S. L. Reed and Western Casualty & Surety Company v. Maryland Casualty Company

244 F.2d 857
CourtCourt of Appeals for the Fifth Circuit
DecidedJune 10, 1957
Docket16099_1
StatusPublished
Cited by6 cases

This text of 244 F.2d 857 (S. L. Reed and Western Casualty & Surety Company v. Maryland Casualty Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S. L. Reed and Western Casualty & Surety Company v. Maryland Casualty Company, 244 F.2d 857 (5th Cir. 1957).

Opinions

PER CURIAM.

On March 17, 1952, Reed-Meredith, Inc., with Maryland Casualty Company as surety, contracted in writing with S. L. Reed1 to perform “certain items of work” embraced in a contract between him (Western Casualty and Surety Company as surety) and the Mississippi Highway Department for the building of a stretch of road in Coahoma County, Mississippi. Certain materials had previously been furnished to Reed and had later been turned over by him to, and used by, Reed-Meredith, and certain services had been performed in connection with the subject matter of the subcontract, prior to the execution of the surety bond; some of the materials so furnished were only used after May 17th. The question presented is whether Maryland, appellee, is liable under its bond (Reed-Meredith being insolvent) for such services and materials. The court below, sitting by agreement without a jury, answered that question in the negative and entered a final judgment on the merits in favor of Maryland and against Reed and Western.2

The litigation was begun by complaint for declaratory judgment brought by Maryland against Reed and Western3 which, with amended complaint, prayed for judgment declaring that its bond did not cover liabilities to said claimants incurred or accruing prior to its execution [859]*859and for other, related relief. The responsive pleadings of Reed and Western consisted of a general denial of the legal and factual averments of the complaint. Appellants and appellees agree that their rights are to be determined by the writings executed on March 17, 1952, consisting of the contract between appellant, S. L. Reed, and Reed-Meredith, Inc., the latter’s application for bond, and the bond executed by appellee, Maryland. But all arguments proceed in recognition of the fact that a wide exploration of the facts is necessary to determine the nature of the respective claims and the situation and relationships of the various parties in connection with them. These facts may well be set out by abridging the findings of fact of the court below.4

The contract (prepared by Reed) of March 17, 1952, between S. L. Reed, contractor, and Reed-Meredith, subcontractor, referred to and incorporated within its terms the contract between Reed and the Highway Department insofar as it laid upon the subcontractor the duty of performing the six items here involved in conformity with the terms of said main contract. Pertinent provisions of the subcontract of March 17th appear in the margin.5 On the same date a representative of Reed-Meredith, in company [860]*860with appellant, Reed, went to Maryland’s agent and executed an application for a bond which contained the question, “When must work begin?” To which the answer was made with pen: “Immediately.” Thereupon Maryland issued to S. L. Reed its “Performance Bond” incorporating by reference the terms of the written subcontract between Reed and Reed-Meredith. The bond was conditioned that it would be null and void “if contractor shall promptly and faithfully perform said contract.”6 (Emphasis added.)

[861]*861The trial court found that Reed-Meredith had completed the contract and had been paid by S. L. Reed the sum of $41,-041.32, being 90% of the full consideration, $7,813.76 of which was paid directly by Reed to Virginia Bridge Company, and that S. L. Reed retained 10% of the total contract price, amounting to $4,-424.58. It held that Reed-Meredith was insolvent and had left unpaid the items involved in this litigation.7 It held also that neither Highway Materials nor Fairchild nor Lynn had any direct claim against Maryland but that they did have valid claims against appellant. This suit, therefore, resolves itself into a contest between appellant, Reed, obligee in the bond, and Maryland, the surety, as to whether Reed can recover from Maryland the amount of the contested items and the rental charge of Reed against Reed-Meredith.

The court construed the contract, the application, and the bond of March 17th to be entirely prospective in their terms and to apply only to work done and obligations incurred after the execution of the writings.

It held that Maryland had no notice or knowledge that any of the materials had been purchased or any obligation incurred or any work performed prior to the execution of its bond, but that it had relied entirely upon the language of the three written instruments as defining its obligation and limiting its liability to what should happen subsequent to its execution.

Appellants claim that the trial court committed error in its findings of fact and its conclusions of law in several particulars.8

We are unable to agree with the district court in its holding that appellee’s obligation on the bond should be limited so as to exclude all materials acquired and all work performed by subcontractors after its execution if done in pursuance to subcontracts entered into before then. The written contract refers to Reed-Meredith’s obligation to complete all of the work required in the performance of certain specified items of work, and to “furnish all necessary materials and pay all labor necessary for completion of the work specified,” and the amount of the bond (and thus the compensation of the surety) is for the entire contract amount. By Mississippi law such construction contracts are indivisible, Clark v. Till, 177 Miss. 891, 172 [862]*862So. 133. The crucial question, therefore, is whether section 374 of the Mississippi Code of 1942 must be interpreted to limit the surety’s obligation under the above-quoted contractual provision which is also embodied in the bond, to the payment of labor and materials furnished after said contract was entered into, or whether the broader contractual obligation must be interpreted to include all labor and materials furnished to accomplish the purpose of the indivisible contract.

The district court relies on the well established rule that in the absence of special provisions a surety contract will be interpreted to be only prospective in effect. But the very quotation used by the court shows the inapplicability of that doctrine as generally stated to the present situation:

“A contract of suretyship is not retrospective in its operation and no liability attaches to the surety for defaults occurring before it is entered into, unless an intent to be so liable is indicated.” (Emphasis added.) 72 C.J.S., Principal and Surety, § 108.

Similarly from 50 Am.Jur., Suretyship, § 34:

“Contract of suretyship affecting ordinary business transactions take effect from the date of their execution, and applying the rule that a surety cannot be held beyond the terms or legal effect of his engagement, the surety’s liability will generally be restricted to defaults of the principal occurring during the period of the suretyship undertaking.” (Emphasis added.)

This is merely a natural consequence of the fact that for practical purposes these suretyship contracts are much like contracts of insurance, whereby the insurer will assume the risk' only of future occurrences but not of past and established ones. Here, however, there was no default

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Larson v. Granite Re, Inc.
532 F.3d 724 (Eighth Circuit, 2008)
Iowa Concrete Breaking Corp. v. Jewat Trucking, Inc.
444 N.W.2d 865 (Court of Appeals of Minnesota, 1989)
Parliament Insurance Co. v. L. B. Foster Co.
533 S.W.2d 43 (Court of Appeals of Texas, 1975)
People v. Great American Insurance
222 Cal. App. 2d 552 (California Court of Appeal, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
244 F.2d 857, Counsel Stack Legal Research, https://law.counselstack.com/opinion/s-l-reed-and-western-casualty-surety-company-v-maryland-casualty-ca5-1957.