Leonard C. Carnaghi, Inc. v. Amwest Surety Ins. Co.

617 N.W.2d 49, 241 Mich. App. 686
CourtMichigan Court of Appeals
DecidedSeptember 19, 2000
DocketDocket 205605
StatusPublished
Cited by3 cases

This text of 617 N.W.2d 49 (Leonard C. Carnaghi, Inc. v. Amwest Surety Ins. Co.) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Leonard C. Carnaghi, Inc. v. Amwest Surety Ins. Co., 617 N.W.2d 49, 241 Mich. App. 686 (Mich. Ct. App. 2000).

Opinion

Jansen, P.J.

Plaintiff appeals as of right from an order granting summary disposition in favor of defendant in this action where plaintiff attempts to recover payments pursuant to a payment bond issued by the defendant to a contractor for whom the plaintiff worked as a subcontractor. We reverse and remand.

On October 28, 1993, the Charter Township of West Bloomfield entered into a contract with U.S. Environ *688 mental Consulting, Inc., subsequently called Growth Environmental Services, Inc. (hereafter Growth), to perform underground environmental improvement work at two of West Bloomfield’s fire stations. The contract involved supervision, monitoring, and testing for contamination in and around the area of the underground storage tanks. Ultimately, contamination was found and required that environmental remediation work be performed. On March 7, 1995, Growth entered into two subcontracts with plaintiff to excavate soil, provide backfill material, and construct a remediation system at the two fire stations. Pursuant to the subcontracts, Growth was to provide labor and material payment bonds.

On May 8, 1995, an affidavit of payment was submitted by plaintiff to Growth, indicating that plaintiff had completed its work at the sites. Plaintiff’s labor and material as provided for in the subcontracts totaled $101,489.45. On June 26, 1995, Growth entered in a contract with West Bloomfield that amended the October 1993 contract to include the additional environmental work. The June 1995 contract required Growth to furnish performance and payment bonds in the amount of $33,000 each, which represented twenty-five percent of the approximate total of the actual construction costs. On August 22, 1995, Grovrih purchased a payment bond issued by defendant. The payment bond guaranteed payment up to the dollar amount of the bond ($66,000) to all subcontractors who furnished labor, material, or equipment for use in performance of the June 26, 1995, construction contract.

Shortly thereafter, Growth filed for bankruptcy. Growth had failed to make any payment to plaintiff *689 for the work done at the two fire stations under the subcontracts. Plaintiff then filed a complaint on April 19, 1996, seeking to recover the entire debt of $101,489.45 that Growth had failed to pay under the payment bond issued by defendant. 1 Defendant filed a motion for summary disposition under MCR 2.116(C)(7) and (10), arguing that plaintiffs claims were barred by the clear and unambiguous terms of the contract entered into between Growth and plaintiff. More specifically, defendant argued that because Growth had not received any payment from West Bloomfield, Growth had no obligation to pay plaintiff pursuant to the terms of the subcontract, and that defendant’s liability under the payment bond could be no greater than Growth’s liability. 2

*690 In its reply brief to plaintiffs answer to the motion for summary disposition, defendant raised an additional argument, contending that plaintiff was not protected by the payment bond because all of plaintiff’s work had been completed before the payment bond was issued. The trial court ultimately granted summary disposition in favor of defendant, ruling that the payment bond did not relate back to plaintiff’s work because plaintiff had completed its work by May 8, 1995, and the payment bond was not entered into until August 22, 1995.

We review de novo a trial court’s ruling with regard to a motion for summary disposition. Spiek v Dep’t of Transportation, 456 Mich 331, 337; 572 NW2d 201 (1998). Defendant filed the motion under MCR 2.116(C)(7) and (10). Under either subsection, affidavits, depositions, admissions, or other documentary evidence may be submitted in support of or in opposition to the motion and if such evidence is submitted, then the court must consider that evidence. MCR 2.116(G)(2) and (4). We reverse the trial court’s order because we find the court’s ruling to be an error of law; thus, defendant is not entitled to judgment as a matter of law on the basis of the issue before us.

Pursuant to MCL 129.201; MSA 5.2321(1), a principal contractor is required to supply a performance bond and a payment bond to the governmental unit before construction can begin on any public building project exceeding $50,000 in value. See, also, W T Andrew Co, Inc v Mid-State Surety Corp, 450 Mich 655, 658; 545 NW2d 351 (1996). A payment bond, *691 such as the one at issue here, is to be in an amount fixed by the governmental unit, but not less than twenty-five percent of the contract amount, and is solely for the protection of claimants. MCL 129.203; MSA 5.2321(3). “Claimant” is statutorily defined as “a person having furnished labor, material, or both, used or reasonably required for use in the performance of the contract.” MCL 129.206; MSA 5.2321(6). As noted by the Court in W T Andrew, supra, p 659, the Legislature adopted MCL 129.201; MSA 5.2321(1) to protect contractors and materialmen in the public sector to ensure that they do not suffer injury when other contractors default on their obligations. Without this legislation, contractors and materialmen were otherwise denied the security afforded when identical work or materials was provided to the public sector because contractors and materialmen may not obtain a mechanics’ lien on a public building. W T Andrew, supra, p 659; Kammer Asphalt Paving Co, Inc v East China Twp Schools, 443 Mich 176, 181; 504 NW2d 635 (1993).

Initially, no performance bond or payment bond was supplied by Growth, in relation to the October 1993 contract, because the anticipated costs were less than $10,000. However, the June 1995 contract provided for payment in excess of $200,000 for remediation work done at the two fire stations and required that Growth furnish a payment bond. The payment bond was ultimately obtained on August 22, 1995, and specifically referenced the June 1995 contract. The trial court ruled that because plaintiff had completed all work before the execution of the payment bond, the payment bond could not retroactively apply to the work performed, relying exclusively on this Court’s *692 decision in In re Slack Estate, 202 Mich App 627; 509 NW2d 861 (1993).

In re Slack Estate, p 630, states the general rule that in the absence of a clearly expressed contrary intent, guaranty contracts have prospective application only and do not cover events that occur before the date the contract becomes effective. However, In re Slack Estate is entirely distinguishable from the present case because that case involved a surety contract in the context of a fiduciary’s duty as the personal representative of an estate. This Court simply held that the bond was a guarantee against future improprieties made by the fiduciary. In other words, the bond was payable only in the event of the fiduciary’s failure to perform her duty after the bond was given, relying on explicit language in the suretyship contract and provisions of the Probate Code.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Larson v. Granite Re, Inc.
532 F.3d 724 (Eighth Circuit, 2008)
Hinkle v. Wayne County Clerk
631 N.W.2d 27 (Michigan Court of Appeals, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
617 N.W.2d 49, 241 Mich. App. 686, Counsel Stack Legal Research, https://law.counselstack.com/opinion/leonard-c-carnaghi-inc-v-amwest-surety-ins-co-michctapp-2000.