Rossi v. Pawiroredjo

2004 MT 39, 85 P.3d 776, 320 Mont. 63, 2004 Mont. LEXIS 45
CourtMontana Supreme Court
DecidedFebruary 24, 2004
Docket02-562
StatusPublished
Cited by17 cases

This text of 2004 MT 39 (Rossi v. Pawiroredjo) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rossi v. Pawiroredjo, 2004 MT 39, 85 P.3d 776, 320 Mont. 63, 2004 Mont. LEXIS 45 (Mo. 2004).

Opinion

JUSTICE RICE

delivered the Opinion of the Court.

¶1 John and Cheryl Rossi (collectively, Rossis) brought this action to set aside a construction lien filed against their property by Defendant, Kai Pawiroredjo (Kai), and for damages for Kai’s defective workmanship. Kai counterclaimed to foreclose the construction lien. The Thirteenth Judicial District Court, Yellowstone County, entered judgment in favor of Kai and awarded him attorney fees. Rossis appeal. We affirm in part, vacate the award of attorney fees, and remand for further proceedings.

¶2 The Rossis raise the following issues on appeal:

¶3 1. Did the District Court err in finding the construction lien was timely filed?

¶4 2. Did the District Court err in failing to consider damages from defective workmanship?

¶5 3. Did the District Court err in awarding attorney fees without a hearing?

FACTUAL AND PROCEDURAL BACKGROUND

¶6 In January 2001, the Rossis hired Kai to do remodeling work in their Billings, Montana, home, which was in deteriorating condition. Over the course of the next several months, Kai completely remodeled the Rossis’ kitchen and bathroom, and worked on the living, dining, and sun room areas.

¶7 The parties disputed the terms of their remodeling agreement at trial, which was not in writing. According to the Rossis, they agreed to purchase the bulk of materials and pay Kai a total of $5,000 for the entire remodeling project. Kai, on the other hand, maintained that the parties entered separate oral agreements for the remodeling of the kitchen, bathroom, and remaining areas, under which he was entitled *65 to receive a total of $11,390 for his labor and materials.

¶8 However, by the end of March 2001, Kai had only received $3,800 from the Rossis. As a result, Kai ceased working on the Rossis’ residence on April 6,2001. After receiving some payment, Kai returned to the Rossis’ residence on June 11, 2001, to attempt to remove stains from the sun room’s tile floor, which he had previously installed, and which had become stained as a result of not being properly sealed during installation.

¶9 On June 25, 2001, the Rossis made their final payment to Kai, bringing their total payments to $5,000. On September 7, 2001, Kai filed a construction lien against the Rossis’ property, asserting a balance due and owing of $6,390, plus interest at 10 percent per annum. The Rossis thereafter brought suit to set aside the construction lien, asserting that $5,000 was the agreed upon contract price and that the construction lien was ineffective as it was untimely filed. The Rossis additionally sought damages for defective workmanship, primarily on the basis that the sun room tile floor became stained as a result of not being properly sealed during installation. Kai denied the allegations of defective workmanship and counterclaimed to foreclose on the construction lien.

¶10 A non-jury trial was held on April 24,2002. The following day, the District Court submitted its Findings of Fact and Conclusions of Law, ruling in favor of Kai as to the value of the work performed, the validity of the lien, foreclosure of the lien, and awarding Kai attorney fees and costs. In particular, the District Court found that the quality of Kai’s work was far above average, that he had performed according to the terms of the parties’ oral agreements, and that the Rossis had instructed him not to seal the tile floor in the sun room as they wished to do so themselves. The court additionally noted that the Rossis sought to remodel and repair their home in the cheapest manner possible, and had hired Kai knowing that he was not a licensed contractor.

¶11 On May 16, 2002, pursuant to the court’s award of attorney fees, Kai’s counsel submitted a memorandum of fees and costs, and the Rossis objected. On June 6, 2002, in the absence of an evidentiary hearing, the District Court issued an order awarding Kai $7,166.40 in attorney fees and $283.94 in costs. From this Order and the District Court’s Findings of Fact and Conclusions of Law, the Rossis appeal.

STANDARD OF REVIEW

¶12 We review a district court’s findings of fact to determine if they *66 are clearly erroneous. Burns v. A Cash Construction Lien Bond, 2000 MT 233, ¶ 6, 301 Mont. 304, ¶ 6, 8 P.3d 795, ¶ 6. A district court’s findings are clearly erroneous if they are not supported by substantial credible evidence, if the district court has misapprehended the effect of the evidence, or if a review of the record leaves this Court with a definite and firm conviction that a mistake has been made. Tungsten Holdings, Inc. v. Olson, 2002 MT 158, ¶ 13, 310 Mont. 374, ¶ 13, 50 P.3d 1086, ¶ 13. Substantial evidence is “evidence that a reasonable mind might accept as adequate to support a conclusion; it consists of more than a mere scintilla of evidence but may be somewhat less than a preponderance.” Barrett v. Asarco, Inc. (1990), 245 Mont. 196, 200, 799 P.2d 1078, 1080.

¶13 Finally, we review a district court’s conclusions of law de novo to determine whether they are correct. Burns, ¶ 6.

DISCUSSION

¶14 Did the District Court err in finding the construction lien was timely filed?

¶15 Kai initially ceased working on the Rossis’ residence on April 6, 2001. On June 11,2001, Kai returned to the residence accompanied by an agent from Home Depot to attempt cleaning of the sun room’s tile floor, which had become stained after installation. However, after approximately forty-five minutes of scrubbing the tile with a brush, water, and cleaning agents, Kai concluded the stains could not be removed. At trial, the parties generally agreed that the cleaning attempt was unsuccessful.

¶16 On September 7,2001, 88 days later, Kai filed a construction lien against the Rossis’ residence, asserting a balance due and owing of $6,390, plus interest. The District Court concluded the lien was timely because Kai had worked on the property within the previous 90 days by virtue of his work on June 11,2001, which it concluded was done for the sole purpose of enhancing the property’s value, and not in an effort to extend the time period for filing a construction lien.

¶17 On appeal, the Rossis contend the District Court erred in finding the lien was timely filed. They maintain that in order to extend the time period for filing a construction lien, the work performed must have rendered a tangible improvement to the property. Since the parties agree that the June 11, 2001 cleaning attempt was unsuccessful, the Rossis argue that this work did not constitute a tangible improvement, and thus, did not extend the lien filing period. They contend the last date of actual work performed occurred on April *67 6, 2001, and that, therefore, the September 7, 2001 filing was untimely, and the lien is invalid.

¶18 Section 71-3-535, MCA (2000), controls the attachment of a construction lien and provides in pertinent part:

Attachment of lien-filing. (1) A person’s lien does not attach and may not be enforced unless,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thomas Mann Post v. Knudsen Family
2022 MT 150 (Montana Supreme Court, 2022)
Adams v. Roberts
D. Montana, 2021
Dick Anderson Construction, Inc. v. Monroe Construction Co.
2009 MT 416 (Montana Supreme Court, 2009)
Sudan Drilling, Inc. v. Anacker
2009 MT 14 (Montana Supreme Court, 2009)
Bitterroot River Prot. Ass'n Inc. v. Bitterroot Cons. Dist.
2008 MT 377 (Montana Supreme Court, 2008)
Rothing v. Kallestad
2007 MT 109 (Montana Supreme Court, 2007)
Johnston v. Palmer
2007 MT 99 (Montana Supreme Court, 2007)
Pumphrey v. Empire Lath & Plaster
2006 MT 255 (Montana Supreme Court, 2006)
James Talcott Construction, Inc. v. P&D Land Enterprises
2006 MT 188 (Montana Supreme Court, 2006)
Chase v. Bearpaw Ranch Ass'n
2006 MT 67 (Montana Supreme Court, 2006)
James R. v. Associates Financial Services Co.
2004 MT 397 (Montana Supreme Court, 2004)
In Re MW
2004 MT 301 (Montana Supreme Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
2004 MT 39, 85 P.3d 776, 320 Mont. 63, 2004 Mont. LEXIS 45, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rossi-v-pawiroredjo-mont-2004.