Saint Paul Fire & Marine Insurance Co. v. Central National Insurance Co. of Omaha

480 N.W.2d 681, 1992 Minn. App. LEXIS 82, 1992 WL 15911
CourtCourt of Appeals of Minnesota
DecidedFebruary 4, 1992
DocketC0-91-1368
StatusPublished
Cited by2 cases

This text of 480 N.W.2d 681 (Saint Paul Fire & Marine Insurance Co. v. Central National Insurance Co. of Omaha) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Saint Paul Fire & Marine Insurance Co. v. Central National Insurance Co. of Omaha, 480 N.W.2d 681, 1992 Minn. App. LEXIS 82, 1992 WL 15911 (Mich. Ct. App. 1992).

Opinion

OPINION

DAVIES, Judge.

Appellant Central National Insurance Company of Omaha (CNICO) argues the trial court erred in ruling that, (1) CNICO was collaterally estopped from challenging its liability to respondent St. Paul Fire & Marine on a payment bond for debts arising from the default of CNICO’s assured, (2) CNICO’s payment bond is subject to the limitation period in Minn.Stat. § 574.31 rather than the limitation contained in the bond, (3) St. Paul Fire & Marine is not barred from raising this claim by the doctrine of res judicata, (4) St. Paul Fire & Marine is entitled to indemnification from CNICO and, (5) St. Paul Fire & Marine is entitled to an award of attorney fees. We affirm.

FACTS

Road Constructors, Inc., was the successful bidder on a state highway project. Road Constructors obtained the bonding for the project required by Minn.Stat. § 574.26 (1984) from St. Paul Fire and Ma *683 rine Insurance Company (St. P. Fire). Road Constructors then subcontracted with Jewat Trucking, Inc. (Jewat), to break concrete for the two phases of the project. The subcontract required that Jewat obtain its own performance bond and a labor and material payment bond. Jewat obtained these bonds from Central National Insurance Company of Omaha, naming Road Constructors as the obligee.

Jewat completed the first phase of the project, but only with the help of Road Constructors. Jewat did not complete the second phase, and Jewat subsequently went out of business owing money to, among others, Hercules Equipment & Company (Hercules).

Hercules commenced an action against St. P. Fire, as surety for Road Constructors. St. P. Fire brought a third-party action against CNICO, alleging the damages suffered by Hercules were the responsibility of CNICO as the issuer of the Jewat bond. St. P. Fire sought to recover from CNICO (by way of contribution or indemnity) any damages awarded against St. P. Fire.

While this case was pending in Ramsey County, a similar action against Jewat (and CNICO) was proceeding in Mower County. In the Mower County action, CNICO was found liable for Jewat’s default on amounts owed to Iowa Concrete Breaking. This court affirmed the Mower County trial court, and the supreme court denied further review. Iowa Concrete Breaking Corp. v. Jewat Trucking, Inc., 444 N.W.2d 865 (Minn.App.1989), pet. for rev. denied (Minn. Nov. 9, 1989).

This case involves the same issue as Iowa Concrete, that is, which surety should answer for the default of Jewat. St. P. Fire moved for partial summary judgment on collateral estoppel grounds. CNICO opposed St. P. Fire’s motion and brought its own motion for summary judgment, arguing that St. P. Fire’s claim was barred by the doctrine of res judicata because it was not asserted in the Mower County action and that it had been commenced more than one year following the date on which Jewat ceased working on its subcontract, contrary to a limitation provision in the surety bond. In addition, CNI-CO alleges St. P. Fire has not paid any money to Hercules and so is not entitled to indemnification, that St. P. Fire has no right to assert Road Constructors’ claim for indemnity, and that St. P. Fire was not a “claimant” as defined by the CNICO payment bond.

The trial court granted St. P. Fire’s motion for summary judgment and denied CNICO’s. CNICO moved to vacate and amend the order for summary judgment against it, for summary judgment in its favor, for stay of entry of judgment, and for a new trial. The trial court denied these motions and ordered judgment entered in favor of St. P. Fire. CNICO appeals.

Additional facts are recited in the analysis section.

ISSUES

1. Did the trial court err in concluding that CNICO was collaterally estopped from challenging whether it was liable to St. P. Fire for payment on debts arising from Jewat’s default?

2. Is CNICO’s payment bond subject to the limitation period in Minn.Stat. § 574.31 rather than the limitation contained in the bond?

3. Is St. P. Fire barred from raising this claim by the doctrine of res judicata?

4. Did the trial court err in determining that St. P. Fire is entitled to indemnification from CNICO?

5. Did the trial court err in awarding attorney’s fees to St. P. Fire?

ANALYSIS

On review of a summary judgment, this court must determine whether there are any genuine issues of material fact and whether the trial court correctly applied the law. Offerdahl v. University of Minn. Hosps. & Clinics, 426 N.W.2d 425, 427 (Minn.1988). The facts must be viewed in the light most favorable to the party against whom summary judgment *684 was granted. Grondahl v. Bulluck, 318 N.W.2d 240 (Minn.1982).

I.

CNICO argues that the trial court erred in holding that the doctrine of collateral estoppel bars CNICO from denying liability to St. P. Fire for debts arising from Jewat’s default. CNICO argues that certain of its defenses are not identical between the claim brought in this case and the claim adjudicated in Iowa Concrete, thus precluding the use of collateral estop-pel.

The purpose of collateral estoppel is to prevent needless consideration of matters decided in earlier litigation. Gulbranson v. Gulbranson, 408 N.W.2d 216, 217 (Minn.App.1987). Collateral estoppel is appropriately applied where (1) the issue at hand is identical to an issue in the prior adjudication, (2) there was a final judgment on the merits, (3) the party to be estopped was a party or in privity with a party to the prior adjudication, and (4) the estopped party was given a full and fair opportunity to litigate the adjudicated issue. Johnson v. Consolidated Freightways, Inc., 420 N.W.2d 608, 613 (Minn.1988).

Whether the trial court correctly applied the doctrine of collateral estoppel to the present case depends on what issues were determined in Iowa Concrete. St. P. Fire argues, and this court agrees, that a key issue in Iowa Concrete was the enforceability of the bonds issued by CNICO to Jewat. See Iowa Concrete, 444 N.W.2d at 867-68. More specifically, the trial court and court of appeals were asked in that case to construe whether both the payment bond and the performance bond were governed by the provisions in Minn.Stat. § 574.26. Both courts concluded that both bonds, by incorporating Road Constructors’ subcontract, were essentially converted front private to statutory bonds. 1 See id. at 871-2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson v. Johnson
902 N.W.2d 79 (Court of Appeals of Minnesota, 2017)
Deli v. Hasselmo
542 N.W.2d 649 (Court of Appeals of Minnesota, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
480 N.W.2d 681, 1992 Minn. App. LEXIS 82, 1992 WL 15911, Counsel Stack Legal Research, https://law.counselstack.com/opinion/saint-paul-fire-marine-insurance-co-v-central-national-insurance-co-of-minnctapp-1992.