Garden City Floral Co. v. Hunt

255 P.2d 352, 255 P.2d 252, 126 Mont. 537, 1953 Mont. LEXIS 18
CourtMontana Supreme Court
DecidedMarch 26, 1953
Docket9136
StatusPublished
Cited by38 cases

This text of 255 P.2d 352 (Garden City Floral Co. v. Hunt) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Garden City Floral Co. v. Hunt, 255 P.2d 352, 255 P.2d 252, 126 Mont. 537, 1953 Mont. LEXIS 18 (Mo. 1953).

Opinion

MR. JUSTICE ANGSTMAN:

Defendants have appealed from a judgment rendered against them on a verdict in favor of plaintiff in the sum of $18,655.

Plaintiff owns two tracts of land in the city of Missoula. On the easterly tract, prior to September 1950, there was a building known as the Bedard building. On August 25, 1950, plaintiff entered into a written agreement with defendant Hunt by the'terms of which Hunt agreed to erect a building on the westerly tract using the west wall of the Bedard building as the east wall of the new building. The contract expressly recited that the specifications and drawings were a part of the contract as if attached thereto or repeated therein. According to the drawings or specifications the new building was to have a 12- *539 foot basement and the west wall of the Bedard building was to be underpinned with concrete in four-foot blocks along its entire length. Defendant Hunt was required to and did furnish a performance bond executed by defendant Continental Casualty Company as surety.

Shortly after the making of the contract defendant Hunt commenced the excavation for the new building, using a bull dozer for that purpose. As a result of the excavation the west wall of the Bedard building collapsed and fell into the excavation. Plaintiff, believing that the Bedard building could not be repaired, caused it to be torn down. This action seeks recovery for damages suffered by plaintiff as the result of the loss of the Bedard building and for indemnity to plaintiff for damages which it may be required to pay to tenants of the Bedard building because of damages sustained by the tenants.

The complaint consists of two causes of action. In the first cause of action it is alleged that defendant Hunt did not use a reasonable or any degree of skill in making the excavation in that he dug a trench along the entire west wall of the Bedard building, deeper than the bottom of the foundation of the Bedard building, and so close to it that the earth and dirt under the foundation slid into the trench; that because thereof the west wall was deprived of lateral support as well as support of the ground upon which it had previously rested and that it therefore fell of its own weight.

The second cause of action alleges that the drawings for the building called for underpinning of the wall of the Bedard building in four-foot blocks along its entire length; that in the contracting business this meant that the excavation should be done in alternate four-foot strips so that each excavated section has a four-foot strip of earth on each side of it; that when a four-foot section is excavated, concrete is poured and allowed to set and that after one section of concrete is poured another excavation of a four-foot strip is made and poured and thus the wall is never deprived of support along its whole length. It is alleged that defendant Hunt breached this part of his contract *540 and dug the trench along the entire length of the wall and dug it deeper than the bottom of the foundation under the Bedard wall and so close to it that the earth under the foundation slid into the trench and the wall was deprived of support causing it to fall of its own weight; that had defendant Hunt used the method of underpinning set out in the drawings the excavation would have been made without damage to the wall.

One question presented by the appeal is whether plaintiff may maintain this action against defendants for such damages where it predicates liability because of the unskillful and neglectful manner in which defendant Hunt performed the excavating resulting in the collapse of the Bedard building.

Defendants take the view that if there be liability for such damages, it must sound in tort and not for breach of contract. Defendant Casualty Company contends that it is not liable for the damages complained of because such damages were not intended to be within the coverage of the bond. Another contention is that plaintiff failed to provide a duly qualified architect, with full supervisory authority and hence that plaintiff did not comply with its part of the contract and that such failure on the part of plaintiff operated to release the Casualty Company.

The bond contains this provision: “Now, therefore, if the Principal shall faithfully perform such contract * * * and shall indemnify and save harmless the Owner from all costs and damages by reason of the Principal’s default or failure so to do, then this obligation shall be null and void; otherwise it shall remain in full force and effect.”

The Casualty Company contends that the terms of the bond do not cover costs and damages arising from the manner in which Hunt performed the terms of his contract. It relies upon National Surety Co. of New York v. Ulmen, 9 Cir., 68 Fed. (2d) 330. In that case it was a third party and not a party to the contract of suretyship who brought the action. What was said in that case must be confined to the facts then before the court.

Here the surety contracted that Hunt would faithfully per *541 form his contract and indemnify and save plaintiff harmless from all costs and damages by reason of his default or failure so to do.

A contract of employment carries with it the obligation to do the work in a reasonably skillful manner. Williston on Contracts, Eev. Ed., Yol. 4, sec. 1014, p. 2792; 38 Am. Jur., Negligence, sec. 20, p. 662. This is also the effect of our statutes, E. C. M. 1947, secs. 41-208 and 41-209. And see Schwab v. Peterson, 80 Mont. 214, 260 Pac. 711.

In the note in 12 L. E. A., N. S., 924, the rule is stated as follows: “Whenever a negligent breach of a contract is also a violation of a common-law duty, an action ex delicto will lie. Accompanying every contract, is a common-law duty to perform the thing agreed to be done with care, skill, reasonable expediency, and faithfulness, and a negligent failure to observe any of these conditions is a tort, as well as a breach of the contract.” To the same general effect are: Roscoe Moss Co. v. Jenkins, 55 Cal. App. (2d) 369, 130 Pac. (2d) 477; Maloney Tank Mfg. Co. v. Mid-Continent Petroleum Co., 10 Cir., 49 F. (2d) 146.

Counsel for the Casualty Company stresses the statement made by plaintiff’s witness, John E. Hightower, to the effect that every contractor has his own method of doing.his work. In addition to that statement Mr. Hightower also testified in substance that in underpinning a wall with concrete piers you would not excavate the whole length of the wall but only in three or four-foot sections leaving soil between each pier; that there would never be more than three or four feet of foundation exposed at any given time; that is what the drawing means when it specifies that the underpinning shall be in four-foot blocks.

There is ample evidence in the record to warrant a finding that defendant Hunt did not perform his contract in that he failed to comply with the drawings requiring underpinning in four-foot blocks and that therefore there was a breach of his contractual obligation. The only reason for requiring under *542 pinning in four-foot blocks was to safeguard tbe west wall of tbe Bedard building.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Grosvold v. Neely
2025 MT 99 (Montana Supreme Court, 2025)
Kostelecky v. Peas in a Pod
2022 MT 195 (Montana Supreme Court, 2022)
Deschamps v. Farwest
2020 MT 2 (Montana Supreme Court, 2020)
Dewey v. Stringer
2014 MT 136 (Montana Supreme Court, 2014)
McEwen v. MCR, LLC
2012 MT 319 (Montana Supreme Court, 2012)
Town of Geraldine v. Montana Municipal Insurance Authority
2008 MT 411 (Montana Supreme Court, 2008)
Demarest v. Broadhurst
2004 MT 147 (Montana Supreme Court, 2004)
Erickson v. Croft
760 P.2d 706 (Montana Supreme Court, 1988)
Thiel v. TAURUS DRILLING LTD. 1980-II
710 P.2d 33 (Montana Supreme Court, 1985)
Thiel v. Taurus Drilling Limited 19
Montana Supreme Court, 1985
Ehrenhaft v. Malcolm Price, Inc.
483 A.2d 1192 (District of Columbia Court of Appeals, 1984)
Unruh v. Buffalo Building Co.
633 P.2d 617 (Montana Supreme Court, 1981)
Jappe v. Co-Op Supply, Inc.
600 P.2d 184 (Montana Supreme Court, 1979)
Vorndran v. Wright
367 So. 2d 1070 (District Court of Appeal of Florida, 1979)
Ferguson v. Town Pump, Inc.
580 P.2d 915 (Montana Supreme Court, 1978)
Slifer v. Wheeler & Lewis
567 P.2d 388 (Colorado Court of Appeals, 1977)
Seeney v. Dover Country Club Apartments, Inc.
318 A.2d 619 (Superior Court of Delaware, 1974)
Arthur E. West v. Morrison-Knudsen Company, Inc.
451 F.2d 493 (Ninth Circuit, 1971)
Bratton v. Slininger
460 P.2d 383 (Idaho Supreme Court, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
255 P.2d 352, 255 P.2d 252, 126 Mont. 537, 1953 Mont. LEXIS 18, Counsel Stack Legal Research, https://law.counselstack.com/opinion/garden-city-floral-co-v-hunt-mont-1953.