Ryffel Family Partnership Ltd. v. Alpine Country Construction, Inc.

2016 MT 350, 386 P.3d 971, 386 Mont. 165, 2016 Mont. LEXIS 1112
CourtMontana Supreme Court
DecidedDecember 28, 2016
DocketDA 15-0805
StatusPublished
Cited by8 cases

This text of 2016 MT 350 (Ryffel Family Partnership Ltd. v. Alpine Country Construction, Inc.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ryffel Family Partnership Ltd. v. Alpine Country Construction, Inc., 2016 MT 350, 386 P.3d 971, 386 Mont. 165, 2016 Mont. LEXIS 1112 (Mo. 2016).

Opinion

JUSTICE McKINNON

delivered the Opinion of the Court.

¶1 Plaintiff and Appellant Ryffel Family Partnership, Ltd. (Ryffel Partnership) appeals from a jury verdict entered in the Eighteenth Judicial District Court, Gallatin County. The jury found that Ryffel Partnership had breached two oral contracts with the Appellee Alpine Construction (Alpine), but awarded zero damages. The first agreement was entered into in January of 2007 and the second agreement was entered into in September of 2007. Although awarding zero damages for Ryffel Partnership’s breach, the jury found Ryffel Partnership was unjustly enriched by Alpine’s labor and awarded Alpine $50,348.18 in damages. Finally, the jury awarded $25,000 to Alpine for Ryffel Partnership’s breach of the covenant of good faith and fair dealing.

¶2 The District Court issued an order pursuant to M. R. Civ. P. 59, amending the judgment to assign the jury’s damages award for unjust enrichment to its finding that Ryffel Partnership breached its contract. The District Court did so upon the basis that breach of contract and unjust enrichment are inconsistent legal theories of recovery. The District Court’s order also struck the jury’s award of $25,000 for breach of the covenant of good faith and fair dealing, concluding no evidence in the record supported the award. Alpine filed a motion to amend the judgment for pre-judgment interest pursuant to § 27-1-211, MCA, which the District Court denied by allowing the motion to expire. In its appeal, Ryffel Partnership seeks anew trial, alleging the jury’s verdict *167 was inconsistent and that there was not substantial evidence to support breach of the second agreement entered into in September of 2007. Ryffel Partnership does not raise any issue regarding the first agreement entered into in January of2007, which the jury found it had also breached. Alpine cross-appeals the District Court’s denial of prejudgment interest. We affirm the District Court’s ruling, including its denial of pre-judgment interest, and deny Ryffel Partnership’s appeal to review the verdict for lack of substantial evidence. We restate the issues on appeal as follows:

1. Whether the jury’s verdict regarding the parties’ second agreement was supported by substantial evidence.
2. Whether the District Court erred in denying Ryffel Partnership’s motion for a new trial based on an inconsistent or illegal jury verdict.
3. Whether the District Court erred in denying Alpine’s motion for pre-judgment interest pursuant to § 27-1-211, MCA.

FACTUAL AND PROCEDURAL BACKGROUND

¶3 Although James Ryffel (Ryffel) was born in Bozeman, Montana, Ryffel Partnership is a Texas-based partnership consisting of Ryffel, his wife, and a family trust as partners. Ryffel often travels to Montana and purchased the property at issue because of its scenic nature and beauty, along with its suitability as a location for a family home. Part of the property’s appeal to Ryffel and his wife were the statuesque “specimen trees” and the “hilly knoll” upon which many of these trees were located.

¶4 Ryffel and his wife wanted to build a home on the property that would, among other things, look upon the beauty of the knoll and its trees. To implement that vision, Ryffel hired Steve Hanson (Hanson) as a general contractor to oversee the building and logging work the project would require. Hanson is an experienced builder of custom log homes. Ryffel’s testimony reflects that, overall, he wanted to cut only the trees necessary to build a road on the property to the home, the trees to build the home itself, thin those trees that then remained on the property, clear those trees that were dead and fallen, and then preserve specimen trees greater than 24 inches in diameter. To those ends, some trees were specially marked for use as house logs in the upcoming construction of the Ryffel Partnership residence on the property.

¶5 Bob Rammers (Rammers) is one of the owners of Alpine Construction. Seeking the potentially substantial logging business on the Ryffel Partnership property, Rammers met Hanson through a *168 mutual acquaintance, Scott Cooper (Cooper). Cooper, Rammers, and Hanson all gathered on the Ryffel Partnership property in January of 2007, and discussed the job. Hanson hired Alpine for logging work on the property: logs were to be delivered to the upper landing where the house would be built, and the thinning would have to be done within parameters, i.e. no specimen trees greater than 24 inches would be cut. Hanson hired Alpine in January of 2007. He showed Rammers where the house logs were and where they should be placed for use in construction.

¶6 Although Hanson could not remember if Rammers gave him a rate sheet for the work, Cooper and Rammers both testified that the terms of the agreement were for Alpine to be paid by the hour. Rammers believed that an hourly rate was the only acceptable payment method under the circumstances because all of the “good logs” were to be used for the Ryffel Partnership house construction, while all of the “butts, tips, and crooked logs” were to go to the mill. However, Rammers contended that it was impossible for him to determine beforehand what should stay on the property, and what should go to the mill, making it difficult to estimate the labor on a lump sum basis. Rammers testified that payments from what he took to the mill were to be offset against Alpine’s costs, and that Alpine would charge a flat fee for delivering each load to the mill. Rammers also testified that Hanson never mentioned the specimen tree restrictions.

¶7 Hanson explained that Alpine performed side jobs as well. According to Hanson, Alpine hauled materials and equipment, and cleared snow and ice from the property’s road to ensure timely deliveries of material and the safe traversal of workers constructing the house. Alpine also cleared trees along the road, and hauled logs that would later serve as trusses for the home. Alpine’s work on the road was frequent, as the road was cleared of materials every time someone needed to travel upon it—at least once or twice per day. Alpine also backfilled around the house’s foundation.

¶8 Alpine sent an invoice dated February 4, 2007, to Ryffel and Hanson for road work. The invoice billed an hourly rate, which Ryffel and Hanson testified was acceptable, because the road work was considered “side work.” Alpine sent another invoice for hourly work on March 1, 2007, for building a de-barker. Ryffel testified that this too was considered side work. Ryffel stated that he received several such invoices, dated between May and September, 2007, for hourly labor and equipment.

¶9 Ryffel questioned the fairness of one of those invoices for $97,000 and so asked Rammers to meet to discuss it. This meeting would form *169 the basis of the parties’ second agreement. At that meeting in September 2007, Rammers and Ryffel discussed the invoices accrued so far, and attempted to concur on the terms of their agreement going forward. Ryffel was concerned in part, because there was no set agreement between Ryffel Partnership and Alpine concerning a rate for the logging work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marriage of: Kahl & Sperano
2025 MT 141N (Montana Supreme Court, 2025)
Grosvold v. Neely
2025 MT 99 (Montana Supreme Court, 2025)
Kalispell Aircraft Co. v. Patterson
2019 MT 142 (Montana Supreme Court, 2019)
Carlson v. Yellowstone County Board of Adjustment
2017 MT 186 (Montana Supreme Court, 2017)
Bank of America, N.A. v. Alexander
2017 MT 31 (Montana Supreme Court, 2017)
Duram v. Ploeger
2017 MT 17N (Montana Supreme Court, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
2016 MT 350, 386 P.3d 971, 386 Mont. 165, 2016 Mont. LEXIS 1112, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ryffel-family-partnership-ltd-v-alpine-country-construction-inc-mont-2016.