Grosvold v. Neely

2025 MT 99, 568 P.3d 525, 421 Mont. 537
CourtMontana Supreme Court
DecidedMay 13, 2025
DocketDA 24-0238
StatusPublished
Cited by1 cases

This text of 2025 MT 99 (Grosvold v. Neely) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grosvold v. Neely, 2025 MT 99, 568 P.3d 525, 421 Mont. 537 (Mo. 2025).

Opinion

05/13/2025

DA 24-0238 Case Number: DA 24-0238

IN THE SUPREME COURT OF THE STATE OF MONTANA

2025 MT 99

JOHN GROSVOLD, d/b/a/ GROSVOLD EXCAVATING,

Plaintiff, Counterclaim-Defendant, Appellee, and Cross-Appellant,

v.

J. BOWMAN NEELY and THE BOWMAN NEELY REVOCABLE TRUST,

Defendant, Counterclaim-Plaintiff, Appellant, and Cross-Appellee.

APPEAL FROM: District Court of the Third Judicial District, In and For the County of Anaconda-Deer Lodge, Cause No. DV 22-03 Honorable Robert J. Whelan, Presiding Judge

COUNSEL OF RECORD:

For Appellant:

J. Bowman Neely, Self-Represented, Missoula, Montana

For Appellee:

Bernard J. “Ben” Everett, J. Ben Everett, Everett Cook Law, Anaconda, Montana

Submitted on Briefs: January 8, 2025

Decided: May 13, 2025

Filed:

__________________________________________ Clerk Chief Justice Cory J. Swanson delivered the Opinion of the Court.

¶1 J. Bowman Neely, pro se, and The J. Bowman Neely Revocable Trust (Neely)

appeal the District Court’s decision not to instruct the jury on a “construction defect” claim

and a negligence claim. John Grosvold, d/b/a Grosvold Excavating (Grosvold)

cross-appeals the District Court’s January 30, 2024 Judgment on Special Verdict denying

Grosvold’s request for prejudgment interest pursuant to § 27-1-211, MCA. We affirm.

¶2 We restate the issues on appeal as follows:

Issue One: Did the District Court err in not instructing the jury on Neely’s construction defect claim?

Issue Two: Did the District Court err in not instructing the jury on Neely’s negligence claim?

Issue Three: Did the District Court err in denying Grosvold’s request for prejudgment interest?

FACTUAL AND PROCEDURAL BACKGROUND

¶3 Neely is the trustee of The J. Bowman Neely Revocable Trust (Trust), which owns

property in Anaconda-Deer Lodge County colloquially referred to as Bowman Camp. In

April 2021, Neely, acting as his own general contractor, hired Grosvold to perform

excavation work as he directed on the property. The parties entered into an oral contract

in which Neely would pay Grosvold an hourly rate for work performed in addition to costs

for materials.1 Grosvold worked on the property from April through October 2021.

1 The only other occasion we have had to address the construction defect statute had the same factual scenario: a home owner acting as both his own general contractor and attorney, and the parties operated according to an oral contract. There may be a trend here. Rafes v. McMillan, 2022 MT 13, 407 Mont. 254, 502 P.3d 674. 2 Grosvold’s work included excavating water, septic, and electric lines, repairing

foundations, building retaining walls for a residence, constructing a bridge, and grading

various parts of the property. Although Neely paid Grosvold for his work through August

23, 2021, their relationship broke down and Neely thereafter refused to pay Grosvold for

an invoice in the amount of $55,858. Neely also disputed and refused to pay other invoiced

fees from Grosvold, including for storage of several I-beams and a safe door.

¶4 On November 1, pursuant to § 70-19-427(1), MCA, Neely sent Grosvold notice of

several alleged defects for his work on the residence at Bowman Camp. Grosvold

responded to Neely’s letter, generally denying any of his work was to Neely’s residence

pursuant to the statute. Grosvold also disputed the alleged defects because he either did

not work on the items in question, they were not in fact defects, or Neely caused the alleged

defects according to his specific instructions.

¶5 On January 14, 2022, Grosvold filed a complaint against Neely for, as relevant here,

breach of contract and prejudgment interest, asserting he was owed $64,687.80. Neely

answered the complaint and counterclaimed for breach of contract, negligence, and

“construction defect” pursuant to § 70-19-427, MCA.

¶6 Grosvold filed a motion for partial summary judgment, arguing that Neely’s

construction defect claim should be dismissed as he had not done any work to a “residence”

as defined in § 70-19-426(7), MCA, nor was the Trust a “homeowner” as defined in

§ 70-19-426(6), MCA. The District Court reserved ruling on this issue until trial.

¶7 In January 2024, the parties tried the case before a jury in Anaconda-Deer Lodge

County. During the settling of jury instructions at the close of evidence, Neely requested

3 standard jury instructions on his negligence claim. Grosvold objected, asserting the case

was strictly a breach of contract case. Neely proposed that he would withdraw his

negligence jury instructions if the court allowed jury instructions on his construction defect

claim as the claims were “close enough in the concepts that if one is done the other isn’t as

necessary.” The court adjourned for the day, noting it would look at the evidence presented

as to the construction defect claim before issuing its summary judgment ruling.

¶8 The next morning, the court ruled it would not allow Neely’s construction defect

claim to go to the jury as the evidence did not substantiate “the work completed was done

to a residence.” The court also did not give Neely’s proposed instructions on negligence,

reasoning “throughout this case we have heard testimony with regards to good

workman-like manner, industry standards, but at no time was there any discussion with

regards to negligence. And I believe those instructions . . . would merely confuse the

jury. . . . [T]he parties can argue industry standards because there’s been plenty of

testimony with regards to that. Based on the evidence presented, I believe we are talking

about breach of contract for both parties.”

¶9 The jury found Neely had breached the contract and awarded Grosvold $60,512.60

in damages. The jury denied Neely’s counterclaim, finding Grosvold did not breach the

contract with Neely. The District Court entered judgment for Grosvold according to the

damages awarded by the jury and imposing costs, for a total amount of $60,869.50, and

awarded post-judgment interest pursuant to § 25-9-205, MCA. However, the court found

Grosvold was not entitled to prejudgment interest pursuant to § 27-1-211, MCA, because

4 the damages were not certain or capable of being made certain until the jury determined

them from the variety of damages claimed by Grosvold.

¶10 Neely appeals the District Court’s refusal to instruct the jury on negligence and

construction defect claims. Grosvold cross-appeals the District Court’s denial of

prejudgment interest.

STANDARD OF REVIEW

¶11 A district court’s ruling on a motion for summary judgment is reviewed de novo.

McClue v. Safeco Ins. Co., 2015 MT 222, ¶ 8, 380 Mont. 204, 354 P.3d 604. “A party has

a right to jury instructions adaptable to his or her theory of the case when the theory is

supported by credible evidence.” Camen v. Glacier Eye Clinic, P.C., 2023 MT 174, ¶ 21,

413 Mont. 277, 539 P.3d 1062. A district court’s refusal to give an offered instruction

constitutes reversable error only when such refusal affects the substantial rights of the party

proposing the instruction, thereby prejudicing him. Camen, ¶ 21; see also M. R. Civ. P.

61. We will affirm a district court’s ruling for reaching the right result, even if it reached

that result for a wrong reason. Davis v. State, 2015 MT 264, ¶ 8, 381 Mont. 59, 357 P.3d

320.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2025 MT 99, 568 P.3d 525, 421 Mont. 537, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grosvold-v-neely-mont-2025.