James Talcott Construction, Inc. v. P&D Land Enterprises

2006 MT 188, 141 P.3d 1200, 333 Mont. 107, 2006 Mont. LEXIS 381
Montana Supreme Court·Decided August 15, 2006·No. 05-103·Published·Cited by 29 cases

Opinion

JUSTICE COTTER

delivered the Opinion of the Court.

¶1 Plaintiff James Talcott Construction (Talcott) and Defendant P&D Land Enterprises (P&D) entered into a contract under which Talcott would construct condominiums on Whitefish Lake in Whitefish, Montana. Problems, delays and disputes arose leading Talcott to sue P&D in the Eleventh Judicial District Court seeking to foreclose on a construction lien and for certain costs. P&D counterclaimed for breach of contract. The District Court appointed a special master to hear the case. The District Court subsequently adopted, with some modifications, the Special Master’s findings of fact and conclusions of law. Talcott appeals. We affirm in part and reverse and remand in part.

¶2 This Court issued its original Opinion in this case on June 27, 2006. Talcott filed a Petition for Rehearing on July 10,2006. P&D filed its Objection to the Petition for Rehearing on July 18, 2006. In its Petition, Talcott correctly argued that this Court erroneously concluded that it was not entitled to post-judgment interest on certain discreetly identifiable amounts sought by Talcott but denied by the District Court. On August 1, 2006, we issued an Order withdrawing our June 27, 2006, Opinion. We replace it with this superseding Opinion.

ISSUES

¶3 A restatement of the issues presented on appeal is:

¶4 Did the District Court err in concluding that Talcott was contractually obligated to perform punch list and warranty work, and in awarding the cost of that work to P&D?

*110 ¶5 Did the District Court err in refusing to approve prejudgment interest on the amount Talcott is entitled to recover under its construction lien?

¶6 Did the District Court err in refusing to award Talcott overhead costs which it claimed resulted from P&D-responsible delays?

¶7 Did the District Court err in its award of fees to Talcott?

FACTUAL AND PROCEDURAL BACKGROUND

¶8 P&D Enterprises is a joint venture consisting of two Montana corporations and a California corporation, all of which also are individual defendants in this case. P&D, as owner of real property located in Whitefish, Montana, entered into a $1.3 million contract with Talcott in 1991, under which Talcott was to construct fifteen condominium units designated as Whitefish Condominiums-Phase II. Talcott furnished a performance bond for $1.3 million and agreed to a one-year warranty period following substantial completion of the project, which contractually was scheduled for February 1, 1992. Under the terms of the contract, Talcott was to be paid a “bonus” of $17,500.00 for on-time completion of the project. However, if completion was not achieved by February 1, Talcott would be penalized $30.00 per day per unit until a Certificate of Occupancy was issued.

¶9 The contract also contained the following relevant provisions:

A. Talcott would submit its monthly “application for payment” to P&D’s Architect by the fifth of each month for work and supplies furnished the previous month;
B. P&D’s Architect would approve Talcott’s bill and certify the amount to be paid;
C. P&D agreed to pay the certified amount by the 25th day of the same month;
D. if P&D failed to pay, Talcott could provide seven written days notice after which it could stop work until payment was received;
E. interest was to be paid by P&D from the date payments were due to Talcott; and
F. costs caused by delays were to be borne by the party responsible for the delays.

¶10 Fourteen of the fifteen units were not completed by February 1, 1992; these units had Certificates of Occupancy issued on April 24, May 1, 6, 8 and 14. It is undisputed that the “completion” dates for these 14 units had been extended from February 1 to various dates between April 6 and May 1. On June 1, Talcott submitted its application for payment in the amount of $106,748.55 for work and materials furnished through May, 1992. Of this amount, P&D’s *111 Architect certified $83,141.50 for payment. However, from the certified amount, P&D then withheld the following sums: 1) $38,640.00 as penalty for Talcott’s failure to complete the units by February 1; 2) $15,000.00 as the claimed cost of repainting the Phase II units (P&D alleged that Talcott had painted the Phase II units a different color from the Phase I condo units.); 3) $10,000.00 representing P&D’s estimated cost for one year of warranty work, on the ground that it suspected Talcott would not return to perform this work and it would be required to hire someone else to do it; and 4) approximately $7,251.00, representing the difference in the cost of floor and tile work and materials actually used versus the cost of this work and materials as included in the original contract. The total amount withheld from Talcott’s certified June bill was $70,891.00.

¶11 As a result of P&D’s refusal to pay Talcott’s certified bill, Talcott notified P&D by written notice on June 26 that it would stop work on July 3, 1992. As a consequence of Talcott leaving the job, P&D proceeded to perform the various unfinished tasks required to finish construction of the units, i.e., the “punch list” of undone tasks, as well as other work which P&D considered covered by the one year warranty. This work cost P&D $12,807.33.

¶12 On July 15,1992, Talcott filed a construction hen on the property for $143,912.81. In August, P&D made a partial payment to Talcott of approximately $51,692.00, which Talcott applied first to interest owing, then to the unpaid principal balance. In September 1992, P&D made another partial payment of approximately $11,515.00 that Talcott similarly applied. In October 1992, Talcott filed an action in the District Court to foreclose the lien and recover the costs of extended overhead. The construction lien has since attached to the real property. After Talcott filed its complaint, P&D filed a counterclaim asserting that Talcott breached the original contract by failing to complete the warranty work and the “punch list.” Finally, after the complaint was filed, P&D paid Talcott the additional sum of $9,356.67. In August 1994, the District Court appointed a special master to hear the case.

¶13 Talcott argued that P&D owed it substantial sums in principal and interest based on P&D’s refusal to pay Talcott’s bill. Talcott asserted that it should not have been penalized for failing to complete the units by February 1,1992, as required by the contract, because the delays were caused by P&D. Talcott maintained that P&D made numerous additions, deletions and revisions to the work in progress which resulted in time delays and added costs for which Talcott should be paid. Moreover, Talcott claimed that P&D had extended completion dates for several units but then wrongfully reverted to the original *112 completion date of February 1 when it calculated penalties.

Free access — add to your briefcase to read the full text and ask questions with AI

James Talcott Construction, Inc. v. P&D Land Enterprises, 2006 MT 188, 141 P.3d 1200, 333 Mont. 107, 2006 Mont. LEXIS 381 (Mo. 2006).

2006 MT 188 (James Talcott Construction, Inc. v. P&D Land Enterprises) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Okragly v. Keitel
Montana Supreme Court, 2026
Waddell v. Studer
2025 MT 269 (Montana Supreme Court, 2025)
Sloway Cabin v. Extreme
2025 MT 161 (Montana Supreme Court, 2025)
Masters Group v. Comerica Bank
2021 MT 161 (Montana Supreme Court, 2021)
Peters v. Hubbard
2020 MT 282 (Montana Supreme Court, 2020)
Gendron v. Montana University System
2020 MT 82 (Montana Supreme Court, 2020)
Odom v. Bank of N.Y. Mellon
2020 MT 58N (Montana Supreme Court, 2020)
Kenyon-Noble Lumber Co. v. Dependant Foundations, Inc.
2018 MT 308 (Montana Supreme Court, 2018)
Mandell v. Bayliss
2016 MT 205 (Montana Supreme Court, 2016)
Stafford v. Fockaert
2016 MT 28 (Montana Supreme Court, 2016)
Overfield v. Great Falls
2013 MT 67N (Montana Supreme Court, 2013)
DeVOE v. City of Missoula
2012 MT 72 (Montana Supreme Court, 2012)
DiMarzio v. CRAZY MOUNTAIN CONST., INC.
2010 MT 231 (Montana Supreme Court, 2010)
Dimarzio v. Crazy Mountain Construction, Inc.
2010 MT 231 (Montana Supreme Court, 2010)
JTL Group, Inc. v. New Outlook, LLP
2010 MT 1 (Montana Supreme Court, 2010)
Textana, Inc. v. Klabzuba Oil & Gas
2009 MT 401 (Montana Supreme Court, 2009)
Textana v. Klabzuba
2009 MT 401 (Montana Supreme Court, 2009)