Keller Supply Co. v. Lydig Construction Co.

789 P.2d 788, 57 Wash. App. 594, 1990 Wash. App. LEXIS 148
CourtCourt of Appeals of Washington
DecidedApril 23, 1990
Docket23107-3-I
StatusPublished
Cited by9 cases

This text of 789 P.2d 788 (Keller Supply Co. v. Lydig Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Keller Supply Co. v. Lydig Construction Co., 789 P.2d 788, 57 Wash. App. 594, 1990 Wash. App. LEXIS 148 (Wash. Ct. App. 1990).

Opinion

Grosse, J.

Lydig Construction, Inc. (Lydig) and Federal Insurance Company (Federal) appeal a summary judgment granted in favor of Keller Supply Company, Inc. *596 (Keller). The question presented is whether Keller substantially complied with the preclaim notice requirements of RCW 39.08 (hereinafter the Bond Act) and RCW 60.28 (hereinafter the Retainage Act). We affirm.

In May of 1986, Lydig, as the project general contractor, and Warrior Mechanical, Inc. (Warrior), as the mechanical subcontractor, commenced work on the University of Washington Husky Stadium Expansion Project. As required by law, Lydig posted a performance bond, provided by Federal, and the University retained a percentage of the total contract to satisfy unpaid claims of material-men. Keller provided plumbing materials to Warrior for the project. During the project, Warrior became insolvent and was unable to pay Keller. Subcontractors, including Keller, filed claims against Lydig's bond and against the retainage. Lydig refused to pay Keller's claim stating Keller failed to comply with the preclaim notice requirements of either the Bond Act or the Retainage Act.

On February 20, 1987, Keller notified the University of Washington it was supplying plumbing materials to Warrior. Keller sent by certified mail a copy of this written notice to Lydig and Warrior. The last paragraph of the notice stated:

We are required by law to furnish this notice to the owners of all property to which we deliver materials and supplies, so they may have notice that in the event of non-payment of our account, a materialman's lien may be claimed by us. This notice is not in itself a claim of lien, nor does it imply in any way that a lien may be necessary. It is sent only because we are required by statute to do so.

The notice did not specifically state that Keller would look to Lydig's bond or the retainage for any claim in case of nonpayment, and the notice was addressed only to the University of Washington, not Lydig.

The two statutes at issue here are RCW 39.08 and RCW 60.28. These statutes provide as follows:

Notice to contractor condition to suit on bond when supplies are furnished to subcontractor. Every person, firm or corporation furnishing materials, supplies or provisions *597 to be used in the construction, performance, carrying on, prosecution or doing of any work for the state, or any county, city, town, district, municipality or other public body, shall, not later than ten days after the date of the first delivery of such materials, supplies or provisions to any subcontractor or agent of any person, firm or corporation having a subcontract for the construction, performance, carrying on, prosecution or doing of such work, deliver or mail to the contractor a notice in writing stating in substance and effect that such person, firm or corporation has commenced to deliver materials, supplies or provisions for use thereon, with the name of the subcontractor or agent ordering or to whom the same is furnished and that such contractor and his bond will be held for the payment of the same, and no suit or action shall be maintained in any court against the contractor or his bond to recover for such material, supplies or provisions or any part thereof unless the provisions of this section have been complied with.

(Italics ours.) RCW 39.08.065.

Recovery from retained percentage—Written notice to contractor of materials furnished. Every person, firm, or corporation furnishing materials, supplies, or equipment to be used in the construction, performance, carrying on, prosecution, or doing of any work for the state, or any county, city, town, district, municipality, or other public body, shall give to the contractor of the work a notice in writing, which notice shall cover the material, supplies, or equipment furnished or leased during the sixty days preceding the giving of such notice as well as all subsequent materials, supplies, or equipment furnished or leased, stating in substance and effect that such person, firm, or corporation is and/or has furnished materials and supplies, or equipment for use thereon, with the name of the subcontractor ordering the same, and that a lien against the retained percentage may be claimed for all materials and supplies, or equipment furnished by such person, firm, or corporation for use thereon, which notice shall be given by (1) mailing the same by registered or certified mail in an envelope addressed to the contractor, or (2) by serving the same personally upon the contractor or the contractor's representative and obtaining evidence of such service in the form of a receipt or other acknowledgement signed by the contractor or the contractor's representative, and no suit or action shall be maintained in any court against the retained percentage to recover for such material, supplies, or equipment or any part thereof unless the provisions of this section have been complied with.

(Italics ours.) RCW 60.28.015.

The preclaim notice requirements of RCW 60.28.015 and RCW 39.08.065 are almost identical. Under both statutes, *598 Keller must (1) notify the contractor "in substance and effect" that he is (2) providing materials to the project, (3) upon the request of a specified subcontractor. Further, pursuant to each statute, Keller must notify the contractor "in substance and effect" that a lien against either the bond or the retained percentage may be claimed. Neither the bond nor the retainage were specifically identified in the notice Keller sent to Lydig. Both statutes preclude action against the bond or retained percentage if the claimant does not comply with their provisions.

'Lydig argues that these statutes should be strictly construed because liens are in derogation to common law, citing International Comm'l Collectors, Inc. v. Mazel Co., 48 Wn. App. 712, 740 P.2d 363 (1987) and CH2M Hill, Inc. v. Greg Bogart & Co., 47 Wn. App. 414, 735 P.2d 1330, review denied, 108 Wn.2d 1023 (1987). Neither case is controlling. Both resolve issues relating to the priority of liens against the contractor's bonds, not the issue of notice. We believe the controlling case is Foremost-McKesson Sys. Div. of Foremost-McKesson, Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Diamaco, Inc. v. Mettler
145 P.3d 399 (Court of Appeals of Washington, 2006)
U.S. Filter Distribution Group, Inc. v. Katspan, Inc.
72 P.3d 1103 (Court of Appeals of Washington, 2003)
Better Financial Solutions, Inc. v. Transtech Electric, Inc.
51 P.3d 108 (Court of Appeals of Washington, 2002)
Thompson v. Peninsula School District No. 401
892 P.2d 760 (Court of Appeals of Washington, 1995)
Okee Industries, Inc. v. National Grange Mutual Insurance
623 A.2d 483 (Supreme Court of Connecticut, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
789 P.2d 788, 57 Wash. App. 594, 1990 Wash. App. LEXIS 148, Counsel Stack Legal Research, https://law.counselstack.com/opinion/keller-supply-co-v-lydig-construction-co-washctapp-1990.