Sudan Drilling, Inc. v. Anacker

2009 MT 14, 202 P.3d 778, 349 Mont. 42, 2009 Mont. LEXIS 13
CourtMontana Supreme Court
DecidedJanuary 21, 2009
DocketDA 08-0006
StatusPublished
Cited by3 cases

This text of 2009 MT 14 (Sudan Drilling, Inc. v. Anacker) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sudan Drilling, Inc. v. Anacker, 2009 MT 14, 202 P.3d 778, 349 Mont. 42, 2009 Mont. LEXIS 13 (Mo. 2009).

Opinions

[43]*43JUSTICE NELSON

delivered the Opinion of the Court.

¶1 Sudan Drilling, Inc. (Sudan), appeals from a summary judgment entered by the Eleventh Judicial District Court, Flathead County, in this action for foreclosure of a construction lien. We reverse and remand for further proceedings consistent with this Opinion.

¶2 We restate the issue as whether genuine issues of material fact preclude summary judgment.

BACKGROUND

¶3 On April 25, 2005, Sudan filed a complaint in the District Court to foreclose on a construction lien against property owned by Glen D. Anacker and Clarice M. Anacker. According to the complaint, the lien represents the balance due Sudan for digging the first of two wells on Anackers’ property. In the complaint, Sudan asked for $3,970 due under the lien, plus interest, attorney fees, and costs and disbursements.

¶4 The Anackers filed an answer in which they admitted having entered into a verbal contract with Sudan, under which Sudan was to drill a domestic water well on their property. They denied owing Sudan any money under the contract, however. As a first affirmative defense, the Anackers claimed the location in which Sudan dug the first well was in violation of both the septic setback terms of their agreement and state and local septic regulations requiring a 100 foot setback between a well and a neighboring septic drainfield. As a second affirmative defense, the Anackers claimed Sudan was advised of the correct location to drill the well before drilling operations commenced and is estopped from prevailing on its lien because it drilled in a location other than it was instructed and in breach of the verbal contract.

¶5 The parties deposed Glen D. Anacker; Marvin Sudan, the owner and president of Sudan; Chad Danielson, Sudan’s employee who drilled the wells; and James Battee, the Anackers’ excavating subcontractor who leveled out a pad for the well drilling equipment to sit on while the wells were being drilled. Based on the record, including those depositions, the Anackers moved for summary judgment. At the District Court hearing on that motion, Sudan requested that summary judgment instead be granted in its favor.

¶6 The District Court later issued a written order granting the Anackers’ motion for summary judgment and denying Sudan’s request for summary judgment. The court’s decision was based on two grounds: that the undisputed fact that the first well was not completed was [44]*44dispositive to defeat Sudan’s lien, and that the undisputed facts established that Sudan had breached its contract with Anackers to drill a domestic well in a workmanlike manner. The District Court directed the Clerk and Recorder of Flathead County to remove Sudan’s construction lien on the Anackers’ property from the public record. Sudan appeals.

STANDARD OF REVIEW

¶7 We review a district court’s ruling on a motion for summary judgment de novo, using the same criteria as does the district court under M. R. Civ. P. 56. Schuff v. Jackson, 2008 MT 81, ¶ 14, 342 Mont. 156, ¶ 14, 179 P.3d 1169, ¶ 14. Pursuant to M. R. Civ. P. 56(c), the judgment sought “shall be rendered forthwith if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” “A material fact is a fact that involves the elements of the cause of action or defenses at issue to an extent that necessitates resolution of the issue by a trier of fact.” Arnold v. Yellowstone Mountain Club, LLC, 2004 MT 284, ¶ 15, 323 Mont. 295, ¶ 15, 100 P.3d 137, ¶ 15 (internal quotation marks and brackets omitted). All reasonable inferences which may be drawn from the offered evidence must be drawn in favor of the party opposing summary judgment. Rosenthal v. County of Madison, 2007 MT 277, ¶ 22, 339 Mont. 419, ¶ 22, 170 P.3d 493, ¶ 22. Finally, summary judgment is an extreme remedy which should not be substituted for a trial on the merits if a controversy exists over a material fact. Mary J. Baker Revoc. Trust v. Cenex Harvest, 2007 MT 159, ¶ 17, 338 Mont. 41, ¶ 17, 164 P.3d 851, ¶ 17.

DISCUSSION

¶8 Do genuine issues of material fact preclude summary judgment ?

¶9 A person furnishing services or materials under a real estate improvement contract may attach and enforce a construction lien against the real estate for any unpaid part of the contract price. Sections 71-3-521 and -526, MCA. The contract price is the amount agreed upon by the contracting parties, increased or diminished by the price of change orders or extras, amounts attributable to altered specifications, and any breach of contract. Section 71-3-522(3), MCA. ¶10 The depositions filed in this case establish that Sudan and the Anackers entered into a verbal contract under which Sudan agreed to [45]*45drill a well on the Anackers’ property and the Anackers agreed to pay Sudan $21 per foot of well drilled. Before a well could be drilled, the Anackers’ excavation subcontractor, James Battee, excavated a roadway to the well’s future location and prepared a flat pad upon which the well-drilling equipment could sit. In his deposition, Battee stated he made the pad (otherwise described as a wide spot in the road) two to three weeks before the first well was drilled, at which time the location for the well was marked by a stake in the ground. A week or two before the well was drilled, the Anackers’ general contractor, Dave Christensen, notified Battee that the pad needed to be widened, and Battee widened it. Battee did not notice the stake when he widened the pad. Then, after Sudan partially completed drilling the first well, Glen Anacker noticed the well was too close to a neighbor’s drainfield. Anacker notified Christensen, who directed Sudan to abandon the first well and drill a second well in a spot further away from the drainfield. Sudan did so.

¶11 The District Court’s first rationale for granting summary judgment to the Anackers was that Sudan’s construction lien was invalid because it did not complete the first well. The court relied upon Durand v. Dowdall, 232 Mont. 347, 757 P.2d 1302 (1988), for the principle that a valid construction lien will not arise when the party claiming the lien failed to substantially complete the contract work.

¶12 Here, the verbal contract between Sudan and the Anackers required Sudan to complete one well for the Anackers. Sudan completed one well for the Anackers — the second well it drilled. As a result, we conclude the District Court’s first rationale for granting summary judgment for the Anackers is unfounded.

¶13 In addition, the depositions reveal a genuine issue of material fact as to whether the abandonment of the first well represented a change order or altered specifications in the contract, for which the Anackers are responsible or, instead, a breach of contract by Sudan when Sudan drilled in the wrong place, thereby eliminating its entitlement to a lien for that work. Chad Danielson, Sudan’s well driller, testified by deposition that he believed his boss Marvin Sudan told him where to drill the first well, but he also stated he asked “the operator that was operating the Cat” to confirm where the well should go. The Anackers claim Sudan or its employee should have relied only on information directly from them or their general contractor, Christensen, on where to drill the well.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. E. Holcomb
2025 MT 190 (Montana Supreme Court, 2025)
Sudan Drillings Inc. v. Anackers
2014 MT 72 (Montana Supreme Court, 2014)
Sudan Drilling, Inc. v. Anacker
2009 MT 14 (Montana Supreme Court, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
2009 MT 14, 202 P.3d 778, 349 Mont. 42, 2009 Mont. LEXIS 13, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sudan-drilling-inc-v-anacker-mont-2009.