Hileman & Gindt v. Faus

178 Iowa 644
CourtSupreme Court of Iowa
DecidedJune 29, 1916
StatusPublished
Cited by6 cases

This text of 178 Iowa 644 (Hileman & Gindt v. Faus) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hileman & Gindt v. Faus, 178 Iowa 644 (iowa 1916).

Opinion

Preston, J.

1. Appeal and error: assignment of ©rroi’s ¡ as- . signmentby nonappellant. Appellee surety company has assigned cross-errors by which it is claimed the court erfed in overruling its demurrer to the petition, and that the court erred in rendering judgment by default against it. •, The defendant surety company answered, after its demurrer was overruled, and the default was, on its motion, set aside, and, as it has not appealed, we do not understand that the assignment of cross-errors, under such circumstances, raises any question for determination. The appellee Southern Surety Company for a paid consideration signed the bond upon which suit is brought, as surety for Faus. Hileman & Gindl, as owners, on February 21, 1913, entered into a contract with D. P. Faus, as contractor, by which Faus was to erect a business block for $12,000, te be—

“paid by the owner to the contractor, in current funds, and only upon certificates of the architect, as follows: 85% of all work completed and all materials on the ground to be computed in value on or about the first of each month, and payment made for same upon proper certificate of the architect. The final payment shall be made within 30 days after the completion of the work included in this contract, and all payments shall be due when certificates for the same are issued. If at any time there shall be evidence of any lien or [647]*647claim, for which, if established, the owner of the said premises might become liable, and which is chargeable to the contractor, the owner shall have the right to retain out of any payment then due or thereafter to become due, an amount sufficient to completely indemnify him against such lien or claim. Should there prove to be any such claim after all payments are made, the contractor shall refund to the owner all moneys that the latter may be compelled to pay in discharging any lien on said premises made obligatory in consequence of the contractor’s default.”

For the purpose of protecting the owners against any liens or claims for which the premises might be liable, and to secure the refund which the contractor was required to make to the owners under the foregoing provisions of the contract, the contractor, Faus, on February 26, 1913, gave to the owners a bond of $4,000, in which he is named as the principal, which recites as follows:

“Whereas, said principal has entered into a certain written eontraht with the obligee for the substantial erection and completion of all concrete and reinforced concrete work in connection with a building to be erected by the said owner on Mulberry Street, Waterloo, Iowa, ih strict accordance with the plans, specifications and contract as prepared by Mortimer B. Cleveland, architect, for the sum of $12,000;
“Now, therefore,- the condition of the foregoing obligation is such that, if the said principal shall well and truly indemnify and save harmless the said obligee from any pecuniary loss resulting from the breach of any of the terms, covenants and conditions of the said contract on the part of the said principal to be performed, then this obligation shall be void,; otherwise to remain in full force and effect in law. ’ ’

The contract also provides that the owner may take charge of the work in case the contractor fails to perform as set out in the contract, and provides the manner of doing so, and that the owner shall provide labor and material for extras, so as hot to delay the contractor. The contractor [648]*648commenced the work, and the owners paid, from time to time, without certificates from the' architect, but upon presentation of labor accounts and material bills which the owners satisfied themselves had been furnished, and plaintiff claims that at no time was there paid more than “85' per cent of all work completed and all materials on the ground; ’ ’ although the aggregate amounts paid, up to October 29, 1913, exceeded $12,000 by the sum of $1,362.20. On the last named date, the owners notified the surety company that Faus had not completed the contract, and had abandoned the work. On November 5, 1913, the surety company wrote the owners, denying liability, upon the ground that the owners had “violated your contract with Mr. D. P. Faus in several material matters, and this company, as surety on the contract bond, has been thereby released.” On November 7, 1913, another notice was given the surety company. The owners thereupon completed the building according to contract, at an additional expense of $3,092.67, making an entire cost to the owners of $16,454.87, or $4,454.87 above the contract price of $12,000. Proofs of loss were served, and thereafter a suit was commenced by the owners to recover $4,000 of the amount of the surplus payment, which, as they claim, Faus agreed to refund, and, to secure the payment of which refund, the surety company signed the bond sued upon. A default was entered against the surety company, which was afterwards set aside; but on the trial as to Faus, certain credits were allowed Faus, and judgment was rendered for $3,755.85, with interest at 6 per cent from January 20, 1914.

After the court had sustained defendant’s motion to direct a verdict in its favor, a stipulation was entered into between the parties to this effect: That, if the case is reversed in the Supreme Court, such judgment may be there entered against the Southern Surety Company in a like amount as that which may be finally recovered by plaintiffs against the defendant Faus in the action now proceeding between plain[649]*649tiff and defendant Faus, not. to exceed the sum of $4,000, with interest from October 7, 1913, and costs, which judgment shall provide, upon the payment thereof by the surety company, that it shall'be subrogated in like amount to any judgment which plaintiff may recover against said defendant Faus.

The issues, as appellant states them, and the errors assigned, relate: First, to the question whether the default entered against the appellee Southern Surety Company was properly set aside, and the appellee permitted to answer; second, to the question whether the contract with the appellee was breached by the appellant, and the surety company thereby released; and, third, to * the question whether the appellee surety company had waived certain of the alleged breaches of the indemnity contract relied upon by appellee as excusing it from the performance of its contract of indemnity.

2. judgment: aeulmvoidaWe °n: casualty.

1. When defendant’s demurrer to the petition was submitted, a written stipulation was entered into, to the effect that, if either party did not' wish to stand on the ruling should be made on the demurrer, ten days should be allowed to the defendant to answer or plead, and to the plaintiff to amend. The statute substantially provides that, for unavoidable casualty or misfortune preventing a party from prosecuting or defending, the district court may vacate the final judgment rendered. The ruling on the demurrer was April 24, 1914, and the ten days allowed under .the stipulation expired May 4th. An answer in general denial was filed May 6th, and later, on May 11th, the application and showing to set aside the default were filed, and another answer tendered. As we understand it, the defendant at that time did not have a local attorney, and it is made to appear that defendant’s counsel was engaged in the trial of a ease in New York City. Without setting out the entire showing, it appears that the clerk for defendant’s counsel, upon receiving word [650]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rowe v. Stufflebeam
89 N.W.2d 875 (Supreme Court of Iowa, 1958)
Iowa Trust & Savings Bank v. Soppe
247 N.W. 632 (Supreme Court of Iowa, 1933)
Onida Independent School Dist. No. 1 v. Groth
221 N.W. 49 (South Dakota Supreme Court, 1928)
Lamson v. Maryland Casualty Co.
196 Iowa 1185 (Supreme Court of Iowa, 1923)
Sheldon v. Chicago Bonding & Surety Co.
190 Iowa 945 (Supreme Court of Iowa, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
178 Iowa 644, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hileman-gindt-v-faus-iowa-1916.