Washington Public Power Supply System v. Pittsburgh-Des Moines Corp.

876 F.2d 690, 1989 WL 53337
CourtCourt of Appeals for the Ninth Circuit
DecidedMay 23, 1989
DocketNos. 86-4300, 88-3554
StatusPublished
Cited by1 cases

This text of 876 F.2d 690 (Washington Public Power Supply System v. Pittsburgh-Des Moines Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Washington Public Power Supply System v. Pittsburgh-Des Moines Corp., 876 F.2d 690, 1989 WL 53337 (9th Cir. 1989).

Opinion

EUGENE A. WRIGHT, Circuit Judge.

This case stems from litigation of issues arising from contractual agreements between Washington Public Power Supply System (WPPSS) and Pittsburgh-Des Moines Corporation (PDM) relating to the construction of WPPSS Nuclear Project No. 2 (WNP-2) and Project No. 5 (WNP-5).

In WPPSS’s appeal (PDMI), we examine several contracts involving the retrofit of WNP-2 to determine the scope of WPPSS’s breach of contract and warranty actions against PDM. In PDM’s cross-appeal (PDM-I1), we decide whether PDM must seek satisfaction of a judgment relating to the construction of WNP-5 only from the WNP-4/5 Construction and Revenue Funds.

[692]*692I. PDM-I: WPPSS’s APPEAL

Background1

In 1972 PDM entered into Contract 213 with WPPSS and agreed to construct the nuclear containment vessel at WNP-2. Both parties fulfilled their contractual obligations satisfactorily. WPPSS determined later that new federal design requirements necessitated reinforcement and modification of the containment vessel. In 1977 PDM entered into Contract 213A in which it agreed to “retrofit” the WNP-2 steel structures.

Problems arose under Contract 213A. In 1981 the parties became dissatisfied with its payment provisions. They modified 213A and replaced it with Modification (Mod.) 164 and Contract 213B. Mod. 164, which bridged the two contracts, provided for a $50 million settlement for completed contract work up to and including February 28, 1981, but saved claims for certain “defective or nonconforming” work. In 1982 PDM completed the retrofit under 213B, and WNP-2 is now operational.

Because the parties could not resolve what claims were saved under Mod. 164, WPPSS sued PDM for damages arising from the alleged collapse of PDM’s quality assurance program. In response, PDM asserted numerous defenses and two counterclaims. PDM I is a contract dispute involving the interpretation of the WNP-2 agreements to determine what terms govern WPPSS’s breach of contract and warranty claims.

Analysis

A. Claims for Breach of Contract and Warranty

Following massive discovery, the parties filed cross-motions for summary judgment. In a lengthy memorandum and order the court ruled (1) that Mod. 164, as a matter of law, unambiguously extinguished all WPPSS’s claims under Contract 213A except those sounding in warranty; (2) that Mod. 164 is ambiguous as to whether Contract 213A or 213B warranties govern the reserved claims; and (3) that Contract 213A warranties are ambiguous as to whether they attached before or after completion and turnover of PDM’s contract work.2 WPPSS contends that the court erred in its three summary judgment rulings.

Examining the WNP-2 contracts, we must determine initially whether certain contractual language is ambiguous.3 Whether a contract is ambiguous is a question of law for the court. Vanderpool v. Grange Ins. Ass’n, 110 Wash.2d 483, 756 P.2d 111, 114 (1988). We review de novo the court’s grant of summary judgment and its interpretation of state law. Cohen v. Paramount Pictures Corp., 845 F.2d 851, 852 (9th Cir.1988); In re McLinn, 739 F.2d 1395, 1397 (9th Cir.1984) (en banc).

Under Washington law, ambiguities exist when contract terms are uncertain or capable of being understood in more than one manner. E.g., McGary v. Westlake Investors, 99 Wash.2d 280, 661 P.2d 971, 974 (1983). “The controlling intent of the parties must be ascertained from reading the contract as a whole, and where the language used is unambiguous, no ambiguity will be read into the contract.” Taylor-Edwards Warehouse & Transfer Co. v. Burlington N., Inc., 715 F.2d 1330, 1334 (9th Cir.1983) (applying Washington law); see St. Yves v. Mid State Bank, 111 Wash. 2d 374, 757 P.2d 1384, 1386-87 (1988) (holding that parol evidence not admissible to create an ambiguity).

1. Reservation of Breach of Contract, Warranty Claims

In Mod. 164 the parties settled all claims arising from the performance of [693]*693Contract 213A except those “related to defective or nonconforming work accomplished prior to February 28, 1981” that may arise from PDM’s failure to implement its quality assurance program properly.

WPPSS contends that the exclusion clause in Mod. 164 saved all breach of warranty and contract claims arising from the breakdown of PDM’s quality assurance program.4 PDM asserts that WPPSS failed to preserve any breach of contract claims.

The crux of the contractual dispute focuses on ¶ 2 of Mod. 164, which reads in its entirety:

[Modification 164]

Provides for settlement and compensation for all completed contract work in place, approved and accepted by the Owner up to and including February 28, 1981 on the basis of a negotiated cost incurred of $50,329,631. Payment is in consideration of settlement and full and final compromise of all outstanding unexecuted change orders, claims, materials on site (not installed) purchased by the Contractor, all escalation, causes of action and damages arising out of or in connection with said performance of the 2808-213A Contract up to and including February 28, 1981, excluding any issues between Owner and Contractor related to defective or nonconforming work accomplished prior to February 28, 1981 and [sic] that may arise from contractors failure to properly implement the Quality Assurance Program as set forth in the 2808-213A by reference herein as applicable to this issue.

(emphasis added).5

The court decided by summary judgment that Mod. 164, as a matter of law, preserved claims for breach of warranty only. Construing 112, it ruled:

[U]nder the Mod. 164 language the claim reserved was that of warranty only since the “any issue” language modifies the “defective” and “nonconforming” language, which terms unambiguously signify warranty notions despite the fact that the term “warranty” is not used.... Manifestly, the saved claims are not ones for both breach of warranty and for breach of contract. Rather, the warranty-type language is limiting and definitive, not cumulative or collective.

Summary Judgment Order at 44. Although the court’s analysis has some appeal, we disagree and find the terms “defective or nonconforming” ambiguous.

Those terms, as a matter of law, do not refer only to warranty concepts. In Eastlake Constr. Co. v. Hess, 102 Wash.2d 30, 686 P.2d 465 (1984), the Washington Supreme Court used the terms when it considered the appropriate measure of damages for a nonwarranty breach of contract claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
876 F.2d 690, 1989 WL 53337, Counsel Stack Legal Research, https://law.counselstack.com/opinion/washington-public-power-supply-system-v-pittsburgh-des-moines-corp-ca9-1989.