlett, 44 Cal. 371; Kretchbaum v. Melton, 49 Cal. 55.)

Moreover, neither the first nor fourth counts contain any sufficient averment of a breach of the covenant of the defendant to pay, which is contained in the special contracts upon which the causes of action are founded.

It appears by the contracts that Loup and Withers, the respondents, undertook to do the grading and masonry work of some sections of the appellant’s railroad, according to specifications of the work which were incorporated in the contracts, and in conformity to the plans and directions and to the satisfaction and acceptance of the chief engineer of the appellant. The work contracted for was to be commenced and finished within specified dates, for which the appellant agreed to pay, at prices fixed by the contracts, from time to time, “and in the manner and form provided” by the contracts. Those provisions were as follows: —

“ 1st. Estimate of the work shall be made by and under the direction of the engineer at the close of each calendar month, or as soon thereafter as may be, of the amouut and value as near as practicable of work done and material furnished and delivered under this contract according to the prices named herein; and within thirty days after the rendering of such estimates the said company shall pay to the said contractor the amount of said estimates, less previous payments, and less ten (10) per cent.

“ 2d. Also, that the-per cent retained from the above monthly estimates shall in no case be considered due or payable to said contractor until the work herein contracted for is fully completed, in accordance with this agreement, and said percentage may be used by the company in case of apprehended delay, in hastening the completion of the work.

“Upon the completion of all the work herein contracted for, in the time and manner agreed upon, or as soon after said completion as may be, the engineer shall make a final estimate of all the work done, from which shall- be deducted the sum of the [101]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Crane Creek Country Club v. City of Boise
826 P.2d 446 (Idaho Supreme Court, 1992)
Pasadena Unified School District v. Pasadena Federation of Teachers
72 Cal. App. 3d 100 (California Court of Appeal, 1977)
Garmon v. San Diego Building Trades Council
320 P.2d 473 (California Supreme Court, 1958)
Eads v. Marks
249 P.2d 257 (California Supreme Court, 1952)
Barris v. Atlas Rock Co.
5 P.2d 670 (California Court of Appeal, 1931)
Minton v. Mitchell
265 P. 271 (California Court of Appeal, 1928)
Northwestern Hardware & Steel Co. v. Winnett
216 P. 568 (Montana Supreme Court, 1923)
W. H. Blodgett Co. v. Bebe Co.
214 P. 38 (California Supreme Court, 1923)
Hearte v. Glassell Development Co.
189 P. 733 (California Court of Appeal, 1920)
N. Am. Dredging Co. of Nevada v. Outer Harbor Dock & Wharf Co.
173 P. 756 (California Supreme Court, 1918)
Felt City Townsite Co. v. Felt Investment Co.
167 P. 835 (Utah Supreme Court, 1917)
Gray v. Cotton
134 P. 1145 (California Supreme Court, 1913)
Fegtly v. Village Blacksmith Mining Co.
111 P. 129 (Idaho Supreme Court, 1910)
Coplew v. Durand
95 P. 38 (California Supreme Court, 1908)
Davisson v. East Whittier Land & Water Co.
96 P. 88 (California Supreme Court, 1908)
Wyman v. Hooker
83 P. 79 (California Court of Appeal, 1905)
Valley Lumber Co. v. Struck
80 P. 405 (California Supreme Court, 1905)
Los Angeles Railway Co. v. Davis
79 P. 865 (California Supreme Court, 1905)
Roche v. Baldwin
65 P. 459 (California Supreme Court, 1902)

Cite This Page — Counsel Stack

Bluebook (online)
63 Cal. 97, 1883 Cal. LEXIS 368, Counsel Stack Legal Research, https://law.counselstack.com/opinion/loup-v-california-southern-railroad-cal-1883.