Shelton v. American Surety Co.

127 F. 736, 1904 U.S. App. LEXIS 4639
CourtU.S. Circuit Court for the District of Eastern Pennsylvania
DecidedFebruary 9, 1904
DocketNo. 84
StatusPublished
Cited by6 cases

This text of 127 F. 736 (Shelton v. American Surety Co.) is published on Counsel Stack Legal Research, covering U.S. Circuit Court for the District of Eastern Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shelton v. American Surety Co., 127 F. 736, 1904 U.S. App. LEXIS 4639 (circtedpa 1904).

Opinion

J. B. McPHERSON, District Judge.

This case arises upon the plaintiff’s statement of claim and the affidavit of defense that has been filed thereto. The facts which appear upon these papers, and, indeed, are undisputed, are as follows: The plaintiff, being about to alter a house, made a contract with a firm of builders, by which it was provid-, ed, inter alia, that the architect should value the work done and the materials furnished each month, and that 80 per cent, of his valuation should be paid to the builders. Under this provision $5,736.43 was paid in four installments. The builders then became insolvent, and the plaintiff completed the work, but he was obliged to pay $2,901.05 more, than the contract price. Under the paragraphs of the contract that are now to he considered the builders were required to apply the installments received by them in payment for work done and materials furnished to the building, but, in violation of these provisions, they only applied $2,833.38, using the balance, $2,901.05 for other purposes. For this balance, included in a larger sum that embraced other claims as well, mechanics’ liens were filed, which the plaintiff was obliged to pay. The present suit is brought against the builders’ surety to recover $2,500 and interest, this being the principal of. the defendant’s bond. The paragraphs in question are as follows:

“(b) That no payments shall become due until in each case the contractors shall have delivered to the architect copies of all bills and vouchers for work done and materials furnished upon which payment is claimed to be done, or until they have given the architect a true and accurate account of the exact standing of all accounts to date, on their books, for the work herein contracted for, and shall have delivered to the owner a satisfactory release of all liens against the premises on the part of all persons, who have delivered materials for use in or performed work on said premises, together with a true and accurate showing of the state of such persons’ accounts then due, or thereafter to become due, for materials to be furnished or work to be done under this agreement.
“And it is further agreed, that before the final payment shall become due a full and complete release of liens, including the liens of the parties ol’ the first part, shall have been delivered to the party of the second part, and accepted by him as satisfactory.
“(e) That no liens, attachment or other .incumbrance under any law of this, state, or otherwise, by any person or persons whosoever, shall at any time be put or remain upon the building or premises, unto or upon which any work is done or may be done, or materials are furnished or may be furnished under this contract for such work or material or by reason of any claim or demand against the contractors in respect thereof.
“And it is further agreed, that if at any time there shall be any lien or claim, which if established, the owner of the said premises might be made liable, and which would be chargeable to the said contractors, the owner shall have the right to retain out of any payment then due, or thereafter to become due, an amount sufficient to completely indemnify him against such lien or claim, until the same be effectually satisfied, or discharged or cancelled, and should there prove to be any such claim after, all payments are made, the contractors do hereby covenant that they will refund to the owner all moneys, that the latter may be compelled to pay discharging any lien on said premises, and obligatory in consequence of the former’s default.’.’ ' ,, ,

[738]*738As already stated, four installments were paid by th,e plaintiff, but he did not require a release of liens to be delivered in accordance^ with the provisions of paragraph “b,” and this failure upon his part is set up as a defense. To this the plaintiff replies that the provision referred to was merely intended for his own protection, and that he was at liberty to waive it if he chose, without danger to his rights against the surety. I cannot agree to the correctness of this position. There can be no doubt that paragraph “b” was intended for the protection of the plaintiff, and perhaps primarily for his protection; but its enforcement would also protect the surety by. compelling the builders to pay the workmen and materialmen as the work went on, thus diminishing the risk that the surety might suffer from the failure of the builders to fulfill their contract concerning liens. The danger of liens was provided against as carefully as possible. Before any installment could become due, copies of bills and vouchers for work and materials were to be furnished, or a true account of these subjects taken from the builders’ books was to be presented, accompanied by a release from all persons entitled to a lien up to that time, together with a true showing of the accounts of such persons with the builders. But, in spite of these precautions, it was recognized that the builders might be careless, or might deceive the architect about these matters, and therefore it was provided that a further release should be given before final payment should become due; and, as even this might not fully protect the owner against the builders’ neglect or dishonesty, an additional paragraph was added, giving the plaintiff a right of action against the builders if any liens should be enforced against the premises after the final payment. As it seems to me, the most important of these safeguards was the first. If these releases were demanded, bills would be paid as the work went on, for the builders could not obtain releases unless they paid the workmen and materialmen, and the result would be that debts could not, accumulate and become too heavy a load for the builders to ca'rry. If they could not pay their debts, liens would become inevitable. In the enforcement of this provision, therefore, the surety was vitally interested, and the plaintiff’s failure to insist upon it is, I think, a bar to recovery.

The rule that a surety’s contract may not be materially changed without his consent is well known. Recent declarations of the rule are found in Prairie State Bank v. United States, 164 U. S. 227, 17 Sup. Ct. 142, 41 L. Ed. 412, and Fidelity Co. v. United States (decided in December, 1903, and not yet officially reported) 24 Sup. Ct. 142, 48 L. Ed. —. Whether the facts of this case justify me in speaking of what was done as a change of the contract, or whether it is more accurate to speak of it as a departure from the contract, seems to be of minor importance. The same consequences follow whether it be a departure or a change. As is said by Brandt in his work on Suretyship,- par. 345 :

“Any dealings with the principal by the creditor, which amount to a departure from the contract by which the surety is bound, and which by possibility might materially vary or enlarge the latter’s liabilities without his consent, generally operate to discharge the surety.”

In a careful opinion by Judge Archbald, now on the bench of the middle district of Pennsylvania (Fitzpatrick v. McAndrew, 12 Pa. Co. [739]*739Ct. R. 353), he pronounces in favor of tlie word “departure,” where the owner pays the builder more rapidly than the contract provides, and it may be that “departure” is the better word to use where the surety complains of a failure to require a release of liens.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Porter v. Hope
279 S.W. 535 (Court of Appeals of Texas, 1926)
Pauly Jail Building & Manufacturing Co. v. Collins
120 N.W. 225 (Wisconsin Supreme Court, 1909)
Fidelity & Deposit Co. v. Agnew
152 F. 955 (Third Circuit, 1907)
York City School Dist. v. Ætna Indemnity Co.
131 F. 131 (U.S. Circuit Court for the District of Middle Pennsylvania, 1904)
Shelton v. American Surety Co.
131 F. 210 (Third Circuit, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
127 F. 736, 1904 U.S. App. LEXIS 4639, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shelton-v-american-surety-co-circtedpa-1904.