N. Am. Dredging Co. of Nevada v. Outer Harbor Dock & Wharf Co.

173 P. 756, 178 Cal. 406, 1918 Cal. LEXIS 490
California Supreme Court·Decided June 12, 1918·No. L. A. No. 4195. Department One.·Published·Cited by 12 cases

Opinion

RICHARDS, J., pro tem.

T his is an appeal from a judgment rendered in the defendant’s favor after its demurrer to the plaintiff’s third amended complaint had been sustained, the plaintiff declining to further amend its pleading. Respondent urges a preliminary objection to the hearing of this appeal upon the ground that it was taken too late. On December 7, 1914, attorneys for the appellant were served with a notice of the entry of judgment in the action on December 3, 1914. The judgment was not, however, actually entered until December 18, 1914. Such notice was, therefore, premature and ineffectual for any purpose, since there could be no valid notice of the existence of something which did not in fact exist. This appeal was taken in February, 1914, prior to the changes in the statutes regulating the procedure on appeal enacted in 1915, and which dispensed with the requirement of notice of entry of judgment in order to set in motion the time for taking appeals. As the statute stood at the time this appeal was taken, an appeal from a judgment was required to be taken within sixty days after notice of the entry of judgment; or, in any event, within six months after entry of the judgment. (Foss v. Johnstone, 158 Cal. 119, [110 Pac. 294].) In the absence of a valid notice of the entry of the judgment, the appellant under the former state of the statute had six months from the date of the actual entry of judgment within which to take its appeal, and having taken it within such time, its appeal is properly before this court.

The action was one upon quantum meruit for work and labor performed. The complaint alleged that the plaintiff and the defendant had upon March 29, 1912, entered into a *409 written contract for the doing of certain dredging work adjacent to certain lands in the harbor of San Pedro, of which lands the defendant was in possession, and also the doing of certain filling upon said lands. The contract was made a part of the complaint. By its terms the plaintiff was to dredge certain channels, shown on a map attached to the contract, designated as the east and west channels and the north slip of the Watchorn Basin. The east and west channels were to be completed to the thirty-foot contour line within five months from date—by August 29, 1912. At least one hundred and fifty thousand cubic yards of dredged material were to be deposited on the property of the Dock Company each ninety days until the land was filled to a certain grade, and at least thirty thousand cubic yards each month. All filling was to be completed by November 1, 1912, and a certain portion, the “Outer Mole,” was to be completed within ninety days. All the work of dredging and filling was to be completed by December 31, 1912. The Dock Company was to construct in advance of the dredging, and to maintain all levees and bulkheads necessary to retain material excavated. The payment which the Dredging Company was to receive was based entirely on amount of material dredged, being twenty-four cents per cubic yard in certain cases and twenty-nine cents in others. A partial payment of twelve cents per cubic yard is also provided for in certain cases. Payment was to be made on or before the tenth of each month for all work done the previous month, ten per cent being reserved until the next month as a guaranty for faithful performance. All work was to be estimated each month by the Dock Company’s engineers, which estimates might be cheeked by the Dredging Company’s engineers, but in making final settlement for any work such estimates were to be disregarded and the actual amount of material excavated was to control. All payments were to be made promptly when due. The Dredging Company was to prosecute all work diligently until completion. Time and minimum quantities of work to be done during a specified time were of the essence of the contract. In case of any disagreements between the parties, they were to be settled by arbitration.

Free access — add to your briefcase to read the full text and ask questions with AI

N. Am. Dredging Co. of Nevada v. Outer Harbor Dock & Wharf Co., 173 P. 756, 178 Cal. 406, 1918 Cal. LEXIS 490 (Cal. 1918).

173 P. 756 (N. Am. Dredging Co. of Nevada v. Outer Harbor Dock & Wharf Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Gelber v. Cappeller
326 P.2d 521 (California Court of Appeal, 1958)
Einot, Inc. v. Einot Sales Co.
49 N.W.2d 625 (Nebraska Supreme Court, 1951)
Joshua Tree Townsite Co. v. Joshua Tree Land Co.
224 P.2d 85 (California Court of Appeal, 1950)
Kulawitz v. Pacific Woodenware & Paper Co.
155 P.2d 24 (California Supreme Court, 1944)
Wilde v. Superior Court
127 P.2d 560 (California Court of Appeal, 1942)
Palmer v. Fix
286 P. 498 (California Court of Appeal, 1930)
Pyle v. Benjamin
283 P. 372 (California Court of Appeal, 1929)
Jameson v. Warren
267 P. 372 (California Court of Appeal, 1928)
W. H. Blodgett Co. v. Bebe Co.
214 P. 38 (California Supreme Court, 1923)
Grimes v. Lamar
213 P. 270 (California Court of Appeal, 1923)