Iowa Concrete Breaking Corp. v. Jewat Trucking, Inc.

444 N.W.2d 865, 1989 Minn. App. LEXIS 956, 1989 WL 100518
CourtCourt of Appeals of Minnesota
DecidedSeptember 5, 1989
DocketC5-88-2585
StatusPublished
Cited by5 cases

This text of 444 N.W.2d 865 (Iowa Concrete Breaking Corp. v. Jewat Trucking, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Iowa Concrete Breaking Corp. v. Jewat Trucking, Inc., 444 N.W.2d 865, 1989 Minn. App. LEXIS 956, 1989 WL 100518 (Mich. Ct. App. 1989).

Opinion

OPINION

HUSPENI, Judge.

Appellant as a surety for a subcontractor was found primarily liable for the subcontractor’s failure to pay a creditor. After a partial stipulation and a trial bifurcating the issues of liability and attorney fees, the trial court found joint and several liability on the part of general contractor, its surety, and appellant. Appellant now challenges its liability and the trial court’s allowance of a cross-claim against it by the general contractor and its surety. We affirm.

FACTS

After bidding on a state highway project, Road Constructors, Inc. (RCI) subcontracted with Jewat Trucking, Inc. (Jewat) to crush pavement for the project’s two stages. The subcontract required that Je-wat obtain a performance bond and a labor and material bond. Subsequently, RCI made inquiries regarding the status of Je- *867 wat s bonds and was told that the bonds were forthcoming.

Jewat contracted with Iowa Concrete Breaking Corporation (ICBC) to provide pavement-breaking equipment and workers. Jewat started work and encountered problems but completed Phase I with the help of RCI. Jewat did not complete Phase II. Jewat’s Phase I problems included not making timely progress on the concrete breaking, failure to make payments to ICBC and an inability to pay workers. On several occasions, RCI made certain payments on behalf of Jewat.

Jewat then obtained from appellant Central National Insurance Co. of Omaha (CNICO) the performance and labor and material bonds required by the subcontract. Ronald Risdon, bonding agent for CNICO, engaged in various communications with Jewat and with the Small Business Association about Jewat before issuing the bonds. However, although Risdon knew RCI was the general contractor on the project, he did not contact RCI before issuing the bonds despite his conflicting information regarding completion dates for Jewat’s work and his knowledge that Je-wat’s contract with RCI was dated five months earlier.

Jewat went out of business still owing money to ICBC. ICBC sued Jewat, CNI-CO, RCI, and its surety, St. Paul Fire and Marine Insurance Company (St. Paul). The parties stipulated that ICBC was owed $25,321.83 by Jewat but disagreed on who was liable. Additionally, over CNICO’s objections, the trial court granted the motion of RCI and St. Paul to amend their pleadings to include a cross-claim for contribution or indemnification against CNICO.

At trial, RCI’s president William Quick testified that because Jewat was a minority contractor without a large capital base, its inability to meet financial obligations was not immediately troubling because such problems were not uncommon with minority contractors.

Finding CNICO liable, the trial court awarded ICBC its stipulated damages plus attorney fees of $8,500. RCI and St. Paul were awarded damages of $10,961.65 plus attorney fees of $8,000. The trial court also found RCI, St. Paul and CNICO jointly and severally liable on the monies owed ICBC, found CNICO primarily liable for these amounts, and awarded RCI and St. Paul indemnification against CNICO.

ISSUES

1. Did the trial court err in finding CNI-CO liable to ICBC?

2. Did the trial court abuse its discretion in permitting RCI’s cross-claim against CNICO?

3. Did the trial court err in finding CNI-CO liable to St. Paul and RCI for indemnity?

4. Did the trial court err in finding CNI-CO liable to RCI?

5. Did the trial court err in awarding ICBC attorney fees?

ANALYSIS

Generally,
[Findings of fact, whether based on oral or documentary evidence, shall not be set aside unless clearly erroneous, and due regard shall be given to the opportunity of the trial court to judge the credibility of the witnesses.

Minn.R.Civ.P. 52.01. Also,

[Ejven though there be evidence to support factual findings, [the reviewing] court may order a reversal if, upon reviewing the entire evidence, [it is] left with a firm conviction that a mistake has been made.

State v. Paulson, 290 Minn. 371, 373, 188 N.W.2d 424, 426 (1971).

I.

CNICO maintains that because its bonds do not cover breaches occurring before the bonds are executed and because it was prejudiced by the extent to which Jewat’s contract had been completed when the bonds were executed, the trial court erred in finding CNICO liable to ICBC. We disagree.

CNICO presumes that the trial court retroactively applied the bonds. The trial *868 court did not explicitly state whether or not it did so. However, its findings, stating that “[the bonds] were to cover the * * * sub-contract between Jewat and RCI” and that

CNICO issued the bonds although they knew or should have known that the work covered by them had already begun,

(emphasis added), suggest that the bonds were retroactively applied.

Generally, a surety bond is to be liberally construed in favor of the obligee, First National Bank v. Iowa Bonding and Casualty Co., 149 Minn. 279, 282, 188 N.W. 832, 833 (1921),

[but] is not retrospective in its application * * * [N]o liability attaches to the surety for defaults occurring prior to the date of execution of the performance bond.

Peterson v. Schrieber, 238 N.W.2d 722, 724 (Wis.1976). However,

In the absence of any showing of prejudice to the surety, it seems completely irrelevant to the purpose of the bond that the contractor had already used labor to perform part of the work [or] had obtained some materials * * * before the bond was executed and delivered.

Reed v. Maryland Casualty Co., 244 F.2d 857, 862 (5th Cir.1957).

CNICO argues that default was evident prior to bond execution because Jewat failed to pay workers, failed to pay ICBC, failed to make sufficient progress, and was working on the contract without proper bonding. When examining rights under surety agreements,

[A]ll arguments proceed in recognition of the fact that a wide exploration of the facts is necessary to determine the nature of the respective claims and the situation and relationships of the various parties in connection with them.

Reed, 244 F.2d at 859.

Regarding the alleged pre-bond breaches of Jewat’s subcontract, the trial court found:

At all times pertinent before the bonds were issued, RCI had no reason to believe Jewat had defaulted or would default on its obligation on the contract.

The trial court’s finding is not clearly erroneous.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Larson v. Granite Re, Inc.
532 F.3d 724 (Eighth Circuit, 2008)
Electrical Electronic Control, Inc. v. Los Angeles Unified School District
24 Cal. Rptr. 3d 316 (California Court of Appeal, 2005)
Leonard C. Carnaghi, Inc. v. Amwest Surety Ins. Co.
617 N.W.2d 49 (Michigan Court of Appeals, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
444 N.W.2d 865, 1989 Minn. App. LEXIS 956, 1989 WL 100518, Counsel Stack Legal Research, https://law.counselstack.com/opinion/iowa-concrete-breaking-corp-v-jewat-trucking-inc-minnctapp-1989.