Standard Accident Insurance v. Interlocking Tile Corp.

6 P.2d 383, 166 Wash. 260, 1932 Wash. LEXIS 509
CourtWashington Supreme Court
DecidedJanuary 7, 1932
DocketNo. 23233. Department One.
StatusPublished
Cited by2 cases

This text of 6 P.2d 383 (Standard Accident Insurance v. Interlocking Tile Corp.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Standard Accident Insurance v. Interlocking Tile Corp., 6 P.2d 383, 166 Wash. 260, 1932 Wash. LEXIS 509 (Wash. 1932).

Opinion

Mitchell, J.

H. Grdbrandson & Son entered into a contract with the county of Snohomish, by and through its board of county commissioners, for the construction of the Snohomish county detention home. The Standard Accident Insurance Company became surety for the contractors, giving the usual statutory bond, under the provisions of Bern. Comp. Stat., §§ 1159 to 1161. The Interlocking Tile Corporation entered into and performed a subcontract with Gfulbrandson & Son for the furnishing and installation of the tile roof on the building, in the sum of $860.

The building was completed and formally accepted *261 by the county, at which time the county retained, pursuant to its rights.under the provisions of the contract, $7,231 of the amount due the contractors. The contractors failed to pay cos'ts of constructing the building in an amount altogether largely in excess of the remainder due the contractors.

The surety company then brought this action against the county and its commissioners, the general contractors, and all persons who, within the information of plaintiff, had or claimed to have any lien or right of action, to ascertain and preserve the amount of money owing and retained by the county, and to have it paid out as ordered by the court. The county paid into court the amount retained by it in'connection with the' contract.

A large number of claimants appeared in the action by cross-complaints, each seeking judgment for the amount of his claim against the plaintiff as surety on the contractor’s bond. On the trial, findings and judgment were entered in favor of several claimants against the plaintiff, on its bond, in amounts in excess of the fund paid into court as the balance due on the contract.

The Interlocking Tile Corporation filed a cross-complaint in the action in the sum of $831.52, as the balance claimed to be due upon the performance of its subcontract. The trial court found, however, that the Interlocking Tile Corporation

“ . . . failed to file a good and sufficient notice of claim as against the reserve fund and the Standard Accident Insurance Company, surety and plaintiff herein, ’ ’

and entered conclusions of law and judgment to the same effect. .

The Interlocking Tile Corporation has appealed, and *262 assigns as errors the finding and conclusion against the sufficiency of its notice of claim, and the refusal of the trial court to sign a requested finding of fact-in its favor.

As applied to this case, Rem. Comp. Stat., § 1161, provides that a subcontractor shall not have a right of action on such bond, unless within thirty days (no question here about the time) after the completion of the contract, with an acceptance of the work by an affirmative action of the board, he present to such board a notice in writing in substance as follows:

“To (here insert the name of the state, county or municipality or other public body, city, town or district) :
“Notice is hereby given that the undersigned (here insert the name of the laborer, mechanic or subcontractor, or materialman, or person claiming to have furnished labor, materials or provisions for or upon such contract or work) has a claim in the sum of.............................. dollars (here insert the amount) against the bond taken from.........................................................(here insert the name of the principal and surety or sureties upon such bond) for the work of...............................................................(here insert a brief mention or description of the work concerning which said bond was taken).'
“ (Here to be signed)....................................................”

Two written instruments are relied on by the appellant as constituting notice. They are as follows:

“May 17, 1930.
“County Commissioners, Everett, Wash.
“Gentlemen:
“On May 14 we started work as sub-contractors under general contractor H. Gulbrandson, to instal the clay tile roof on the Detention Home at Everett, and if for any reason our account is not paid, we will hold Mr. H. Gulbrandson and his bond for payment of the same. ‘ ‘ Tours very truly,
“Interlocking Tile Corp.,
“By Albert Armstrong.”
*263 “July 10, 1930.
“County Commissioners, Everett, "Wash.
‘ ‘ Gentlemen:
“We enclose herewith statement of our account against H. Gulbrandson for labor and material furnished in connection with the roof on the Detention Home at Everett, as per plans by C. Ferris White.
“We understand that Mr. Gulbrandson’s work in this building is covered by bond, and will take this means of informing you that this account is past due.
“Yours very truly,
“Interlocking Tile Corp.,
“By Albert Armstrong.”

The statute, it has been noticed, says that the claimant shall file a notice in writing. As a matter of fact, neither of the instruments in this case was filed, but, being treated as ordinary correspondence by the county auditor, they became lost or destroyed, and could not be produced at the trial; so that secondary evidence of the sending and contents of the letters was resorted to. Of course, the claimant in a way was not blameable for the loss of the letters by the county auditor, but from the standpoint of the claimant with reference to the requirement of notice, the claimant neither suggested nor requested in the letters, or otherwise, that they be filed or preserved.

The notice the statute requires to be given is intended in part for the benefit of the surety on the contractor’s bond. The statute speaks of notice of a claim against the “bond taken from...................................................(here insert the name of the principal and surety or sureties upon such bond),” etc. In the letters to the county commissioners in this case, there was a very poor effort at naming the contractor, as H. Gulbrandson instead of H. Gulbrandson & Son, and no attempt whatever to name the surety.

Appellant attempts to justify its conduct in that respect as sufficient by reason of statements in certain *264 of our eases to the effect that it is not necessary that the statute be strictly complied with. Three of those cases are Strandell v. Moran, 49 Wash. 533, 95 Pac. 1106; Cascade Lumber Co. v. Aetna Indemnity Co., 56 Wash. 503, 106 Pac. 158, and Robinson Mfg. Co. v. Bradley, 71 Wash. 611, 129 Pac. 382.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fidelity & Deposit Co. v. Herbert H. Conway, Inc.
128 P.2d 764 (Washington Supreme Court, 1942)
United States Fidelity & Guaranty Co. v. Port of Seattle
13 P.2d 33 (Washington Supreme Court, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
6 P.2d 383, 166 Wash. 260, 1932 Wash. LEXIS 509, Counsel Stack Legal Research, https://law.counselstack.com/opinion/standard-accident-insurance-v-interlocking-tile-corp-wash-1932.