Fidelity & Deposit Co. v. Agnew

152 F. 955, 1907 U.S. App. LEXIS 4355
CourtCourt of Appeals for the Third Circuit
DecidedApril 10, 1907
DocketNo. 31
StatusPublished
Cited by21 cases

This text of 152 F. 955 (Fidelity & Deposit Co. v. Agnew) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fidelity & Deposit Co. v. Agnew, 152 F. 955, 1907 U.S. App. LEXIS 4355 (3d Cir. 1907).

Opinion

ARCHBALD, District Judge.

The provision in a building or working contract that the contractor or builder shall be paid as the work progresses according to the amount of materials furnished or work performed, upon estimates to be made by the supervising architect or engineer, whether a percentage is to be retained therefrom, until the whole is done or not, redounds to the benefit of a surety or guarantor of the party who is to fulfill the contract; and, upon payment being made in disregard of it, there is such a departure from the contract upon which the undertaking of the surety or guarantor is based that he is released. The purpose of'such a stipulation is to guard against the consequences of a default, in case the principal contract proves a losing one, or the contracting party for-any reason fails to comply, the percentage retained, where that is provided for, affording additional security, as well as holding out an incentive; and when it is not observed, and advance or overpayments are made, it is so obviously to the prejudice of the surety that it operates as a discharge as matter of law. Steam Navigation Co. v. Bolt, 6 Com. Bench N. S. 550; Calvert v. London Dock Co., 2 Keen, 639; Prairie State Bank v. U. S., 164 U. S. 227, 17 Sup. Ct. 142, 41 L. Ed. 412; Shelton v. American Surety Co. (C. C.) 127 Fed. 736, affirmed 131 Fed. 210, 66 C. C. A. 94; Welch v. Hubschmitt, 61 N. J. Law, 57, 38 Atl. 824; Village of Chester v. Leonard, 37 Atl. 397, 68 Conn. 495; Fitzpatrick v. McAndrews, 12 Pa. Co. Ct. Rep. 353. This is too well established to be controverted, and the only question is how far it applies here.

The bond upon which suit is brought was given by the Avondale Marble Company, as principal, with the Fidelity & Deposit Company [957]*957of Maryland, as surety, to W. H. H. Van Houten, in the stun of $66,-000, for the faithful performance of an agreement entered into by the marble company, to furnish and deliver marble and granite for the new courthouse, in process of construction at Paterson, N. J., of which Mr. Van Houten was the contractor or builder. By the agreement referred to it was, among other things, stipulated that “the sum to be paid by the party of the second part [Van Houten] to the party of the first part [the marble company] for the said materials shall be one hundred and ten thousand dollars” (subject to deductions as therein provided), and that the said sum should be paid in current funds on or about the 5th day of each and every month, “upon estimates made by the architect in charge of said work, of the material on the ground, delivered during the preceding month,” the marble company to be paid 90 per cent, of the amount of these estimates, and 90 (lays after the architect should have accepted all the material the retained 10 per cent, to be paid to the marble compaj^ upon its furnishing satisfactory evidence that no liens existed thereon. The marble and granite was to be delivered f. o. b. at the quarry, at Avondale, Chester county, Pa., and shipped to Van Tiouten, the contractor, with the cost of the freight from the quarry to the city of Paterson “to be allowed and deducted” by him from the contract price; and upon failure to deliver it, as required by the agreement, he was to be at liberty, upon five days’ written notice, to supply the material and deduct the cost from the moneys due. The complaint of the surety is that, instead of adhering to the terms of the agreement and paying upon estimates of the architect as the work went on, no estimates, or at least none worthy of the name, were made, with the result that, with the knowledge of the contractor, payments were allowed which' were greatly in excess of the material delivered; and, further, that, when but a fraction of the agreement had been performed, the marble company, needing money to conduct its operations, was favored with large advances to be met b}r future deliveries, this arrangement continuing down to the close* of the transaction, the restrictions provided by the agreement being thereby virtually abrogated. Instructions appropriate to these issues were asked at the trial, and, in view of the undisputed evidence with regard to them, the request was made by the surety that a verdict be directed in its favor. This was refused, and, the case having been submitted to the jury, a verdict of some $40,000 was rendered against it, upon which the record is now brought here for review.

The question whether estimates were in fact made was for the jury under proper instructions, provided there was evidence upon which to predicate it. But, unfortunately, all that there was upon this subject was that Mr. Reed, the supervising architect, approved the invoices, on which the material was billed from the quarry by the marble company, after going over them at the end of each month with the contractor or his son, who had charge of this part of his father’s business. This was clearly not a compliance with the agreement. An estimate such as .is there spoken of necessarily involved, not only an approximate judgment, upon inspection by the architect or, his representative, [958]*958of the quantity and value of the material delivered, .having regard to its character, whether granite, marble, or carved marble, as to which there was a considerable difference, but the relative value of it to the total quantity which had been contracted for. And when it is considered that, out of a total contract price of $110,000, representing 82,000 weighed feet to be delivered, bills for some $105,000 were approved and paid, when but 60,000 weighed feet, having a relative value of but $73,000, had been furnished — an overpayment of $32,000' — • it is altogether too much to ask that the mere looking over of the invoices in the way described shall be accepted as in any sense constituting an estimate such as was contemplated. The prejudice of this to the surety is manifest, the overpayment made being substantially the amount above the contract price, which is now demanded, which, had it been kept back by the contractor as provided in the agreement, he would have had in hand enough to cover the material unfurnished, without calling^pon fhe surety.

No doubt the_ contractor was not chargeable with the inefficiency or mistakes of the architect, provided an attempt at an estimate was really made; and, in the absence of notice to the contrary, an approval of the invoices may have been sufficient for him to act upon without a' formal certificate, nothing being said about that' in the agreement. But not only were the deficiencies in the deliveries so gross as tó put him upon inquiry, but the only basis for the architect’s approval, to his certain knowledge, being the invoices on which the material was' shipped, and the representations made at the time by himself and his son, one or both, with regard to them, he was fully advised as to how the approvals were obtained, and just what they amounted to, and they are only available to him here, in consequence, for what they stand. That Mr.'Van Houten was also aware, at least in a general way, from the. outstart, of the discrepancy in deliveries, is shown by his letters — one of January 5, 1898, complaining that not a hundredth-part of the material had been furnished, which would only have entitled the marble company to about $1,000, ‘after deducting the percentage, although bills to the extent of $4,450 had been already approved and paid; and another of August 4th, declaring that not quite a quarter was on the ground, at which time $30,311 had been paid, as against $24,750 due, an advancement of'some $5,000. It is not necessary to consider whether, even though no estimates were made, Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sandusky Grain Co. v. Borden's Condensed Milk Co.
183 N.W. 218 (Michigan Supreme Court, 1921)
Globe Indemnity Co. v. Unity Rys. Co.
272 F. 607 (Third Circuit, 1921)
Williams v. Baldwin
228 S.W. 554 (Texas Commission of Appeals, 1921)
Harvey v. George
175 N.W. 140 (Michigan Supreme Court, 1919)
Texas Fidelity & Bonding Co. v. Rosenberg Independent School Dist.
195 S.W. 298 (Court of Appeals of Texas, 1917)
Neilson v. Title Guaranty & Surety Co.
159 P. 1151 (Oregon Supreme Court, 1916)
Fort Dodge, Des Moines & Southern Railroad v. Burns
177 Iowa 51 (Supreme Court of Iowa, 1916)
Doyle v. Faust
153 N.W. 725 (Michigan Supreme Court, 1915)
Maine Central Railroad v. National Surety Co.
94 A. 929 (Supreme Judicial Court of Maine, 1915)
Wells v. National Surety Co.
222 F. 8 (Third Circuit, 1915)
Justice v. Empire State Surety Co.
218 F. 802 (Third Circuit, 1914)
Burroughs v. Joint School District No. 2
144 N.W. 977 (Wisconsin Supreme Court, 1914)
Justice v. Empire State Surety Co.
209 F. 105 (E.D. Pennsylvania, 1913)
City of Chicago v. Agnew
182 Ill. App. 499 (Appellate Court of Illinois, 1913)
Young Men's Christian Ass'n v. Ritter
133 P. 894 (Supreme Court of Kansas, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
152 F. 955, 1907 U.S. App. LEXIS 4355, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fidelity-deposit-co-v-agnew-ca3-1907.