Exxon Mobil Corporation v. Aecom Energy & Construction, Inc.

CourtCourt of Appeals for the Ninth Circuit
DecidedJune 30, 2026
Docket25-4597
StatusUnpublished

This text of Exxon Mobil Corporation v. Aecom Energy & Construction, Inc. (Exxon Mobil Corporation v. Aecom Energy & Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Exxon Mobil Corporation v. Aecom Energy & Construction, Inc., (9th Cir. 2026).

Opinion

NOT FOR PUBLICATION FILED UNITED STATES COURT OF APPEALS JUN 30 2026 MOLLY C. DWYER, CLERK U.S. COURT OF APPEALS FOR THE NINTH CIRCUIT

No. 25-4597 EXXON MOBIL CORPORATION, D.C. No. 1:19-cv-00107-SPW Plaintiff-Counterclaim Defendant-Appellee, MEMORANDUM* v.

AECOM ENERGY & CONSTRUCTION, INC.,

Defendant-Counterclaim Plaintiff-Appellant.

Appeal from the United States District Court for the District of Montana Susan P. Watters, District Judge, Presiding

Argued and Submitted June 10, 2026 Seattle, Washington

Before: HAWKINS, W. FLETCHER, and M. SMITH, Circuit Judges.

Exxon Mobil Corporation (“Exxon”) hired AECOM Energy & Construction

(“AECOM”) to perform a significant overhaul of its oil refinery in Billings,

* This disposition is not appropriate for publication and is not precedent except as provided by Ninth Circuit Rule 36-3. Montana. During the course of the contract, disputes arose over delays in the project

as well as the quality of AECOM’s performance; AECOM also asserted it was owed

significant additional amounts for project changes made by Exxon. The dispute was

eventually tried before a jury, which concluded both parties had breached some of

their contractual obligations, and awarded AECOM $64 million and $20 million to

Exxon. AECOM now appeals three post-trial rulings by the district court, including

how to interpret the jury verdict form, the grant of judgment as a matter of law to

Exxon on AECOM’s Prompt Payment Act (“PPA”) claim, and the denial of

prejudgment interest. We have jurisdiction pursuant to 28 U.S.C. § 1291, and we

affirm.

I. Rule 50(b) Motion re PPA Claim

Following the jury’s verdict, Exxon renewed its motion for judgment as a

matter of law on AECOM’s PPA claim. A Rule 50(b) motion should be granted

when “the evidence permits only one reasonable conclusion, and that conclusion is

contrary to the jury’s verdict.” EEOC v. Go Daddy Software, Inc., 581 F.3d 951,

961 (9th Cir. 2009). We review the grant of a Rule 50(b) motion de novo, see id.,

and we may affirm the district court on any ground supported by the record,

Charley’s Taxi Radio Dispatch Corp. v. SIDA of Haw., Inc., 810 F.2d 869, 874 (9th

Cir. 1987). We conclude that the district court properly granted judgment in favor

2 25-4597 of Exxon because there was no evidence from which a jury could have concluded

Exxon violated the PPA.

In Montana, the PPA provides for the timely payment of contractors and

subcontractors under construction contracts according to a default monthly billing

cycle. Under the Act, an invoice is considered approved by the owner twenty-one

days after a contractor submits it, unless the owner provides a written statement to

the contractor disapproving the payment request and delineating the specific items

of which the owner disapproves. Mont. Code Ann. § 28-2-2103(1)(b)–(c). The Act

further provides that if payment “required by a construction contract . . . is delayed

by more than 30 days from the date the payment is required by the contract to be

made” the owner must pay interest to the contractor at the rate of 1.5% a month on

the unpaid balance. Id. at § 28-2-2104. However, the Act also allows parties to

adopt alternative billing processes. Id. at § 28-2-2115.

In the Purchase Order, the parties contractually agreed to a more complex

scheme for progress payments which were divided into three phases and sixteen

progress milestones. The procedures for milestone completion certificates and

invoicing procedures were set forth in the Purchase Order and required Exxon to pay

within thirty days “after receipt of a correct and complete invoice.” The Purchase

Order also gave Exxon the right to set off any losses it may have incurred “against

any performance or payment due to Supplier.”

3 25-4597 There were six invoices which were considered by the jury as part of

AECOM’s claim. AECOM submitted four of these invoices to Exxon on February

25, 2019. Under the Purchase Order, Exxon then had thirty days to pay after receipt

of a “correct and complete invoice” or, if incomplete, to return the invoice wholly

or partially unpaid.

Twenty-nine days later, Exxon informed AECOM that it would not pay these

invoices because it was exercising its setoff rights under the Purchase Order and

listed its reasons for setoff. Indeed, the jury ultimately determined Exxon’s damages

were $20 million, well more than the sum of these invoices. With respect to the

other two invoices, AECOM failed to establish the date they were actually submitted

to Exxon, but Exxon rejected the invoices on March 13, 2019, and provided reasons.

The additional interest penalty in the PPA is only applicable when a party fails

to pay an invoice “more than 30 days from the date the payment is required by the

contract to be made.”1 The PPA “clearly recognizes an owner’s right to dispute all

or part of a progress payment request for a litany of reasons . . . and requires an

owner to promptly pay only the ‘approved amount.’” JEM Contracting, Inc. v.

Morrison-Maierle, Inc., 318 P.3d 678, 681 (Mont. 2014); see also id. (the PPA is

1 The district court admitted it had incorrectly instructed the jury it could find a violation of the PPA if Exxon did not object to the invoices within twenty-one days. “When reviewing a motion for judgment as a matter of law, we apply the law as it should be, rather than the law as it was read to the jury.” Pincay v. Andrews, 238 F.3d 1106, 1109 n.4 (9th Cir. 2001).

4 25-4597 not “a mandate that owners progressively pay contractors for billed amounts

regardless of work quality or conformance with the contract”).

Here, the parties contracted around the default provisions of the PPA. With

respect to four invoices, the evidence demonstrated that Exxon clearly exercised its

setoff rights within the contractually-agreed to timeframe; with respect to the

remaining two invoices, AECOM failed to establish the date they were actually

submitted to Exxon, and there was therefore no evidence that Exxon’s dispute of

these invoices fell outside the contractual thirty-day period. As such, there were no

payments “required by a construction contract” which were delayed by more than

thirty days to support a PPA violation and the increased interest penalties. Mont.

Code Ann. § 28-2-2104. We therefore affirm the district court’s grant of judgment

as a matter of law to Exxon on the PPA claim.2

II. Jury Verdict

Following the verdict, AECOM filed a Motion for Clarification and

Quantification of the Judgment, asking the court to clarify that it was entitled to $64

million plus $8,034,725 for the PPA claim, for a total of over $72 million. In light

of our determination above that Exxon was entitled to judgment as a matter of law

on the PPA claim, we affirm the district court’s interpretation of the jury award.

2 Because of this conclusion, we need not address the district court’s application of the law of the case doctrine with respect to the Rule 50(b) motion.

5 25-4597 III. Prejudgment Interest

We apply state law to determine if an award of prejudgment interest is

appropriate.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Exxon Mobil Corporation v. Aecom Energy & Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/exxon-mobil-corporation-v-aecom-energy-construction-inc-ca9-2026.