Exxon Mobil Corporation v. Aecom Energy & Construction, Inc.
Opinion
NOT FOR PUBLICATION FILED UNITED STATES COURT OF APPEALS JUN 30 2026 MOLLY C. DWYER, CLERK
U.S. COURT OF APPEALS
FOR THE NINTH CIRCUIT
No. 25-4597
EXXON MOBIL CORPORATION, D.C. No.
1:19-cv-00107-SPW
Plaintiff-Counterclaim
Defendant-Appellee, MEMORANDUM* v.
AECOM ENERGY & CONSTRUCTION, INC.,
Defendant-Counterclaim
Plaintiff-Appellant.
Appeal from the United States District Court for the District of Montana Susan P. Watters, District Judge, Presiding
Argued and Submitted June 10, 2026 Seattle, Washington
Before: HAWKINS, W. FLETCHER, and M. SMITH, Circuit Judges.
Exxon Mobil Corporation (“Exxon”) hired AECOM Energy & Construction (“AECOM”) to perform a significant overhaul of its oil refinery in Billings,
*
This disposition is not appropriate for publication and is not precedent except as provided by Ninth Circuit Rule 36-3.
Montana. During the course of the contract, disputes arose over delays in the project as well as the quality of AECOM’s performance; AECOM also asserted it was owed significant additional amounts for project changes made by Exxon. The dispute was eventually tried before a jury, which concluded both parties had breached some of their contractual obligations, and awarded AECOM $64 million and $20 million to Exxon. AECOM now appeals three post-trial rulings by the district court, including how to interpret the jury verdict form, the grant of judgment as a matter of law to Exxon on AECOM’s Prompt Payment Act (“PPA”) claim, and the denial of prejudgment interest. We have jurisdiction pursuant to 28 U.S.C. § 1291, and we affirm. I. Rule 50(b) Motion re PPA Claim Following the jury’s verdict, Exxon renewed its motion for judgment as a matter of law on AECOM’s PPA claim. A Rule 50(b) motion should be granted when “the evidence permits only one reasonable conclusion, and that conclusion is contrary to the jury’s verdict.” EEOC v. Go Daddy Software, Inc., 581 F.3d 951, 961 (9th Cir. 2009). We review the grant of a Rule 50(b) motion de novo, see id., and we may affirm the district court on any ground supported by the record, Charley’s Taxi Radio Dispatch Corp. v. SIDA of Haw., Inc., 810 F.2d 869, 874 (9th Cir. 1987). We conclude that the district court properly granted judgment in favor
of Exxon because there was no evidence from which a jury could have concluded Exxon violated the PPA.
In Montana, the PPA provides for the timely payment of contractors and subcontractors under construction contracts according to a default monthly billing cycle. Under the Act, an invoice is considered approved by the owner twenty-one days after a contractor submits it, unless the owner provides a written statement to the contractor disapproving the payment request and delineating the specific items of which the owner disapproves. Mont. Code Ann. § 28-2-2103(1)(b)–(c). The Act further provides that if payment “required by a construction contract . . . is delayed by more than 30 days from the date the payment is required by the contract to be made” the owner must pay interest to the contractor at the rate of 1.5% a month on the unpaid balance. Id. at § 28-2-2104. However, the Act also allows parties to adopt alternative billing processes. Id. at § 28-2-2115.
In the Purchase Order, the parties contractually agreed to a more complex scheme for progress payments which were divided into three phases and sixteen progress milestones. The procedures for milestone completion certificates and invoicing procedures were set forth in the Purchase Order and required Exxon to pay within thirty days “after receipt of a correct and complete invoice.” The Purchase Order also gave Exxon the right to set off any losses it may have incurred “against any performance or payment due to Supplier.”
There were six invoices which were considered by the jury as part of AECOM’s claim. AECOM submitted four of these invoices to Exxon on February 25, 2019. Under the Purchase Order, Exxon then had thirty days to pay after receipt of a “correct and complete invoice” or, if incomplete, to return the invoice wholly or partially unpaid.
Twenty-nine days later, Exxon informed AECOM that it would not pay these invoices because it was exercising its setoff rights under the Purchase Order and listed its reasons for setoff. Indeed, the jury ultimately determined Exxon’s damages were $20 million, well more than the sum of these invoices. With respect to the other two invoices, AECOM failed to establish the date they were actually submitted to Exxon, but Exxon rejected the invoices on March 13, 2019, and provided reasons.
The additional interest penalty in the PPA is only applicable when a party fails to pay an invoice “more than 30 days from the date the payment is required by the contract to be made.”1 The PPA “clearly recognizes an owner’s right to dispute all or part of a progress payment request for a litany of reasons . . . and requires an owner to promptly pay only the ‘approved amount.’” JEM Contracting, Inc. v. Morrison-Maierle, Inc., 318 P.3d 678, 681 (Mont. 2014); see also id. (the PPA is
1 The district court admitted it had incorrectly instructed the jury it could find a violation of the PPA if Exxon did not object to the invoices within twenty-one days. “When reviewing a motion for judgment as a matter of law, we apply the law as it should be, rather than the law as it was read to the jury.” Pincay v. Andrews, 238 F.3d 1106, 1109 n.4 (9th Cir. 2001).
not “a mandate that owners progressively pay contractors for billed amounts regardless of work quality or conformance with the contract”).
Here, the parties contracted around the default provisions of the PPA. With respect to four invoices, the evidence demonstrated that Exxon clearly exercised its setoff rights within the contractually-agreed to timeframe; with respect to the remaining two invoices, AECOM failed to establish the date they were actually submitted to Exxon, and there was therefore no evidence that Exxon’s dispute of these invoices fell outside the contractual thirty-day period. As such, there were no payments “required by a construction contract” which were delayed by more than thirty days to support a PPA violation and the increased interest penalties. Mont. Code Ann. § 28-2-2104. We therefore affirm the district court’s grant of judgment as a matter of law to Exxon on the PPA claim.2 II. Jury Verdict Following the verdict, AECOM filed a Motion for Clarification and Quantification of the Judgment, asking the court to clarify that it was entitled to $64 million plus $8,034,725 for the PPA claim, for a total of over $72 million. In light of our determination above that Exxon was entitled to judgment as a matter of law on the PPA claim, we affirm the district court’s interpretation of the jury award.
2 Because of this conclusion, we need not address the district court’s application of the law of the case doctrine with respect to the Rule 50(b) motion.
III. Prejudgment Interest We apply state law to determine if an award of prejudgment interest is appropriate. In re Exxon Valdez, 484 F.3d 1098, 1101 (9th Cir. 2007).3 Prejudgment interest is available in Montana if (1) there is an underlying monetary obligation, (2) the amount of recovery is capable of being made certain, and (3) the right to recover must vest on a particular day. Mont. Petroleum Tank Release Comp. Bd. v. Crumleys, Inc., 174 P.3d 948, 965 (Mont. 2008). Prejudgment interest is inappropriate when the amount of a party’s damages is uncertain or disputed. Id.
Free access — add to your briefcase to read the full text and ask questions with AI
Exxon Mobil Corporation v. Aecom Energy & Construction, Inc. (Exxon Mobil Corporation v. Aecom Energy & Construction, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.