Peet v. City of East Grand Forks

112 N.W. 1005, 101 Minn. 523, 1907 Minn. LEXIS 616
CourtSupreme Court of Minnesota
DecidedJuly 12, 1907
DocketNos. 15,229-(150)
StatusPublished
Cited by5 cases

This text of 112 N.W. 1005 (Peet v. City of East Grand Forks) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peet v. City of East Grand Forks, 112 N.W. 1005, 101 Minn. 523, 1907 Minn. LEXIS 616 (Mich. 1907).

Opinion

BROWN, J.

This action involves the same transaction that was under consideration in the preceding case between the same parties (supra, p. 518, 112 N. W. 1003), in which a brief outline of the facts is given. In this action recovery is sought upon the engineer’s estimate issued under contract designated “No. 1”; the same covering a piece of work performed under the general contract, independent of that involved in that case. One material- difference between the two cases is found 'in the fact that in the other case the engineer’s estimate was made for a partial, while in this case it was made for a full, performance of the contract. As in the other case, the estimate was issued by the engineer and delivered by him to the contractor, who in turn submitted it to the city council, by which body it was approved and confirmed. No warrant was issued for the amount certified to be due, $11,701.84, and the action was brought by plaintiff, to whom the estimate was duly assigned by the contractor, to recover thereon.

The defense interposed by the city was that the contractor had failed substantially to perform his contract in the respects pointed out in the answer, and that the estimate was fraudulently issued by the engineer with the full knowledge and connivance of the contractor.

The trial court found both defenses true, and further found that the damage suffered by the city by the failure of the contractor to perform the contract in accordance with its terms amounted in value to the sum of $4,865. This amount the court deducted from the total amount due the contractor according to the engineer’s estimate, and ordered [525]*525judgment in plaintiff’s favor for the balance, $6,361.84. Judgment was entered accordingly, and defendant appealed.

Upon what theory of the law the learned trial court proceeded in ordering judgment for plaintiff for the contract price of the work less the damage suffered by the city from the failure of the contractor to comply with his contract is not made clear by the record. The finding of a breach of contract, based upon a charge that the contractor improperly did the work and used materials not called for by the plans and specifications, and the finding that the engineer’s estimate was fraudulently issued, are unchallenged, are supported by evidence, and, in our view of the principles of law applicable to the questions presented, conclusive against any recovery at all by plaintiff, unless, perhaps, one or.all of the contentions made by him, to be referred to presently, are sustained. It is elementary that, where one of the parties to an entire contract fails to perform the same in accordance with 'its terms .and provisions, he is not entitled to compensation for a partial performance ; there being no waiver of his breach by the other party. , A failure to perform in a substantial respect is affirmatively found as a fact in this case. There was no waiver thereof by defendant. At least, none is found by the court, and the general rule referred to •must apply. The failure of the city to pay the estimate in accordance with the contract and the city charter applied to this, as well as the other case, and it is probable the trial court adopted the view, urged in that case, that the failure of the city in this respect justified the ■contractor in abandoning further work under the contract and entitled him to recover upon quantum meruit as for partial performance. Reference is made to this subject in the opinion in the other case, but the rule referred to can have no application here. It appeared in the ■other case that the work actually performed was in substantial compliance with the terms of the contract, so far as it progressed, while in this case the contract was not complied with, but was substantially violated. In' the former situation the contractor is, under the authorities, entitled to the value of the work actually performed; while here the contractor committed the breach, and brought himself within the general rule which precludes his recovery for the work actually performed. Plaintiff is in no better position than the contractor would have been, had he brought the action; and it is beyond question that lie could not recover. The court was therefore in error, from the [526]*526standpoint of its findings, in directing judgment for plaintiff for the difference between the contract price of the work and the damages suffered by the city.

But it is contended by plaintiff (1) that defendant is estopped from-denying its liability; and (2) that the estimate upon which the action was founded, conceding it to have been invalid by reason of the facts-found by the trial court, was validated by section 9, c. 382, p. 695, Laws 1903; and (3) that the city waived the breach of contract by consenting to the use of material different in kind from that called for by the contract.

The first contention referred to, that defendant is estopped from denying its liability, is based upon the fact, appearing from the record, that the engineer’s estimate was formally approved and confirmed by the city council, coupled with the contention that plaintiff became the purchaser of the estimate in the usual course of business for a valuable consideration and in reliance upon the approval of the city council, which was attached thereto. The court below made no findings upon this question, either one way or the other, and the evidence is not cow-elusive in plaintiff’s favor that defendant is estopped from denying its liability. The only theory upon which the doctrine could be invoked is that by the conduct of the city council in formally approving and confirming the action of the engineer the estimate was held out to the commercial world as a valid obligation of the city, upon which plaintiff had the right to rely in purchasing the same, and that it should not now be permitted to change its position to the plaintiff’s prejudice. The evidence does not show that the approval of the estimate was relied upon by plaintiff when he purchased it from the contractor, or that he knew of its existence. There is nothing, therefore, to show that plaintiff was in any way misled by the action of the city council, if it be conceded that he was a purchaser of the estimate for a valuable consideration — a question which, in view of the fact that there must be another trial of the action, we do not consider.

The second contention, namely, that the invalidity of the estimate as an evidence of indebtedness against the city was cured, and all defenses interposed by the city in this action extinguished and rendered unavailable, by section 9, c. 382, p. 695, Laws 1903, cannot be sustained. That statute was before us in Merchants’ Nat. Bank v. City of East Grand Forks, 94 Minn. 246, 102 N. W. 703, a case involving this same im[527]*527provement contract, where its application to city warrants issued in payment for work performed under the contract was under consideration. We there held, speaking through Mr. Justice Jaggard, that all defects and irregularities antecedent to the issuance of the city warrants were cured by the statute. But the decision is not an authority here. The statute can have no application to the facts of this case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fuller v. Mohawk Fire Insurance Co.
245 N.W. 617 (Supreme Court of Minnesota, 1932)
Snortum v. Snortum
193 N.W. 304 (Supreme Court of Minnesota, 1923)
Town of Farley v. Town of Boxville
129 N.W. 381 (Supreme Court of Minnesota, 1911)
Peet v. City of East Grand Forks
122 N.W. 327 (Supreme Court of Minnesota, 1909)
Thornton v. City of East Grand Forks
118 N.W. 834 (Supreme Court of Minnesota, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
112 N.W. 1005, 101 Minn. 523, 1907 Minn. LEXIS 616, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peet-v-city-of-east-grand-forks-minn-1907.