Moore v. Maryland Casualty Co.

12 F. Supp. 90, 1935 U.S. Dist. LEXIS 1300
CourtDistrict Court, D. Massachusetts
DecidedAugust 6, 1935
DocketNo. 3142
StatusPublished
Cited by1 cases

This text of 12 F. Supp. 90 (Moore v. Maryland Casualty Co.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moore v. Maryland Casualty Co., 12 F. Supp. 90, 1935 U.S. Dist. LEXIS 1300 (D. Mass. 1935).

Opinion

BREWSTER, District Judge.

This is an action at law, brought upon a surety bond given by the defendant to secure the completion of a building in Brookline. The principal obligor was the Pelham Hall, Inc., a Massachusetts corporation, organized for the purpose of acquiring land and erecting thereon an apartment house known as “Pelham Hall.”

The action was referred to an auditor and was later recommitted, for further findings of fact. The case was tried without a jury upon the auditor’s original and supplemental reports and exhibits. The bond is in the penal sum of $500,000. Its execution in the regular course of business upon payment of an established premium is admitted.

Apparently the parties proceeded before the auditor as if the action was for breach of condition of the bond. Accordingly, if plaintiff is entitled to recover on the bond, he is entitled to a judgment for the penal sum of $500,000, execution to be awarded for so much of the penal sum as is “due and payable in equity and good conscience” at time of issuance of execution. Gen. Laws (Ter. Ed.) Mass. c. 235, §§ 9 and 10.

The first question, therefore, to be decided is whether, on the facts found by the auditor, plaintiff has made out a case of breach of covenant of defendant’s bond.

Before the auditor, the controversy was waged along a wide front. Numerous defenses, some of them technical, were interposed, but inasmuch as the argument before me related principally to the question whether the defendant was released by reason of certain changes made in the building as the work progressed, I confine my opinion to that single issue.

My views on the other defenses are indicated in my rulings on requests.

In order to better understand the consideration of this question, a preliminary statement of facts appearing in the auditor’s report is necessary. The Pelham Hall, Inc. (hereinafter referred to as the owner) financed the construction of the building by means of an issue of bonds, secured by a mortgage on the land and on the building which it agreed to erect. It entered into a written contract with the American Bond & Mortgage Company, Inc. (hereinafter referred to as the American Company), to sell the bonds. This contract, called the “Brokerage Agreement,” was entered into on the 7th day of July, 1925. Pertinent provisions of this contract will be referred to later. According to its terms, a mortgage was given to the plaintiff, as individual trustee, and to the American Trust and Safe Deposit Company, an Illinois corporation, as corporate trustee, to secure an issue of $1,200,000 in amount of bonds of the owner. The brokerage agreement required the owner to give a bond with sufficient surety in the penal sum of $500,000 for the completion of the building by the owner. This bond was given, the owner being the principal and the defendant the surety, and ran to the American Company, to the plaintiff as individual trustee, and to the holders, from time to time, of the bonds. According to the terms of the brokerage agreement and the mortgage, the building was to be completed before August 1, 1926. The general contractor, who undertook the work of construction, became financially involved and abandoned the work. The owner was not able to complete the building with the unexpended balance derived from the sale of the bonds, and the defendant was called on to complete the building. This, the defendant refused to do, whereupon the plaintiff took possession, completed the building [92]*92and expended for that purpose $181,500 in addition to $125,000 then in the hands of the American Company. This $181,500 was borrowed by the plaintiff from the American Company and expended by him in the completion of the building.

During the progress of the work, changes were made in the plans without the consent of the defendant. Because of the changes, the defendant now contends that it cannot be held liable on its bond.

In order to dispose of defendant’s contention, it is necessary to consider first the undertakings of the principal, for which the plaintiff became surety; second, the contract of suretyship; and, third, the changes and their legal effect.

The findings of fact made by the auditor are not attacked, although plaintiff assails, as erroneous, certain conclusions of law embodied in the auditor’s report.

First: The owner’s agreement respecting the construction and erection of the building is found in two instruments, namely, the brokerage agreement, and the mortgage. In the brokerage agreement it is recited that the owner is to start erecting “an eight story, basement and penthouse apartment building to contain approximately 415 rooms and 1,390,000 cubic feet, as further defined in paragraph 15, page 5 and schedule ‘B’ of this agreement.” (Italics supplied.)

Paragraph 15 is a guarantee by the owner that the building erected will contain not less than the stipulated number of cubic feet.

Schedule B, entitled “Description of Building which the Owner agrees to erect,” gives certain specifications, of which the following are pertinent. It shows that the building was to be an eight-story, fireproof building, with stores and apartments on the first floor and apartments on all floors above. The number of apartments was “to be in accordance with plan to be approved by broker.” In the brokerage agreement the owner further covenanted with the broker “for the use and benefit of the trustee or trustees and of each of the holders of the bonds to be secured by said mortgage” ; that it submitted to the broker only a preliminary sketch of the typical floor plans of the building, and that it would submit and deliver to the broker within 45 days from the date thereof complete plans and specifications prepared by an architect satisfactory to the broker, and the owner agreed to employ a general contractor satisfactory to the broker. Thé owner agreed that all contracts with contractor should provide for the erection and construction of the building according to plans, drawings, and specifications presented to and approved by the broker, and that it would make no alteration, modification, or changes in the contract without the approval of the broker. The brokerage contract contains also the following paragraph : “Should the plans or any modification thereof not be in the hands of the broker at the time of the execution of this agreement they shall be submitted _ to the broker before they are approved by the Superintendent of Buildings or any other department or official whose approval is required and the building shall be constructed in strict accordance with the plans and specifications and such modifications as are approved by the broker in writing:’ (Italics supplied.)

It was covenanted that if the construction of the building should be discontinued at any time, the trustee might complete the building, and any sum expended for that purpose in excess of the proceeds of the bond should be deemed as additional indebtedness secured by the mortgage.

The owner agreed in the brokerage agreement, as part consideration for the broker entering into the contracts, to furnish to the broker a surety bond with a surety company thereon as surety running to and operating for the benefit of the broker; the trustees in the mortgage and the holders of the bond, to secure which the trust mortgage was given, guaranteeing the completion, and the full payment by the owner, of the building, to be when completed free and clear of any and all liens equal or superior to the lien of the first mortgage.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stout v. Napolitano
18 F. Supp. 3d 9 (District of Columbia, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
12 F. Supp. 90, 1935 U.S. Dist. LEXIS 1300, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moore-v-maryland-casualty-co-mad-1935.