Frank L. Pirtz Construction, Inc. v. Hardin Town Pump, Inc.

692 P.2d 460, 214 Mont. 131, 1984 Mont. LEXIS 1125
CourtMontana Supreme Court
DecidedDecember 13, 1984
Docket84-198
StatusPublished
Cited by12 cases

This text of 692 P.2d 460 (Frank L. Pirtz Construction, Inc. v. Hardin Town Pump, Inc.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Frank L. Pirtz Construction, Inc. v. Hardin Town Pump, Inc., 692 P.2d 460, 214 Mont. 131, 1984 Mont. LEXIS 1125 (Mo. 1984).

Opinion

MR. JUSTICE SHEEHY

delivered the Opinion of the Court.

This is an appeal by Hardin Town Pump from a judgment and award of the Sixteenth Judicial District, Rosebud County. The judgment resulted from an action by Pirtz Construction, Inc., to recover the reasonable value of labor, materials and supplies furnished for a construction project. Pirtz cross-appeals its interest award. The judgment and award of the District Court are affirmed in all respects.

This case involves an oral contract. On July 9, 1981, Pirtz Construction, Inc. filed a mechanic’s lien on a residence in Colstrip, Montana owned by Hardin Town Pump. On October 8, 1981, Pirtz filed an action to recover $62,539 from Hardin Town Pump for work done on the residence and $5,991 for remodeling a gas station. Pirtz also sought 10% per annum interest and attorney’s fees. The District Court awarded Pirtz Construction, Inc. $63,310 under the construction contract, $11,111 interest computed at 6% from April 20, 1981, and $21,103 attorney’s fees. The court also granted Pirtz Construction, Inc. a lien for the total of $95,524.

Hardin Town Pump raises the following issues:

1. Are the findings supported by substantial evidence?

2. Is the award of damages reasonable?

3. Is the award of attorney’s fees correct?

4. Is a contingency fee agreement an appropriate measure of reasonable attorney’s fees?

5. Should Hardin Town Pump recover the costs of correcting construction defects?

6. Should the case be remanded based on errors in the transcript?

Pirtz’s cross-appeal raises one issue — should interest be calculated on the amount it paid on its operating loans rather *135 than 6% from the date work was last performed?

The parties stipulated the following facts:

1. Pirtz and Hardin Town Pump are both lawfully incorporated under Montana Law.

2. Pirtz provided labor, material and supplies to relocate a pre-fab home for Hardin Town Pump from one location in Colstrip to a new location three to four blocks away.

3. The total amount for the project was $79,384 of which Hardin Town Pump paid $16,074.

4. In November 1980, Hardin Town Pump took possession of the pre-fab.

5. On July 9, 1981, Pirtz filed a lien on the pre-fab. Hardin Town Pump never filed a notice of completion.

At issue here are the terms of an oral contract. The District Court in a non-jury trial adopted Pirtz’s version of the terms and, with the evidence in the record, we will not overturn the lower court’s findings. In reviewing the record to resolve the issues raised on appeal, we are governed by well established principles. In a nonjury trial, the credibility of witnesses and the weight of their testimony are matters for the District Court to determine. The sufficiency of the evidence must be reviewed from the perspective most favorable to the prevailing party. The District Court’s findings and judgment are presumed correct and will not be overturned unless the appellant meets the burden of proving with a preponderance of evidence that they are wrong. Merely showing the evidence establishes reasonable grounds for reaching a different conclusion is insufficient to reverse the District Court findings. Lumby v. Doetch (1979), 183 Mont. 427, 431, 600 P.2d 200, 202.

The parties disagree about the terms of the oral contract to move and remodel the pre-fab home. The parties previously had made a written contract to remodel a store. That contract was on a cost plus basis with an “upset price,” or cap, placing a maximum on what Pirtz could charge. The District Court did not determine the terms of that contract because the mechanic’s lien filed did not cover that work. *136 Both parties stated the agreed price for the pre-fab was cost plus 15% for in-house work or 10% of work subcontracted, but Hardin Town Pump claimed there was a ceiling of $25,000 to $30,000 with additional work to be performed only upon the general manager’s approval. Pirtz claimed the agreement to move the pre-fab was on a cost plus basis with no ceiling.

Hardin Town Pump contended that in June 1980, their general manager contacted Pirtz’s agent about moving a pre-fab home. The general manager testified that Hardin Town Pump believed the pre-fab home could be moved, a foundation built, a bedroom added, a deck built and a double garage built for $25,000 to $30,000. Hardin Town Pump’s agent testified that an employee of Pirtz quoted that price. Pirtz denied that the price was quoted for all the work.

Pirtz contended, and the lower court agreed, that when the work for the written contract concerning the store was nearly completed Hardin Town Pump’s general manager asked Pirtz how much it would cost to move a pre-fab house and make it liveable; the answer was it would have to be done on a cost plus basis at around $25,000 to $30,000. Hardin Town Pump told Pirtz to begin and later ordered additional work — a deck, finished basement and attached garage.

Pirtz completed the basement and billed Hardin Town Pump $16,074 prior to moving the house. Hardin Town Pump paid the bill. Hardin Town Pump’s general manager, Ron Roos, testified that before paying the bill he inspected the worksite and saw the house on the foundation, a bedroom built and a deck started. Roos testified he paid the bill believing $16,074 represented 80% of the work.

On cross-examination and rebuttal counsel for Pirtz effectively challenged Roos’ credibility. Roos testified he considered the work 80% complete when he viewed the worksite on August 10th or 11th but Pirtz introduced evidence establishing this was impossible because the house was not *137 moved until September 4th. (dated invoices establish the date). Evidence was also introduced establishing that the price for work in Colstrip is relatively high. An expert witness testified that the price Pirtz charged for its work was reasonable.

ISSUE NO. 1. Is the judgment supported by substantial evidence?

“. . . ‘Substantial evidence’ is evidence such ‘as will convince reasonable men . . .’ (Citing cases) The evidence may be inherently weak and still be deemed ‘substantial’ and substantial evidence may conflict with other evidence presented. (Citing cases)” Cameron v. Cameron (1978), 179 Mont. 219, 228, 587 P.2d 939, 944, 945.

There was testimony from the parties’ agents that the agreement was for work on a cost plus basis. The $25,000 to $30,000 figure was an original estimate when Hardin Town Pump was only requesting that the house be moved and placed on a 24 by 48 foot foundation. There was testimony regarding Pirtz’s loss on the store contract and its reluctance thereafter to enter into a contract with an “upset price.” There was testimony and exhibits showing that Hardin Town Pump requested additional work and knew it was being performed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Asbestos Litigation Cases
Montana Supreme Court, 2021
Hidden Hollow Ranch v. Fields
2004 MT 153 (Montana Supreme Court, 2004)
Rossi v. Pawiroredjo
2004 MT 39 (Montana Supreme Court, 2004)
American Simmental Ass'n v. Coregis Insurance
234 F. Supp. 2d 1028 (D. Nebraska, 2002)
In Re the Marriage of Debuff
2002 MT 159 (Montana Supreme Court, 2002)
DeVoe v. State
935 P.2d 256 (Montana Supreme Court, 1997)
Majers v. Shining Mountains
750 P.2d 449 (Montana Supreme Court, 1988)
Springer v. Opsahl
744 P.2d 884 (Montana Supreme Court, 1987)
Somont Oil Co., Inc. v. Nutter
743 P.2d 1016 (Montana Supreme Court, 1987)
Morris v. Nationwide Insurance
722 P.2d 628 (Montana Supreme Court, 1986)
Farmers State Bank v. Imperial Cattle Co.
708 P.2d 223 (Montana Supreme Court, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
692 P.2d 460, 214 Mont. 131, 1984 Mont. LEXIS 1125, Counsel Stack Legal Research, https://law.counselstack.com/opinion/frank-l-pirtz-construction-inc-v-hardin-town-pump-inc-mont-1984.