Grant County Constructors v. E. v. Lane Corp.

459 P.2d 947, 77 Wash. 2d 110, 1969 Wash. LEXIS 569
CourtWashington Supreme Court
DecidedOctober 16, 1969
Docket39462
StatusPublished
Cited by42 cases

This text of 459 P.2d 947 (Grant County Constructors v. E. v. Lane Corp.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grant County Constructors v. E. v. Lane Corp., 459 P.2d 947, 77 Wash. 2d 110, 1969 Wash. LEXIS 569 (Wash. 1969).

Opinion

Hale, J.

Grant County Constructors, prime contractor on the Columbia River Wanapum hydroelectric project, seeks recovery against its subcontractor and the latter’s insurance carriers for fire damage to a generator shaft. The trial court, ultimately seeing an ambiguity in the contract between the two contractors and in the insurance policy, admitted parol evidence to explain the ambiguity. From this parol evidence, the court concluded that the prime contractor and not defendant subcontractor was on the risk at the moment of loss, and defendant insurance carriers, therefore, were not liable. The prime contractor and its insurance carrier appeal.

Grant County Constructors, a joint venture composed of four construction companies, was awarded the prime contract in 1959 by Grant County Public Utility District No. 2 to build the Wanapum Dam and powerhouse on the Columbia River and to install the hydroelectric generating system at a contract cost of about $92,000,000. The joint venturing companies delegated to Morrison-Knudsen Company, one of the members, main powers of management, supervision and leadership in performing the contract. Equipment and materials essential to build the dam and complete the hydroelectric generating system would exceed $30,000,000. Contrary to the customary practice in hydroelectric developments, the contract required Grant County Constructors to purchase and supply all equipment and materials required for the project. To meet this added responsibility, Grant County Constructors procured comprehensive insurance coverage — including a transportation floater — from plaintiff Fireman’s Fund Insurance Company effective in *112 July, 1959, covering losses incurred during transportation of materials and equipment.

September 30, 1959, Grant County Constructors awarded to Gunther-Shirley-Lane Corporation a $3,000,000 subcontract to perform the mechanical work on the dam and powerhouse, including installation of the generators. Gunther-Shirley-Lane, a joint venture of E. V. Lane Corporation and Gunther & Shirley Company, designated E. V. Lane Corporation as the lead, sponsoring and managing member. At the outset, the subcontractor was not required to provide fire insurance coverage for the material and equipment to be supplied by Grant County Constructors for installation under the mechanical subcontract.

After awarding the mechanical subcontract, however, plaintiff Grant County Constructors, facing possibilities of a high insurance loss on the $92,000,000 prime contract, decided to share this insurance risk by having Gunther-Shirley-Lane provide insurance protection on materials, supplies and equipment utilized in performing the subcontract. Even if it were to pay the premium for this insurance, the prime contractor saw a benefit in transferring a part of the risk. The enormity of the losses possible under the entire contract persuaded the prime contractor that a sharing of the risk would be one means of avoiding an exceptionally unfavorable loss experience. Promising to pay the premiums, Grant County Constructors sought to induce Gunther-Shirley-Lane to procure fire insurance protection on all materials, equipment and supplies utilized in the course of performing the mechanical subcontract.

Accordingly, Grant County Constructors opened negotiations by requesting Gunther-Shirley-Lane to study the matter of insurance protection with the idea of obtaining adequate fire insurance coverage. After a period of negotiations and after Grant County Constructors had considered certain proposals advanced by Gunther-Shirley-Lane, their representatives met in Boise, Idaho, November 3, 1959, to discuss insurance matters. Following these negotiations, the parties on January 14, I960, entered into a written agreement referred to as modification No. 1, as follows':

*113 Grant County Constructors Modification No. 1 to Subcontract of Gunther-Shirley-Lane
* * *
Wanapum Development — Columbia River For Grant County Public Utility District No. 2
Contractor and Subcontractor understand and agree that Subcontractor will assume responsibility for the protection of work, equipment and materials covered under its Subcontract dated September 30, 1959, from the time such property, equipment and materials are handled by or placed in the custody of Subcontractor and during such time as Subcontractor is performing any operation thereon until Subcontractor is relieved from physical custody thereof or until the installation of said property, equipment and materials has been completed and accepted by the District.
Subcontractor agrees to secure and maintain suitable in surance covering this responsibility with a limit of $2,000,000 per occurrence. Upon receipt by Contractor of a copy of such policy or policies evidencing this coverage, Contractor agrees to pay to Subcontractor the sum of $24,000.00.
rN Witness Whereof, the parties have set their hand"’ this 14th day of January, 1960.
Grant County Constructors
Witness:
/s/ W. H. Smith
By: /s/ George Piedmont
Witness:
/s/ W. W. Davis
Gunther-Shirley-Lane By: /s/ E. V. Lane
(Italics ours.)

Modification agreement No. 1 was a carefully negotiated contract. Although it was dated January 14, 1960, the parties had apparently substantially agreed upon its terms earlier, for on November 6, 1959, the general counsel for Grant County Constructors, referring specifically to this agreement, wrote a letter 1 to Gunther-Shirley-Lane which contained the following paragraph:

*114 It is understood and agreed that you have undertaken full responsibility for the protection of all work, property, equipment and materials entrusted to your custody from the time you take physical custody thereof until the time you are divested of physical custody or until such work, property, equipment and materials are completed and have been accepted by the Public Utility District. Likewise, we understand that you are obtaining insurance with a primary limit of $2,000,000 covering this responsibility.

Acting in accordance with this letter and the modification agreement, Gunther-Shirley-Lane proceeded to obtain insurance from defendant insurance companies with defendant American Home Assurance Company assuming 50 per cent of the risk and defendants Universal Insurance Company, Balfour Guthrie Insurance Company, Agricultural Insurance Company and United States Fire Insurance Company the remaining 50 per cent at 12% per cent each. The policy, issued for a premium of $24,000, expressly named “Gunther-Shirley-Lane Wanapum Powerhouse Joint Venture (Subcontractors)” as the insured, and covered “all materials and equipment and structures and appurtenant work to be used in connection therewith.” It fixed the beginning and duration of the risk as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carlstrom v. Hanline
990 P.2d 986 (Court of Appeals of Washington, 2000)
Universal/Land Construction Co. v. City of Spokane
745 P.2d 53 (Court of Appeals of Washington, 1987)
Danielson v. City of Seattle
742 P.2d 717 (Washington Supreme Court, 1987)
Hansen v. City of Seattle
724 P.2d 371 (Court of Appeals of Washington, 1986)
McDowell v. AUSTIN COMPANY
693 P.2d 744 (Court of Appeals of Washington, 1985)
Thornton v. Interstate Securities Co.
666 P.2d 370 (Court of Appeals of Washington, 1983)
Spokane Helicopter Service, Inc. v. Malone
623 P.2d 727 (Court of Appeals of Washington, 1981)
Continental Insurance v. Paccar, Inc.
614 P.2d 675 (Court of Appeals of Washington, 1980)
Maxwell's Electric, Inc. v. Hegeman-Harris Co. of Canada, Ltd.
567 P.2d 1149 (Court of Appeals of Washington, 1977)
Seattle-First National Bank v. Earl
565 P.2d 1215 (Court of Appeals of Washington, 1977)
Seattle-First National Bank v. Hawk
562 P.2d 260 (Court of Appeals of Washington, 1977)
Dwelley v. Chesterfield
560 P.2d 353 (Washington Supreme Court, 1977)
Jones v. Hollingsworth
560 P.2d 348 (Washington Supreme Court, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
459 P.2d 947, 77 Wash. 2d 110, 1969 Wash. LEXIS 569, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grant-county-constructors-v-e-v-lane-corp-wash-1969.